This is a Performance Work Statement (PWS) for a drain line replacement project at the National Weather Service (NWS) Weather Forecast Office in Brownsville, Texas, dated August 7, 2026.
The project requires full replacement of the facility's sewage drain system, which has experienced numerous clogging and backups with documented breaks and buildup. The contractor must replace the drain line connecting the men's and women's restrooms, the kitchen drain line, and the main drain line from the building. Work must be executed as a turnkey, start-to-finish project with minimal interruption to the facility's 24/7 mission-critical operations. A critical requirement is constructing a temporary wall to subdivide the equipment room, allowing one computer room air conditioning (CRAC) unit to remain operational throughout the project duration. The contractor must perform comprehensive diagnostic testing including video inspection and mapping of all piping, replace cast iron piping with PVC pipe, and restore all affected areas including flooring, walls, pavement, landscaping, and fencing to original condition or better. The project encompasses work in multiple areas: restrooms (concrete breaking, floor tile and paint matching), kitchen (lateral replacement, floor tile color selection by government), corridor, electrical tech room (cubicle disassembly/reassembly and flooring replacement), equipment room (access flooring removal/reinstallation, equipment relocation, and HVAC rerouting), storage room (two cleanout replacements), and exterior work (50-foot main line with two cleanouts, HVAC equipment relocation, and lift station connection). The contractor must disconnect and reconnect all obstructions, document equipment conditions with photos/videos before disconnection, and comply with dust control measures.
The period of performance shall not exceed 120 calendar days from notice to proceed. The contractor is responsible for obtaining all licenses, permits, and fees, and must comply with the Davis-Bacon Act prevailing wage requirements. Weekly certified payroll records using Form WH-347 must be submitted. A detailed safety plan must be submitted within five days of award and finalized within five days of the post-award conference. Performance and payment bonds must be provided within ten calendar days of award, with a bid guarantee of at least 20 percent of the bid price. Key personnel include a project manager and onsite manager (which can be the same person), both designated as key personnel and requiring government approval for replacement. The contractor must provide weekly progress reports detailing work performed, labor hours by category, direct costs by line item, schedule status, and technical progress. All submittals, including project schedule (10 days from award), detailed construction schedule (30 days before onsite work), product specifications for piping and materials, permits, project photographs, red-line construction drawings (7 days after restoration completion), as-built drawings if changes are made (30 days from installation completion), and operations/maintenance manuals become government property. The contractor must provide a 5-year warranty on all workmanship and manufacturer's warranty documentation on all materials. Government contact for submissions is the Contracting Officer Representative (Jamie Moore, 816-343-8360, james.moore@noaa.gov), with additional site points of contact provided upon award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement Drain Line Replacement
BRO- Brownsville, TX 20 S. Vermillion Ave.
Brownsville, TX 78521
August 7, 2026
1.0General
1.1 Background:
This project is for the National Weather Service (NWS) Weather Forecast Office (WFO) in Brownsville, TX, (BRO). The main office requires full replacement of its sewage drain lines.
Numerous clogging and backups have occurred and during a recent cleaning, breaks as well as build up have been documented.
1.2 Objective:
Replace the sewage drain system to full functioning condition. NWS needs replacement of the drain line connecting the men’s and women’s restrooms, replacement of the drain line connecting the kitchen and replacement of the main drain line from the building. The NWS requests a turnkey start-to-finish project necessary to complete the replacement while ensuring minimal interruption to the facility’s 24/7 mission-critical operations. This includes building a temporary wall to allow the equipment room to remain operational throughout the duration of the project.
1.3 Applicable Documents
The Contractor must adhere to all current local prevailing wages, as mandated by the Davis-Bacon Act (DBA) of 1931. Other relevant documents, if requested, are specified in the Deliverables section (Section 8.0).
1.4 Value Engineering
NWS assumes a full drain line replacement, which requires slab removal/restoration or alternative access methods (e.g., below-grade tunneling). Quoters may propose alternative technical execution methods provided the proposed solution satisfies all functional, structural, and mission-continuity requirements outlined in this PWS. All proposed methods will be evaluated on a Pass/Fail basis against the Technical Acceptability factors in the solicitation.
2.0Specific Requirements/Tasks
The Contractor is responsible for all labor, tools, equipment, materials, supervision, management, sub-contractors, licenses and permits, site preparation, execution, and final restoration. It is Required that any contractor who will be submitting a quote as the Prime contractor, schedule a site visit and sign-in for physical inspection of existing conditions to ensure all offerors are quoting on the same scope of work. Due to the location of essential equipment, other means of restoration may be necessary (below grade tunneling) to reach the piping. If needed as-builts drawings are available on site for reference. The contractor will verify all piping dimensions, slope and grade. The NWS staff will notify the contractor of any recent issues at the site visit.
2.1 General Requirement
● Perform a full diagnostic testing of piping to include, video inspection, mapping and documentation of all findings (pre and final) per location and to include the full function of sewage lift station.
● Verify all dimensions, grades, pipe sizing, obstructions, cleanout locations and other elements necessary prior to starting the project.
● Replace cast iron piping with PVC pipe.
● Draft a detailed plan of action with schedule and present to NWS staff.
● Execute a full-system sewage drain replacement using industry standards.
● Construct a temporary wall to allow continuous operation of the equipment room through the duration of the project using one of the two computer room air conditioning (CRAC) units for cooling.
● Restore the facility and all affected areas- including flooring, walls, pavement, landscaping, fencing and/ or relocated equipment to their original condition or better.
● Prior to disconnecting any equipment, the contractor along with NWS will survey and test the existing equipment. After reviewing the equipment, the contractor will document any discrepancies found during the review. The contractor will submit a report identifying the discrepancies for NWS approval.
● Disconnect, disassemble, move and reconnect/replace all obstructions preventing access to the drain line piping. Mark locations of each item for reinstallation. Disconnected equipment can be stored onsite. Coordinate on-site location with NWS Staff.
● Reinstall and reconnect all equipment relocated in the execution of the work. Coordinate with NWS on specific locations of all equipment and wiring.
● Dust control: During construction erect barriers as necessary to maintain dust in the construction area. Any equipment not relocated cover for dust protection.
● Test new sewer piping to ensure proper slope and drainage.
● Test and verify operations of existing sewer grinder and lift station prior to connecting the new line.
2.2 Restroom Drain Line
● Replace cleanout in women’s restroom
● Remove and reinstall any obstructions necessary to replace the drain lines.
● Replace bathroom floor drains. Connect new drains into the sewer line
● Break concrete as necessary to access and replace drain lines. Men’s restroom, women’s restroom and storage room.
● Remove and replace Wye fittings where the bathroom branch connects to the main drain line
● When the new line is installed repair/replace any broken concrete
● Replace floor tiles in the bathroom floor. Match existing
● Paint bathroom. Color to match existing.
● Reinstall and connect bathroom fixtures to the new drain line.
● Restore the site to its original condition unless otherwise noted.
**Photos illustrate approximate path and location of drain lines**
Women’s Restroom
Women’s Sink
Men’s Restroom- Path of Drain Lines
2.3 Kitchen Drain Line
● Replacement included lateral connecting sink to the drain line. Work does not include replacing the drain line from the mezzanine.
● Replace cleanout located in the hallway
● Remove and reinstall any obstructions necessary to replace the drain lines.
● Break concrete as necessary to access and replace drain lines. Corridor, Ready Room, Elec
Tech Room. Remove walls as necessary to replace the main drain line.
● The Ready Room also serves as the storm shelter for the building. The construction of the walls and flooring may vary from elsewhere in the building. The contractor will verify the depth and thickness before breaking concrete floor or through wall as necessary.
● Remove and replace Wye fittings where the kitchen branch connects to the main drain line
● Remove and replace fitting where mezzanine lateral connects to the kitchen drain line
● When the new line is installed repair/replace any broken concrete
● Replace all of the kitchen floor tiles. The contractor will submit color samples to COR for determination.
● Reinstall or replace the section of carpet removed to replace the drain line. Match existing.
● Reinstall and reconnect any fixtures removed during replacement.
● When the new line is installed repair/replace any broken concrete
Kitchen and Equipment Room Drain Line
Kitchen and Equipment Room Drain Line
2.3 Main Drain Line
● Disconnect, relocate and store HVAC equipment determined to be within the path of the drain line. Prior to disconnection, contractors along with NWS will verify the operations of all HVAC equipment. Documents listing equipment and existing condition will be provided for signatures from both NWS Staff and contractor. Photos/ Videos will be taken to show function of equipment.
● Once replacement is completed all HVAC equipment will be returned to its original location. HVAC equipment will be reconnected and tested for operation.
● Storage Room: Replace two cleanouts in the storage room. Break concrete as necessary to replace the main drain line. Remove walls as necessary to replace the main drain line.
Remove and reinstall any obstructions necessary to replace the drain lines.
Storage Room
● Corridor: Break concrete as necessary to replace the main drain line. Remove walls as necessary to replace the main drain line. Remove and reinstall any obstructions necessary to replace the drain lines. Reinstall or replace the section of carpet removed to replace the drain line. Match existing.
Hallway
● Elec Tech Room - Break concrete as necessary to replace the main drain line. Remove walls as necessary to replace the main drain line. Remove and reinstall any obstructions necessary to replace the drain lines. Disassemble, store and reassemble existing cubicle furniture. Remove and replace existing flooring in the room. Match existing.
ET Shop
ET Shop
● Equipment Room:
● The equipment room is to remain operational through the duration of this project. The equipment room is cooled via two computer room air conditioning (CRAC) units. One of the units is in the path of the replacement but the other unit is to remain operational.
● Temporary Wall - To allow the equipment room to remain operational and protect the operating equipment, a temporary wall will need to be built to subdivide the equipment room into an “operational” side (where existing equipment will continue to run) and a “project” side (where the drain replacement work will occur).
o The Contractor shall provide all labor, materials, tools, equipment, and supervision necessary to complete the installation of the temporary wall.
o Pre-Construction & Prep
▪ Measure and mark the exact centerline of the temporary wall as agreed upon with the NWS.
▪ Protect existing flooring, walls, and furniture in the work zone using drop cloths, plastic sheeting, and masking tape.
o Framing & Installation
▪ Framing: Build a light-gauge metal stud frame spaced 16 inches on center.
▪ Surface Protection (Damage Prevention): Use sill sealer, foam tape, or a non-adhesive barrier between the temporary wall plates (top, bottom, and sides) and the existing finishes to prevent permanent damage.
▪ Anchoring: Secure the wall using non-destructive methods where possible (e.g., tension fitting, or minimal screw attachments into existing studs/joists that can be easily patched later). No heavy anchors shall be driven into floors.
▪ Drywall: Install ½ inch drywall on the “operational” side of the frame.
o HVAC Condensation Lines
▪ CRAC #2 will remain operational through the duration of the project. The condensate from the drain line from CRAC #2 and AHU #1-3 will need to be temporarily re-routed during the project and re-connected at the conclusion of the project.
o Removal
▪ At the conclusion of the project, the temporary wall will be completely removed and the equipment room is to be restored to its original state.
Equipment Room
● On the “Project” side, remove access flooring as necessary for replacement. Disconnect and relocate any wiring, cabling, conduits and electrical determined to be in the path of the replacement. Remove any HVAC equipment determined to be within the path of replacement. The equipment room has one (1) 10-ton computer room air conditioner in the path of the new line. Relocate any server cabinets determined to be in the path of replacement. The equipment room has one server cabinet in the path of the new line. NWS will identify cabling locations for disconnection and reinstallation. (Reference photos provided)
● Raised access flooring will be reinstalled upon completion of the drain line replacement.
Wiring, cabling, conduits and electrical shall be reconnected to their original location unless otherwise determined by NWS. NWS will make the connection to the servers in the equipment room. Coordinate timing with site POC. Cabinets will be reinstalled in their original location unless otherwise determined by NWS. HVAC equipment will be returned to its original location.
● Replace connection from operations drain line into new sewer line.
Equipment Room- (Drain line path under equipment)
● Exterior Main Line – The exterior main line runs approximately 50 ft from the building.
Replace two exterior cleanouts. One cleanout is by the condensing unit and the other is by the A/C unit. Relocate, store and reinstall any HVAC equipment determined to be within the path of the replacement. There is one condensing unit and one A/C unit in the path of the existing line. The contractor will determine if any additional equipment needs to be relocated. Excavate from the building to the manhole as necessary to replace the drain line.
Backfill excavation to rough grade.
Rear of Building
● Connect the new sewer drain line into the existing lift station.
Sewage Lift Station
Sewage Lift Station
● Repair/adjust sewer grinder and lift station operations as necessary to allow for a new drain line.
● If the new drain line does not connect into the existing manhole penetration, then the contractor will cap the existing penetration.
● When the new line is installed repair/replace any broken concrete
2.5.3 -The Contractor shall repair to the satisfaction and approval of the Contracting Officer Representative all Grass Areas, Shrubs, Plants, Sidewalks, Sprinkler Systems, Asphalt Parking Areas, and etc. when damaged by the Contractor during construction.
2.5.4 - All disputes regarding "Contractor Caused" damage shall be documented in writing and with digital pictures by the Contractor. The Contractor shall send all such documentation to the Contracting Officer for review and final decision.
2.6 Licenses, Permits and Fees
2.6.1 - The Contractor shall be responsible for obtaining and paying for all licenses, permits, and fees required for completing all required work.
2.7 Safety Plan
2.7.1 - The Contractor shall observe and institute all applicable OSHA safety requirements, regulations and procedures to prevent accidents and injuries to both Contractor and Government employees and shall comply with 40 CFR 1926 Subpart M for fall protection requirements, PPE, LOTO etc.
for all workers on this project. It is the responsibility of the contractor to ensure safe work practices and compliance.
2.7.2 - The Contractor shall designate one person as Safety Coordinator for purposes of communication between the Contractor and the National Weather Service. The safety coordination can also be the contractor project manager.
2.7.3 - The Contractor shall provide a Safety Plan and Procedure to protect employees from being injured on the job site. Submit a draft plan for review within five (5) days of award and finalized plan for approval no later than five (5) days after the Post Award Conference.
3.0 Contractor Personnel
3.1 Qualified Personnel
The Contractor shall provide qualified personnel to perform all requirements specified in this.
3.2 Continuity of Support
The Contractor shall ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor shall ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor shall provide e-mail notification to the Contracting Officer’s Representative (COR) prior to employee absence.
Otherwise, the Contractor shall provide a fully qualified replacement.
3.3 Designated Contractor Personnel
The following Contractor personnel are designated for this requirement. Note: The Government may designate additional Contractor personnel at the time of award.
● Project Manager – Must be able to represent the contractor in regards to contract requirements.
● Onsite Manager – Must be at the project location whenever work is being performed.
These positions can be occupied by the same person but must be able to fulfill both position roles.
3.4 Project Manager
The Contractor shall provide a Project Manager who shall be responsible for all Contractor work performed under this PWS. The Project Manager shall be a single point of contact for the Contracting Officer and the COR. The name of the Project Manager, and the name(s) of any alternate(s) who shall act for the Contractor in the absence of the Project Manager, shall be provided to the Government as part of the Contractor's proposal. The Project Manager is further designated as Key by the Government. During any absence of the Project Manager, only one alternate shall have full authority to act for the Contractor on all matters relating to work performed under this contract. The Project Manager and all designated alternates shall be able to read, write, speak and understand English. Additionally, the Contractor shall not replace the Project Manager without prior approval from the Contracting Officer.
3.4.1 - The Project Manager shall be available to the COR via telephone between the hours of 8:00am and 4:00pm CST, Monday through Friday, unless otherwise approved by the COR, and shall respond to a request for discussion or resolution of technical problems within 2 business days of notification.
3.5 Employee Identification
3.5.1 - Contractor employees visiting Government facilities shall wear an identification badge that, at a minimum, displays the Contractor name, the employee’s photo, name, clearance-level and badge expiration date. Visiting Contractor employees shall comply with all Government escort rules and requirements. All Contractor employees shall identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times.
3.5.2 - Contractor employees working on-site at Government facilities shall wear a Government issued identification badge. All Contractor employees shall identify themselves as Contractors when their status is not readily apparent (in meetings, when answering Government telephones, in e-mail messages, etc.) and display the Government issued badge in plain view above the waist at all times.
3.6 Employee Conduct
Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, etc.) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees present a professional appearance at all times and that their conduct shall not reflect discredit on the United States or the Department of Commerce. The Project Manager shall ensure Contractor employees understand and abide by Department of Commerce established rules, regulations and policies concerning safety and security.
3.7 Removing Employees for Misconduct or Security Reasons
The Government may, at its sole discretion (in coordination with the Contracting Officer where practical), direct the Contractor to remove any Contractor employee from NOAA facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
4.0 Compliance
The Contractor shall comply with all local, state, and Federal environmental, health, and safety regulations while conducting this work. In addition, the Contractor shall ensure that all work is in compliance with the applicable codes and be responsible for all licenses, permits and fees required to complete this project.
All work contained in this Performance Work Statement shall be completed in a professional and workmanlike manner, per manufacturers' specifications and requirements and in accordance with industry standards and practices, and in accordance with the latest edition of Local, State and Federal regulations.
4.1 Security
Contractor access to classified information is not currently required under this PWS. However, contractors shall sign in each morning and sign out each evening at each WFO.
4.2 Period of performance
The period of performance for this contract shall not exceed 120 calendar days from the notice to proceed.
4.3 Place of Performance
The primary place of performance will at 20 S. Vermillion Avenue Brownsville, TX 78521
4.4 Hours of Operation
It is NWS intention to mostly vacate the building during construction. Due to the critical nature of the replacement the contractor is authorized to work hours that will minimize down time. Working hours will be identified in the contractors’ weekly reports. NWS staff will be available Monday – Friday 8am – 4pm excluding Federal Holidays. The contractor is not required to provide service on Federal Holidays.
New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving, and Christmas.
4.5 Post Award Conference
The Contractor shall attend a Post Award Conference with the Contracting Officer and the COR no later than 10 business days after the date of award. The purpose of the Post Award Conference, which will be chaired by the Contracting Officer, is to discuss technical and contracting objectives of this contract and review the Contractor's draft project plan. The Post Award Conference will be held via teleconference.
4.6 Progress Reports
The Project Manager shall provide a weekly progress report to the Contracting Officer and COR via electronic mail. This report shall include a summary of all Contractor work performed, including a breakdown of labor hours by labor category, all direct costs by line item, an assessment of technical progress, schedule status, any travel conducted, any Contractor concerns or recommendations for the previous reporting period and look ahead to the following week.
4.7 General Reporting Requirements
The Contractor shall provide all written reports in electronic format with read/write capability using applications that are compatible with NOAA workstations (e.g. Windows XP and Microsoft Office Applications).
4.8 Payment and Performance Bonds
The Contractor shall secure and provide executed Performance and Payment Bonds (in accordance with FAR 52.228-15). These original documents must be submitted to the Contracting Officer for review and approval within ten (10) calendar days after receipt of the Notice of Award. No on-site work or physical mobilization may occur, and the formal Notice to Proceed (NTP) will not be issued, until all required bonds and insurance certificates are approved by the Government.
4.9 Davis-Bacon Act
This project is strictly subject to the Davis-Bacon Act (FAR 52.222-6). The Contractor and all subcontractors shall pay all mechanics and laborers prevailing wages and benefits in accordance with the applicable Department of Labor (DOL) Wage Determination incorporated into this contract. The Contractor is required to submit weekly certified payroll records (using Form WH-347 or equivalent) to the Contracting Officer’s Representative (COR) for all weeks in which contract work is performed.
4.10 Bid-Gurantee
In accordance with RFO FAR 28.101-1, bid guarantees must be required whenever a performance bond or a performance and payment bond is required. The bid guarantee amount must be at least 20 percent of the bid price but must not exceed $3 million. This project is subject to RFO FAR 52.228-1.
5.0 Government Furnished Resources
5.1 Resources
The Government will not furnish any resources to the Contractor in support of this contract.
5.2 Exclusions
Unless otherwise indicated elsewhere in this PWS, the Government will provide no data, materials, equipment and/or services to the Contractor. Any and all research required to fulfill the PWS described herein, shall be the responsibility of the Contractor. The Government retains the right to request the Contractor to acquire additional information on behalf of the Government
6.0 Contractor Furnished Property
The Contractor shall furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract. Contractor will provide their own porta potty during the work
7.0 Government Acceptance Period
The COR will review deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the COR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
7.1 The COR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the COR of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
7.2 The COR will have 5 business days to review deliverables and make comments. The Contractor shall have 5 business days to make corrections and redeliver.
7.3 All other review times and schedules for deliverables shall be agreed upon by the parties based on the final approved Project Plan. The Contractor shall be responsible for timely delivery to Government personnel in the agreed upon review chain, at each stage of the review. The Contractor shall work with personnel reviewing the deliverables to assure that the established schedule is maintained.
8.0 Deliverables
NUMBER
DELIVERABLE /
EVENT REFERENCE QUANTITY DUE BY
DISTRIBUTION
Post Award Conference
PWS 4.5 1 Each Within ten
(10) days of award
CO and COR
Project Safety Plan Draft & Final
PWS 2.7 1 Each
Within 5 days of award and Final within 5 days of Post Award Conference
CO and COR
Sexual Assault and Sexual Harassment Training
NAM
1330-52-222-
1 per contractor employee
Within 30 days of award
CO and COR
Security Processing Requirements for Contractor/ Subcontractor Personnel Working on a Department of Commerce (DOC) Site
CAR
1352.237-71
1 per contractor employee
As determined COR
5 Submittals PWS 10.5 As required As required for approval
CO and COR
Payment & Performance Bonds
PWS 4.8 1 Each
Within 10 days after receipt of Award
CO/CS
7 Bid Gurantee PWS 4.10 1 Submitted with quote
CO/CS
8 Payrolls PWS 4.9 Weekly Weekly CO and COR
9 Progress Reports PWS Weekly Weekly CO & COR
9.0 Project Final Acceptance
9.1 Walk-Through
Upon substantial project completion, the Contractor, COR and NWS Staff shall conduct a joint walkthrough inspection. The purpose is to identify any unfinished work, defects, or deficiencies to be corrected prior to Final Completion. A formal Punch List will be generated during the walkthrough, documenting items. This list will be signed by both parties and will include a mutually agreed-upon deadline for completion.
9.2 Final Completion
After verification that all punch list items are resolved, the COR will sign off the completion and request the final invoice initiating payment and close out.
10.0 Additional Information
10.1 Guidelines
The Project shall follow the guidelines stated in the PWS, including, but not limited to, the following:
● The contractor shall be responsible for restoring the work site to its original condition.
● All work contained in this Performance Work Statement shall be completed in a professional and workmanlike manner, per manufacturers' specifications and requirements and in accordance with industry standards and practices, and in accordance with the latest edition of Local, State and Federal regulations
● All Offerors are strongly encouraged to attend a site visit to inspect all proposed replacement work and to acquire all necessary site information to properly prepare their bid proposal. Failure of the Contractor to attend a site visit and acquire all necessary site information to properly prepare their proposal shall not be acceptable cause to justify a later request for additional costs after Contract Award. All technical questions must be in writing and sent to the Contracting Specialist before the Question due date that is identified in the Request for Quote (RFQ).
● The Contractor shall acknowledge that only written inquiries and responses shall be deemed official.
Any verbal guidance provided on-site is considered unofficial and non-binding unless formally documented. Please ensure all questions, including those arising during site visits, are submitted in writing for a formal response. Point of contact information for questions and quotes will be provided in the RFQ.
10.2 Government Contact
The Contracting Officer Representative (COR) will serve as the Government’s point of contact for all submissions. Contact information for the COR as well as site Points of Contact (POC’s) will be provided upon award of the contract.
Jamie Moore; Contracting Officer Representative, 816-343-8360; james.moore@noaa.gov
Jorge Negrete, Facilities Engineering Technician, 830-401-2055; jorge.negrete@noaa.gov
Cesar Ochoa, Electronic Systems Analyst 956-245-3356; cesar.ochoa@noaa.gov
10.3 Documents
The Government does not warrant that any documents provided as attachments are free from discrepancies, ambiguities, errors, omissions, or changing conditions. It is the responsibility of the Contractor to confirm existing conditions, dimensions, obstructions and resolve discrepancies.
10.4 Warranty
The Contractor shall provide documentation for the manufacturer’s warranty on all piping and material used. Contractor will provide a 5 year warranty on all workmanship related to scope of work.
10.5 Submittals
Submittal Process: Please ensure the specific product selection is highlighted and clearly shown. The Contractor may not proceed with work or procure materials until the Government has reviewed and approved these submittals. The government will have five (5 days) to review submittals.
Submittal Register: The contractor shall prepare and maintain a submittal register and provide a copy to the COR.
The Contractor will be responsible for sending the following submittals.
Project Schedule – 10 days from Award to coincide with Per Construction conference
Detailed Construction Schedule – 30 days from performing work on site.
Product Specifications – Piping, wye connections, tile flooring and carpet.
Permits as required – Prior to starting onsite construction
Project photos (4 to 5) showing work are requested to be included in the weekly report
Red line construction drawings (digital and hard copy) – 7 days after completing restoration
As Built Drawing – If drain line slope or location is changed contractor will provide as built drawings (digital and hard copy) reflecting the changes 30 days from completion of the install
Operations and Maintenance Manuals – Upon completion of work
Warranty – Upon completion of work
***All submittals shall become the property of the U.S. Government***
End of Performance Work Statement