This Performance Work Statement (PWS) outlines construction services for the Naval Surface Warfare Center Dahlgren Division (NSWCDD) at multiple locations including Dahlgren, VA, Pumpkin Neck Annex, Wallops Island, and the Naval Observatory in Washington, DC. The contract requires the contractor to provide comprehensive maintenance, sustainment, repair, and minor construction services, with complex work involving multiple disciplines and coordination with Architect-Engineer contractors.
Key requirements include joint project scoping, field surveying, soil and hazardous material sampling, engineering analysis, energy computations, and providing operation and maintenance support information. The contractor must comply with Navy and local instructions, building codes, and safety regulations. Work will be performed through task orders issued as Firm-Fixed-Price contracts, using either Best Value Tradeoff or Lowest Price Technically Acceptable selection processes. Mandatory requirements include a Program Manager with at least 10 years of experience, ability to access NSWCDD Base, a facility within 100 miles of Dahlgren, VA, and maintaining all necessary trade certifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Labor Category Min Quals - Construction IDIQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT
C.1 GENERAL REQUIREMENTS – CONSTRUCTION SERVICES
C.1.1 SCOPE OF SERVICES
C.1.1.1 The Contractor shall provide all management, labor, material, equipment, transportation, supervision, and environmental and quality controls, to accomplish simultaneous maintenance, sustainment, repair, and minor construction projects at the following locations: Naval Surface Warfare Center Dahlgren Division (NSWCDD) and occupying tenants; Pumpkin Neck Annex Explosive Experimental location in King George, VA; Surface Warfare facilities at Wallops Island on the Eastern Shore, VA; and NSWCDD facilities located at the Naval Observatory in Washington, DC.
C.1.1.2 In addition to standard maintenance, sustainment, repair, and minor construction, the following are considered within the scope of this contract:
a) Joint scoping of project requirements between the Contractor and NSWCDD Government to jointly identify project requirements for individual Task Orders.
b) Field surveying of sites to document existing conditions (e.g. utilities, grading, sidewalks, etc.), and mapping of new site conditions required to update Geographic Information System (GIS).
c) Soil boring sampling at potential work sites; analyzing the samples and providing test reports to the Government in determining soil-bearing capacity of a given site.
d) Sampling and testing of potential existing hazardous construction materials (e.g. lead paint, flooring mastic, pipe insulation, etc.). Providing test reports to the Government documenting materials sampled.
e) Performing and providing engineering analysis and evaluations to determine the structural or electrical capacity to support mission equipment.
f) Providing energy computations for infrastructure solutions including: energy or thermal performance of wall and roof systems; projecting energy performance of new systems (e.g. new boiler, air handling unit (AHU), hot water heater, etc.)
C.1.1.3 Work performed under this contract will be complex in nature and require multiple disciplines working simultaneously to include coordination with Architect-Engineer (A-E) Contractors as necessary. All such work shall be accomplished in strict accordance with all applicable Navy and local instructions, processes, and procedures and applicable building and life safety code requirements.
C.1.2 HOURS OF OPERATION
Normal working hours at all locations are Monday through Friday, 0600 to 1700. Work shall not occur outside those hours unless previously approved by the Contracting Officer or specified in a Task Order. In the event that Government testing schedules interfere with the Contractor’s planned work schedule, and that interference will cause a delay in schedule or increase in price, the Contractor shall notify the Contracting Officer immediately.
C.2 TASK ORDER PROCESS
C.2.1.1 ORDERING PROCEDURES
1.1. All subsequent Task Orders under this Multiple Award Construction Contract (MACC) will be awarded as Firm-Fixed-Price (FFP). The Government will utilize either a Best Value Tradeoff or Lowest Price Technically Acceptable (LPTA) process in award decisions as deemed appropriate by the Government for each individual Task Order. The Contracting Officer may decide to award a non-competitive Task Order after consideration of:
1. Contract minimums
2. Urgency of requirement
3. Capacity to perform
C.2.1.2 For competitive Task Orders, the Contracting Officer will issue a Task Order Proposal Request (TOPR) to the MACC once construction projects are identified. The TOPR will include all specifications necessary for the Contractor to adequately bid on the work, as well as the disclosure of magnitude as required by FAR 36.204.
C.2.1.3 A site visit will be scheduled as necessary to review and clarify the requirements of the TOPR, verify existing conditions, and obtain whatever measurements and information are necessary to develop a complete and accurate Task Order Proposal (TOP).
C.2.2 CONTRACTOR PROPOSALS
An acceptable TOP shall consist of the following:
C.2.2.1. Cover Sheet: Each TOP cover sheet shall include contract number, project number, project title, contact information for the Contractor, performance period, assumptions, exceptions, and the date to which the proposal will be valid. At a minimum each proposal shall be valid for 120 calendar days unless a longer period is requested in the RFP.
C.2.2.2 Price: An electronic copy of the Contractor’s pricing, with sufficient data to substantiate pricing (data other than certified cost or pricing, ref. FAR 52.215-20 Alt IV). The Government reserves the right to request additional pricing information after receipt and evaluation of proposals.
C.2.2.3 Project Schedule: Each TOP shall include a brief critical path schedule, taking into account the major work elements, mobilization, material delivery times, anticipated weather delays, anticipated range delays and final inspection. The proposed timeline should be of sufficient detail to demonstrate that the Offeror can meet the Governments proposed Period of Performance (PoP). A brief narrative of how the contractor plans to accomplish to meet the project objective, and understanding of the PWS shall also be included.
C.2.3. PERIOD OF PERFORMANCE
If the Government has a maximum PoP it will be stated in the TOR. If not, the Contractor can propose a PoP using the brief critical path schedule. The PoP shall start on the TO award date.
The calculated PoP is made up of the following:
• Pre-Construction Period: Not more than 30 calendar days. Time allotted to the Contractor to submit insurance and bonding information, submission of preconstruction submittals required by specifications, and onsite mobilization.
• Physical Construction: Varies by TO. Time allotted to the Contractor to complete all construction activities required by the TO.
• Project Closeout: Not more than 30 calendar days. Time allotted to the Contractor to prepare all project close out submittals and submit application for final payment.
C.3 COMMENCEMENT OF WORK
C.3.1 TOs will be issued by the Contracting Officer using the Department of Defense (DD) Form 1155, Order for Supplies and Services. Each TO will include the following information:
• Date of Task Order;
• Contract Number and Task Order Number;
• Item Number, description, material submittal requirements, quantity and unit prices for items and total;
• Task order price and delivery or performance date;
• Accounting and appropriation data;
• Liquidated damage, if any; and;
• Any statement of work, drawings or other pertinent data.
C.3.2. The Contracting Officer will issue Notice to Proceed (NTP) with the contract award unless otherwise noted within the contract document. Prior to starting any construction activities all pre construction submittals must be approved by the government. In rare circumstances, on projects deemed emergencies, the Contracting officer may issue verbal direction prior to the issuance of the written TO. In those circumstances, the NTP shall be the date the Contractor received the verbal NTP from the Contracting Officer with written notification to follow with seventy-two (72) hours, which represents the commencement date.
C.4 PROJECT REQUIREMENTS
C.4.1 Requirements
Each Task Order (TO) will specify the project requirements. For all TOs, the Contractor shall::
a) Procure all construction equipment, materials, and documentation necessary for timely completion of projects. The Contractor shall maintain all certification and re-certification equipment paperwork; inspection records (QA/QC form filled out by Government TPOC to inspect prior to small projects, attached to SR ticket); and permits and licenses for heavy equipment operation.
b) Provide a project schedule at the beginning of each Task Order. A Government approved schedule is required prior to commencing work on any project. The Contractor shall be required to maintain the construction schedule throughout the duration of the project and adjust the schedule accordingly based on any project delays or efficiencies incurred throughout the course of the project.
c) Conduct a site visit prior to commencing work in order to verify existing conditions;
coordinate with NSWCDD/NAVFAC to confirm location and type of existing utilities at buildings or sites that may be impacted by construction work.
d) Regularly inspect all work to ensure it is in accordance with all project requirements, design documents, and safety requirements.
e) Obtain all permits and regulatory approvals required to perform work (ex: Virginia
Department of Environmental Quality, VDEQ).
f) Operation and Maintenance Support Information (OMSI): Provide training to the
Government on operating and maintaining all critical systems. The Contractor shall submit to the Government all Operation and Management (O&M) manuals at the conclusion of each Task Order.
C.4.2 REGULATIONS
C.4.2.1 All work performed under this contract shall be performed following applicable Government plans, standards, policies, and processes. The Contractor’s activities shall conform to the systems test and operations environment and standards including all updates, improvements, and additions to these process documents made over the life of the contract. The Contractor shall use the Department of Defense (DoD) Unified Facilities Criteria (UFC) for facilities and infrastructure construction and modification. All documentation shall be developed within the software environment specified by the Government, Microsoft Office toolset and other specific tools and environments as stipulated in each Task Order. Deviations from these processes, policies, and procedures are not authorized without advance approval by the COR.
C.4.2.2. All projects under this contract shall comply with the most recent edition of applicable federal, state, and local laws, codes, and regulations including but not limited to the following (any exception must be approved in writing by the Contracting Officer):
1. OPNAVINST 5100.23 (5 JUN 2020)
2. OPNAVINST 5100.27 (02 MAY2008)
3. OPNAVINST 5090.1 (25JUN 2020)
4. NAVSEA S0420-AA-RAD-010 (19 JUL 2007)
5. NAVFAC P-307 (JAN 2025)
6. NAVSUP Publication 538 (01 APR 2012)
7. NSWCDDINST 5100.1F (2 May 2023)
C.4.2.3. The Contractor shall comply with the requirements of NAVSEA and NSWCDD instructions / manuals regarding performance in Government facilities.
C.4.3 Contractor Personnel
The Contractor shall employ a sufficient number of qualified personnel to adequately perform and oversee all work under this contract. When work is performed at any site, the assigned Lead (i.e. Superintendent, Supervisor, Foreman, etc.) or an appointed alternate shall be available as a liaison for the Government. Any appointed alternate shall be authorized to act on behalf of the contractor.
C.4.4 Employee Equipment
Contractor shall provide all required Personal Protective Equipment (PPE) and any special equipment required for safe and timely completion of projects. Certain Safety items will need to be approved by NSWCDD Base Safety prior to use (example: safety harness for fall protection).
C.4.5 Employee Requirements
The Contractor shall ensure that the employees and Sub-contractor employees have current, valid licenses and certifications necessary to perform their functions. Any cost or time associated with obtaining licenses or certifications shall be at the Contractor’s expense. Training necessary to ensure that personnel performing under this contract maintain the knowledge and skills to successfully perform the required functions is the responsibility of the Contractor. The Contractor shall ensure manufacturer certified maintenance personnel perform maintenance and repair on mechanical and electrical critical systems in accordance with this Performance Work Statement (PWS).
C.4.6 Employee Conduct
The Base Commander has authority to refuse access to any person working under this contract for reasons of misconduct, security, or if found to be or suspected to be under the influence of alcohol, drugs, or any other incapacitating agent (ref. 18 U.S.C.1382 (1972)). Assignment, transfer, and reassignment of Contractor personnel shall be at the discretion of the Contractor.
However, when the Government directs, the Contractor shall remove from contract performance any person who endangers life, property, or national security through improper conduct. All Contractor personnel engaged in work while on Government property shall be subject to the Standards of Conduct contained in SECNAVINST 5370.2J. All persons engaged in work while on Government property shall be subject to search of their persons (no bodily searches) and vehicles at any time by the Government, and shall report any known or suspected security violations to the appropriate Security Department.
C.4.7 Employee Required Training
The Contractor shall have personnel certified in Hazard Communication (HAZCOM).
C.4.8 Mandatory Requirements
All Mandatory Requirements shall be maintained throughout the life of the Contract. The mandatory requirements are as follows:
Requirement 1: Program Manager must have a minimum of Ten (10) years of program management experience which includes both technical and administrative aspects of Government contract performance, providing contract data deliverables, and having oversight of contract schedule and cost. Five (5) years of experience managing Federal Government programs/contracts. Experience with administrative oversight of contractual matters and serving as a liaison between the Customer Representative and corporate management. Experience managing services simultaneously while supporting many projects. Experience organizing resources to support many concurrent activities. Experience ensuring that all activities conform to the terms and conditions of the contract.
Requirement 2: Must be able to access NSWCDD Base through the Pass and ID Office.
Requirement 3: Facility Location: The Prime Contractor’s primary facility providing support to this requirement must be located within 100 miles of NSWCDD in Dahlgren, VA.
Requirement 4: Must have and maintain all necessary trade certifications required to perform all work under this PWS.
C.5 Contract Data Requirements List (CDRL)
C.5.1. CDRL A001 – CONTRACTOR’S PERSONNEL ROSTER
Within ten business days of Task Order issue, the Contractor shall submit a list of all employees working on the project to the Contracting Officer. This list shall include each employee's name, work assignment, and confirmation of a Secret level security clearance. Changes to the personnel list shall be submitted at least ten business days in advance. In emergency situations and cases of adverse actions where ten business days’ notice is not possible, the Contractor shall submit the required information regarding the change in writing to the Contracting Officer Representative (COR) not later than 24 hours after the replacement employee is on board.
C.5.2. CDRL A002 – HAZARDOUS MATERIALS MANAGEMENT PROGRAM
(HMMP) PLAN
The Contractor shall submit a Hazardous Material Management Plan (HMMP) as addressed in paragraph 2.2 of Section 01010.
C.5.3. CDRL A003 – MONTHLY STATUS REPORT
Contractor shall provide a Monthly Status Report for each project in which the support was provided. The report shall discuss major impacts, issues, and steps for remediation of issues, proposals to improve operational efficiencies, effectiveness, quality, or the customer experience.
C.5.4. CDRL A004 –INTEGRATED PROGRAM MANAGEMENT DATA AND
ANALYSIS REPORT (IPMDAR)
The Contractor shall develop a Integrated Program Management Data and Analysis Report (IPMDAR) at the Task Level/Summary and for each Task Order Project Requirement. The IPMDAR shall be signed by the Contractor (to include signature by Contractor’s Element-Level Manager), Government TPOC, and the Government Contracting Officer prior to commencing work on any project. The signed IPMDAR shall be provided electronically to the Contract Specialist, COR, Alternate Contracting Officer Representative (ACOR), and the appropriate Government TPOC within ten calendar days after task order performance start date or modification which affect the Level of Effort (LOE) or Dollar Ceiling.
C.6 Construction Wage Rate Determination
Construction Wage Determination(s) shall be current and site specific to each order and incorporated at the time the order is placed.
C.7 SAFETY
C.7.1 SAFETY
C.7.1.1 The Contractor shall comply with the requirements of NSWCDD, Department of the Navy (DON), and DOD safety policies and practices currently in force and all subsequent revisions. Established policies, directives, and guidance relating to safe operating practices and personnel safety are mandatory and shall be complied with at all times. The Contractor shall monitor and observe all activities and personnel to ensure strict adherence and compliance to applicable standard operating procedures and safety procedures. The Contractor shall observe all applicable technical, safety, and policy requirements as applies to the handling of hazardous materials.
C.7.1.2 The Contractor shall address and comply with all applicable workplace and work environment conditions for compliance with the intent and letter of Federal, State, local and DoD Occupational Safety and Health laws and regulations, policies, and practices.
C.7.1.3 All operations are subject to DOD/DON/NSWCDD safety inspections. The Contractor shall support NSWCDD annual safety and environmental facility audits and data collection efforts. The Contractor shall be responsible to correct any deficiencies noted during a safety inspection of the project site
C.7.2 ENVIRONMENTAL AND HAZARDOUS MATERIALS HANDLING
C.7.2.1 The Contractor, suppliers, and Sub-contractors shall comply with all certification, licensing, and training requirements for all federal, state, and local laws and regulations with respect to the handling and disposal of hazardous materials.
C.7.2.2 The Contractor shall create a Hazardous Material Management Plan (HMMP) (CDRL A002) at locations where the Contractor disposes of hazardous materials such as batteries;
fluorescent tubes, caulking tubes, and refrigerant. Contractor shall utilize hazardous materials collection points or Government collection centers for discarded hazardous material.
C.7.2.3 Asbestos and lead‐based paint assessments may be required on this contract to determine the presence of hazardous material during demolition or at utility points of connections. Work on and around waterfront structures, including under deck and underwater, and work in confined spaces may be required on this contract. The Contractor shall be able to accept work that involves asbestos, lead paint, Poly‐Chlorinated Biphenyls (PCBs), and other hazardous materials, work on and under waterfront structures, and in confined spaces.
C.8 SECURITY
C.8.1 Portable Electronic Devices
C.8.1.1 Non-Government and personally owned portable electronic devices (PEDs) are prohibited in all NSWCDD buildings with the exception of personally owned cell phones which are authorized for use in spaces up to and including Controlled Access Areas. The Contractor shall ensure the onsite personnel remain compliant with this PED policy. NSWCDD instruction defines PEDs as the following: any electronic device designed to be easily transported, with the capability to store, record, receive or transmit text, images, video, or audio data in any format via any transmission medium. PEDs include, but are not limited to, pagers, laptops, radios, compact discs, and cassette players/recorders. In addition, this includes removable storage media such as flash memory, memory sticks, multimedia cards and secure digital cards, micro-drive modules, ZIP drives, ZIP disks, recordable CDs, DVDs, MP3 players, iPad, digital picture frames, electronic book readers, kindle, nook, cameras, external hard dish drives, and floppy diskettes.
C.8.1.2 Personal Wearable Fitness Devices (PWFDs) marketed primarily as fitness or sleep devices are allowed in all Navy spaces, if they are compliant with NAVADIN 216/15, where collateral non-Sensitive Compartmented Information (SCI), classified information is processed, stored, or discussed up to and including SECRET. The user must ensure the PWFD is compliant with all requirements in NAVADMIN 216/15, Cyber Hygiene Authorization to use Personal Wearable Fitness Devices (e.g., FitBit, Jawbone UP, etc.) in Navy Spaces, dated 14 September 2015 and register PWFD in the NSWCDD Fitness Device Tracker.
C.8.1.3 Personnel requiring the use of Medical Portable Electronic Devices (MPEDS) must submit Form NSWCDD 5239/4 for SCIF authorization to the SCIF authorizations to the Special Security Officer (SSO). For Special Access Program Facility (SAPF) authorizations, follow the guidance provided by the Government Special Access Program Security Officer (GSSO).
Authorizations for use in SAPFs that are co-utilized within NSWCDD SCIFS require coordination between both the GSSO and SSO. For authorizations to use MPED in Collateral Classified spaces, submit form to the Special Programs Branch, Code 1053.
C.8.1.4 PEDs belonging to an external organization shall not be connected to NSWCDD networks or infrastructure without prior approval from the NSWCDD Information Assurance and Compliance Branch. This approval will be granted using the TARIS form and action tracker process.
C.8.1.5Personally owned hardware or software shall not be connected or introduced to any NSWCDD hardware, network, or information system infrastructure.
C.8.2 Operations Security (OPSEC)
C.8.2.1 Contractor personnel shall follow OPSEC concepts and principles in the conduct of this requirement to protect critical information, personnel, facilities, equipment, and operations from compromise. These OPSEC requirements will be in effect throughout the life of the procurement from award through the conclusion of services at the end of the period of performance (PoP) or other procurement termination. The Contractor must immediately notify the Government upon the discovery of any nonconformance with the OPSEC Plan.
C.8.3 Privacy Program Training
Privacy training is mandatory for all NSWCDD personnel (military, civilian, and Contractor) and must be completed annually. Total Workforce Management Services (TWMS) is the official database for workforce training and is the tool for taking and recording Privacy Act training.
The Contractor is responsible for ensuring individual annual privacy training requirements are met.
C.9 PRIVACY INFORMATION
Work under this Contract may require that personnel have access to Privacy Information.
Contractor personnel shall adhere to the Privacy Act, Title 5 of the U.S. Code Section 552a, FAR 52.224-2 Privacy Act, and applicable agency rules and regulations.
C.10 NON-PERSONAL SERVICES/INHERENTLY GOVERNMENT FUNCTIONS
(a) The Government will neither supervise Contractor employees nor control the method by which the Contractor performs the required tasks. The Government will not direct the hiring, dismissal or reassignment of Contractor personnel. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual Contractor employees. It shall be the responsibility of the Contractor to manage its employees and to guard against any actions that are of the nature of personal services or give the perception that personal services are being provided. If the Contractor feels that any actions constitute, or are perceived to constitute personal services, it shall be the Contractor's responsibility to notify the Contracting Officer immediately in accordance with FAR 52.243-7 Notification of Changes.
(b) Inherently-Governmental functions are not within the scope of this contract. Decisions relative to programs supported by the Contractor shall be the sole responsibility of the Government. The Contractor may be required to attend technical meetings for the Government;
however, they are not, under any circumstances, authorized to represent the Government or give the appearance that they are doing so.
C.11 TERMINATION OF EMPLOYEES WITH U.S. GOVERNMENT BADGES
(a) The Contractor shall ensure that all employees who have a DOD Common Access Card (CAC), turn in the CAC immediately upon employee separation and/or termination of their employment under this Contract. The above requirement shall be made a part of the standard employee facility clearance procedures for all separated personnel. The Contractor shall advise Command Physical Security of all changes in their personnel requiring DOD base access.
(b) For involuntarily separated personnel and those separated under adverse circumstances, the Contractor shall notify Command Physical Security in advance of the date, time, and location where the Command representative retrieve the DOD CAC prior to the employee departing the Contractor’s facility. In the event the employee is separated in his or her absence, the Contractor shall immediately notify Command Physical Security of the separation and make arrangements between the former employee and Command Physical Security for the return of the CAC. If circumstances arise which necessitate urgent revocation of a CAC after normal business hours, the Mission Partner Identity, Credential and Access Management (MP ICAM) Mission Partner Affiliation Sponsor (MPAS) shall be immediately contacted. MPAS contact information will be provided by the COR after Contract award.
CLAUSES INCORPORATED BY FULL TEXT
C-202-H001 ADDITIONAL DEFINITIONS--BASIC (NAVSEA) (OCT 2018)
(a) Department means the Department of the Navy.
(b) Commander, Naval Sea Systems Command means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.
(c) References to The Federal Acquisition Regulation (FAR) All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.
(d) National Stock Numbers Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:
(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit nonsignificant number.
(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.
(End of Text)
C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT
FILES (NAVSEA) (OCT 2018)
(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:
(1) The support contractor not disclose any information;
(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;
(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.
(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.
C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018)
(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in Proposal dated in response to NAVSEA Solicitation No. .
(b) The technical volume(s) of the Contractor's proposal is(are) hereby incorporated by reference and made subject to the "Order of Precedence" (FAR 52.215-8) clause of this contract. Under the "Order of Precedence" clause, the technical volume(s) of the Contractor's proposal referenced herein is (are) hereby designated as item (f) of the clause, following "the specifications" in the order of precedence.
C-223-W002 ON-SITE SAFETY REQUIREMENTS (NAVSEA) (OCT 2018)
(a) The contractor shall ensure that each contractor employee reads any necessary safety documents within 30 days of commencing performance at any Government facility. Required safety documents can be obtained from the respective safety office. Contractors shall notify the Safety office points of contact below to report completion of the required training via email. The email shall include the contractor employee’s name, work site, and contract number.
(b) It is expected that contractor employees will have received training from their employer on hazards associated with the areas in which they will be working and know what to do in order to protect themselves. Contractors are required to adhere to the requirements of 29 CFR 1910, 29 CFR 1926 and applicable state and local requirements while in Government spaces. The contractor shall ensure that all on-site contractor work at the Government facility is in accordance with any local safety instructions as provided via the COR. The contractor shall report all work-related injuries/illnesses that occurred while working at the Government site to the COR.
(c) Contractors whose employees perform work within Government spaces in excess of 1000 hours per calendar quarter during a calendar year shall submit the data elements on OSHA Form 300A, Summary of Work Related Injuries and Illnesses, for those employees to the safety office , via the COR by 15 January for the previous calendar year, even if no work related injuries or illnesses occurred. If a contractor’s injury/illness rates are above the Bureau of Labor Statistics industry standards, a safety assessment may be performed by the Safety Office to determine if any administrative or engineering controls can be utilized to prevent further injuries/illnesses, or if any additional Personal Protective Equipment or training will be required.
(d) Any contractor employee exhibiting unsafe behavior may be removed from the Government site. Such removal shall not relieve the contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR 52.249-14.
(e) The Safety Office points of contacts are as follows:
C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)
The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) A, attached hereto.
C-227-H009 ACCESS TO DATA OR COMPUTER SOFTWARE WITH RESTRICTIVE
MARKINGS (NAVSEA) (JAN 2019)
(a) Performance under this contract may require that the Contractor have access to technical data, computer software, or other sensitive data of another party that contains restrictive markings. If access to such data or software is required or to be provided, the Contractor shall enter into a written agreement with such party prior to gaining access to such data or software. The agreement shall address, at a minimum, (1) access to, and use of, the restrictively marked data or software exclusively for the purposes of performance of the work required by this contract, and (2) safeguards to protect such data or software from unauthorized use or disclosure for so long as the data or software remains properly restrictively marked. In addition, the agreement shall not impose any limitation upon the Government or its employees with respect to such data or software. A copy of the executed agreement shall be provided to the Contracting Officer. The Government may unilaterally modify the contract to list those third parties with which the Contractor has agreement(s).
(b) The Contractor agrees to: (1) indoctrinate its personnel who will have access to the data or software as to the restrictions under which access is granted; (2) not disclose the data or software to another party or other Contractor personnel except as authorized by the Contracting Officer;
(3) not engage in any other action, venture, or employment wherein this information will be used, other than under this contract, in any manner inconsistent with this requirement; (4) not disclose the data or software to any other party, including, but not limited to, joint venturer, affiliate, successor, or assign of the Contractor; and (5) reproduce the restrictive stamp, marking, or legend on each use of the data or software whether in whole or in part.
(c) These restrictions on use and disclosure of the data and software also apply to information received from the Government through any means to which the Contractor has access in the performance of this contract that contains restrictive markings.
(d) The Contractor agrees that it will promptly notify the Contracting Officer of any attempt to gain access to any information with restrictive markings. Such notification shall include the name and organization of the individual, company, or Government representative seeking access to such information.
(e) The Contractor shall include this requirement in subcontracts of any tier which involve access to information covered by paragraph (a), substituting "subcontractor" for "Contractor" where appropriate.
(f) Compliance with this requirement is a material requirement of this contract.
C-228-H002 MINIMUM INSURANCE REQUIREMENTS (NAVSEA) (JAN 2019)
(a) In accordance with the clause(s) of this contract entitled "Insurance--Work On a Government Installation" (FAR 52.228-5) and “Liability and Insurance” (DFARS 252.217-7012), as applicable, the Contractor shall procure and maintain insurance, of at least the kinds and minimum amounts set forth below:
(i) Workers' compensation and employer’s liability coverage shall be at least $100,000, except as provided in FAR 28.307-2(a), if applicable
(ii) Bodily injury liability insurance coverage shall be written on the comprehensive form of policy of at least $500,000 per occurrence.
(iii) Automobile liability policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
(b) To be approved by the Contracting Officer, insurance certificates must include the following cancellation policy statement: Prior to cancellation or material change in coverage, the contractor shall give 30 days written notice to the Contracting Officer.
(c) Physical work cannot begin until the insurance certificate has been approved by the Contracting Officer. Failure to provide an acceptable insurance certificate will not remove the contractor’s responsibility to meet the delivery requirements outlined in Section F and FAR 52.211-11, Liquidated Damages – Supplies, Services, or Research and Development, if applicable.
C-237-H002 SUBSTITUTION OF KEY PERSONNEL (NAVSEA) (OCT 2018)
(a) The Contractor agrees that a partial basis for award of this contract is the list of key personnel proposed. Accordingly, the Contractor agrees to assign to this contract those key persons whose resumes were submitted with the proposal necessary to fulfill the requirements of the contract. No substitution shall be made without prior notification to and concurrence of the Contracting Officer in accordance with this requirement. Substitution shall include, but not be limited to, subdividing hours of any key personnel and assigning or allocating those hours to another individual not approved as key personnel.
(b) All proposed substitutes shall have qualifications equal to or higher than the qualifications of the person to be replaced. The Contracting Officer shall be notified in writing of any proposed substitution at least fortyfive (45) days, or ninety (90) days if a security clearance is to be obtained, in advance of the proposed substitution. Such notification shall include: (1) an explanation of the circumstances necessitating the substitution; (2) a complete resume of the proposed substitute; (3) an explanation as to why the proposed substitute is considered to have equal or better qualifications than the person being replaced; (4) payroll record of the proposed replacement; and (5) any other information requested by the Contracting Officer to enable him/her to judge whether or not the Contractor is maintaining the same high quality of personnel that provided the partial basis for award.
(c) Key personnel are identified in an attachment in Section J.
C-242-H001 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (OCT 2018)
(a) As part of the negotiated fixed price or total estimated amount of this contract, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $1,000 or less at the time of final contract closeout. The term "residual dollar amount" shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.
(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.
| C.1.1 Scope of Services |
| C.1.2 Hours of Operation |
| C.2.1.1 Ordering Procedures |
| C.2.2 Contractor Proposals |
| C.3 COMMENCEMENT OF WORK |
| C.4 PROJECT REQUIREMENTS |
| C.4.1 Requirements |
| Each Task Order (TO) will specify the project requirements. For all TOs, the Contractor shall:: |
| C.4.2 Regulations |
| C.4.3 Contractor Personnel |
| C.4.4 Employee Equipment |
| C.4.5 Employee Requirements |
| C.4.6 Employee Conduct |
| C.4.7 Employee Required Training |
| C.7 Safety |
| C.7.2 ENVIRONMENTAL AND HAZARDOUS MATERIALS HANDLING |
| C.8 Security |
| C.8.1 Portable Electronic Devices |
| C.8.2 Operations Security (OPSEC) |
| C.9 Privacy information |
| C.10 Non-personal services/inherently government functions |
| C.11 Termination of Employees with U.S. Government Badges |
| C-202-H001 ADDITIONAL DEFINITIONS--BASIC (NAVSEA) (OCT 2018) |
| C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA) (OCT 2018) |
| C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019) |
| C-215-H002 CONTRACTOR PROPOSAL (NAVSEA) (OCT 2018) |
| C-223-W002 ON-SITE SAFETY REQUIREMENTS (NAVSEA) (OCT 2018) |
| C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018) |
| C-227-H009 ACCESS TO DATA OR COMPUTER SOFTWARE WITH RESTRICTIVE MARKINGS (NAVSEA) (JAN 2019) |
| C-228-H002 MINIMUM INSURANCE REQUIREMENTS (NAVSEA) (JAN 2019) |
| C-237-H002 SUBSTITUTION OF KEY PERSONNEL (NAVSEA) (OCT 2018) |
| C-242-H001 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (OCT 2018) |