PWS 26-R-CN23 Poland Training Lab.pdf

PDF 1004 KB Posted

Attached to
FY26 EUCOM Construction
Solicitation number
FA4890-26-R-CN23
Issued by

About this file

This is a Performance Work Statement (PWS) for federal contract FA4890-26-R-CN23, issued by the U.S. Air Force Acquisition Management & Integration Center (AMIC) on February 4, 2026, for construction work under Title 10 U.S. Code, section 284c. The contract covers design and construction of a simulated illicit drug production facility at the Police International Training Center in Legionowo, Poland, supporting EUCOM's Counter Narcotics & Stabilization Policy (CNSP) objectives. The primary deliverable is a new single-story drug production simulator building of at least 570 square meters constructed with reinforced concrete masonry and metal-clad roofing, including clandestine laboratories, drying rooms, processing rooms, decontamination rooms, and administrative offices with a covered walkway connection to an existing building. Construction must comply with Polish host nation building codes and include all associated utilities (electrical, water, sewer, and telecommunications connections), HVAC systems, fire protection systems, plumbing fixtures, interior finishes with ceramic tile flooring and suspended ceilings, and stormwater management infrastructure.

The contractor must execute a full design-build delivery with multiple design submission phases (15%, 35%, 95%, and 100%) for government and host nation approval prior to construction commencement. Key performance requirements include maintaining at least one on-site qualified superintendent with 10 years of experience and a dedicated quality control manager at all times during work, submitting comprehensive quality control plans with three-phase inspection protocols, integrated master schedules, bill of materials, and bi-weekly progress reports. All design drawings and specifications must be provided in English and Polish. The contract mandates use of local host nation licensed subcontractors, compliance with all applicable host nation taxes and duties (inclusive in pricing), and Defense Base Act insurance for non-citizen OCONUS personnel. Contractor personnel require advance approval from host nation security authorities with documentation including passport copies submitted 60 days prior. Warranty coverage of one year minimum from final acceptance is required, with contractor responsibility for original equipment manufacturer manuals and end-user training on all systems and equipment prior to handover.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

FA4890-26-R-CN23 POLICE INTERNATIONAL TRAINING CENTER,

LEGIONOWO, POLAND

ACQUISITION MANAGEMENT &

INTEGRATION CENTER (AMIC)

FA4890-26-R-CN23

4 February 2026

This project will be completed under Title 10 United States Code, section 284c.

EUCOM –POLICE INTERNATIONAL TRAINING CENTER

HQ ACC AMIC/PMT

Counter Narcotics & Stabilization Policy (CNSP)

OPR: ACC AMIC/PMT(Construction) 300 Exploration Way, Suite 407 Revision 0, Dated 04 February 2026 Hampton, VA 23666

CONTENTS

1. OBJECTIVE

1.1. SCOPE

1.2. PERFORMANCE REQUIREMENTS

1.2.1. MAINTAINABILITY AND SUSTAINABILITY

1.2.2. CONNECTION TO LOCAL COMMERCIAL UTILITIES

1.2.3. LIFE SAFETY

1.2.4. LIFESPAN

1.2.5. COUNTRY SPECIFIC HN CONTRACTOR REQUIREMENTS

1.2.6. TAXES AND DUTIES IN FOREIGN LOCATIONS

1.2.7. DESIGN & CONSTRUCTION STANDARDS AND REQUIREMENTS

1.2.8. PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

1.2.9. EXISTING CONDITIONS AND CONDITIONS AFFECTING THE WORK

1.3. PERFORMANCE SCHEDULE AND LOCATION

1.3.1. PERFORMANCE SCHEDULE

1.3.2. PLACE(S) OF PERFORMANCE

1.4. PROJECT MANAGEMENT

1.4.1. DEFINITION OF "DIRECT EMPLOYEE":

1.4.2. QUALITY CONTROL STAFF REQUIREMENTS:

1.4.3. PROJECT SUPERINTENDENT REQUIREMENTS:

1.4.4. CONSTRUCTION SITE SUPERINTENDENT

1.4.5. COMBINED ROLE (OPTIONAL):

1.4.6. GOVERNMENT APPROVAL:

1.4.7. CONSEQUENCES OF NON-COMPLIANCE:

1.5. CONSTRUCTION PROJECT DOCUMENTATION

1.6. CONTRACTOR PAYMENT FOR CONSTRUCTION

1.7. TEMPORARY DUTY TRAVEL (TDY)

1.7.1. TRAVEL INSTRUCTIONS

1.8. OTHER REQUIREMENTS

1.8.1. QUALIFICATIONS

1.8.2. SAFETY

1.8.3. ENVIRONMENTAL

1.8.4. CONTRACTOR COMMUNICATION

1.8.5. ISSUE RESOLUTION

1.8.6. DEFENSE BASE ACT (DBA)

1.8.7. TECHNICAL DISCUSSIONS

1.8.8. ORGANIZATIONAL CONFLICT OF INTEREST (OCI)

1.8.9. CONTRACTOR FURNISHED SUPPLIES, EQUIPMENT, AND SERVICES

1.8.10. USG-FURNISHED SUPPORT

1.9. SECURITY

1.10. SUBMITTALS

1.11. SUBMITAL REGISTRY

1.12. QUALITY CONTROL PLAN (QCP)

1.12.1. QC ORGANIZATION

1.12.2. QCP PROCEDURES

1.12.3. QCP THREE PHASE CONTROL SYSTEM

1.12.4. QCP SUBMITTAL MANAGEMENT

1.12.5. DEFINABLE FEATURES OF WORK (DFOW)

1.12.6. QCP INSPECTION/TESTS/ETC

1.13. INTEGRATED MASTER SCHEDULE (IMS)

1.14. BILL OF MATERIAL SUBMITTAL

1.15. BI-WEEKLY PROGRESS REPORT

1.16. QUALITY, ENVIRONMENTAL, SAFETY & HEALTH REPORT (QESHR)

1.17. WARRANTY PLAN

1.18. DESIGN SUBMITTALS

1.18.1. PROCESS

1.18.2. 15% CONCEPTUAL DESIGN SUBMITTAL

1.18.3. 35% DESIGN SUBMITTAL

1.18.4. 95% DESIGN SUBMITTAL

1.18.5. 100% DESIGN SUBMITTAL

1.19. ACCEPTANCE INSPECTION REQUEST

1.20. CLOSE OUT REQUIREMENTS

1.20.1. AS BUILT / RECORD DRAWINGS

1.20.2. ORIGINAL EQUIPMENT MANUFACTURER (OEM) MANUALS

1.20.3. EU TRAINING

1.20.4. KEY CONTROL INVENTORY

2. PERFORMANCE STATEMENT

2.1. PROJECT(S) OBJECTIVES

2.2. SITE LAYOUT

2.3. KEY FACILITY REQUIREMENTS

2.3.1. ILLICIT DRUG PRODUCTION FACILITY SIMULATOR

2.4. SITE EARTHWORKS & IMPROVEMENTS

2.4.1. PEDESTRIAN WALKING SURFACES

2.4.2. STORMWATER MANAGEMENT

2.5. FOUNDATION

2.5.1. SUPERSTRUCTURE

2.6. EXTERIOR WALLS

2.6.1. EXTERIOR COATINGS

2.7. EXTERIOR WINDOWS

2.8. EXTERIOR DOORS

2.8.1. OVERHEAD/ROLL-UP DOORS

2.9. ROOFING

2.10. INTERIOR DOORS

2.10.1. SPECIALTIES

2.10.2. TOILET AND BATH ACCESSORIES

2.10.3. SIGNAGE

2.10.4. COUNTERS

2.10.5. FIRESTOPPING PENETRATIONS

2.11. INTERIOR FINISHES

2.12. PLUMBING

2.12.1. PLUMBING FIXTURES

2.12.2. WATER CLOSETS

2.12.3. URINALS

2.12.4. LAVATORIES

2.12.5. MOP SINK

2.13. UTILITY SERVICES

2.14. POTABLE WATER SYSTEM

2.15. SEWER SYSTEM

2.15.1. FLOOR DRAINS

2.15.2. RAINWATER DRAINAGE

2.15.3. HVAC

2.15.4. SYSTEMS TESTING ADJUSTING & BALANCING

2.16. FIRE PROTECTION SYSTEMS

2.17. ELECTRICAL SERVICE & DISTRIBUTION

2.18. TELECOMMUNICATIONS SYSTEMS

2.19. HN SECURITY SYSTEM

2.20. GOVERNMENT FURNISHED EQUIPMENT

1. OBJECTIVE

The objective of this contract is to construct and or repair facilities as indicated in Performance Work Statement (PWS) Section 2 below using a local national labor force in the country where work will be performed.

SCOPE

The Contractor shall design and construct facilities and or infrastructure as indicated in the PWS, all attachments and contract documents. The scope includes, but is not limited to, basis of design, detailed drawings, specifications, all associated calculations, and analysis (to include, where term “analysis” is noted herein, all engineering calculations, decisions, and conclusions), performance time breakout (construction schedule), schedule of values (SOV), warranty schedule, and submittal register. The work shall include all labor, transportation, travel, materials, tools, equipment, plant, tests, investigations, surveys, and all functions necessary to provide complete and fully functional facility(s).

1.1. PERFORMANCE REQUIREMENTS

Complete design build projects for construction, repair and/or security upgrades as indicated within the PWS and any attachment(s). PWS and attachments include the specific project location, as well as project requirements and may include conceptual drawings, and photo documentation. The Contractor is strongly encouraged to conduct a site survey/investigation prior to bidding. The USG will facilitate site visitation to the extent practical. The Contractor is responsible for all risks associated with failure to visit the site and complete a survey. The Contractor is responsible for investigating existing conditions, fully developing the requirements into a comprehensive executable design, ultimately approved by the Host Nation (HN) and the Contracting Officer (CO). Completed facilities and infrastructure systems shall be weather tight, waterproof, insect, and rodent proof. The requirement is for the completed facility(s)/building(s) and/or infrastructure systems to be complete and useable prior to final acceptance.

1.1.1. MAINTAINABILITY AND SUSTAINABILITY

Facilities, infrastructure, and related systems shall be designed and installed for very low total cost of ownership.

Energy efficiency (building envelope & systems) is a critical design factor. Facilities, infrastructure, and related equipment shall be readily accessible for maintenance, repair, or replacement. Adequate vehicle circulation space is required around facilities for fire and emergency services and vehicle access for delivering to and servicing the facilities and related systems. All equipment and fixtures to include but not limited to; air handlers, condensers, water heaters, boilers, generators, fuel tanks, plumbing fixtures, appliances, etc. shall be installed with suitable clearance and be accessible for servicing or replacement. All equipment shall have isolation/disconnecting means (switches or valves as appropriate) located within sight of the equipment and readily accessible.

1.1.2. CONNECTION TO LOCAL COMMERCIAL UTILITIES

The Contractor is responsible for connecting, or facilitating connections, for all utilities (electrical, water, sewer, communications, etc.) required by this PWS to the local commercial utility systems, including assisting with arranging for facility connections and end user account creation. This responsibility encompasses assistance with all applications, and payment of connection fees, as well as active coordination with both the end user and the local commercial utility service provider. The Contractor must coordinate with the local commercial utility service provider as early as possible in the project to ensure completion of all connections prior to final acceptance and handover or to facilitate a timely completion of connection and account creation post-handover.

1.1.3. LIFE SAFETY

The Contractor shall ensure the design & construction includes necessary life safety systems (i.e., fire alarms, smoke detectors, emergency lighting, exit lighting, fire suppression systems, etc.), identifies egress routes, and complies with HN building code and fire safety requirements as appropriate. All facilities shall have a secondary means of egress.

The construction and all work shall comply with all local safety and health requirements.

1.1.4. LIFESPAN

Design lifespan for all facilities and infrastructure shall be IAW Host Nation building code.

1.1.5. COUNTRY SPECIFIC HN CONTRACTOR REQUIREMENTS

A. Licensed HN Subcontractors. The contractor shall team with one (1) or more HN licensed subcontractor(s) to perform the design, construction, repair or other work as required by this CONTRACT. The contractor is responsible for partnering/selecting HN subcontractor(s) that comply with the agency/authority (Border Guard (BG), National Police, SEMAR etc.) security and other requirements for accessing the installation/property where the work is to be performed. The Contractor shall comply with human rights requirements of the Foreign Assistance Act and 10 U.S.

Code § 2249e. HN labor laws and regulations shall apply.

B. Site Access Information: The Contractor shall obtain approval from the HN agency/authority that controls the site/facilities for all personnel requiring access. The Contractor shall follow all HN agency requirements for access.

Typically, the HN agency/authority requires the following information for each person who will require access to the site(s) a minimum of sixty (60) calendar days in advance to allow for approval clearances for access to HN properties.

This shall be merged into one (1) Excel document for all personnel and for vehicles. The required personnel and vehicle information includes:

1. Company Info: Company name (i.e., Contractor, Sub-contractor, etc.), address, and phone number

2. Personnel Names. Provide full names (LAST, FIRST MIDDLE) for each person requiring access to the site

3. Job Title. Provide the job title/trade of each person

4. Vehicle Information. Provide the following for each vehicle requiring access to the site:

a. Manufacturer

b. Model

c. Color

d. License Plate Number

e. Copy of Registration Document

5. Copy* of Passport or official National Identification. Provide official identification information which includes:

a. Document number

b. Photo

c. Full Name

d. Expiration date

* Passport copy shall be high resolution scan of passport photo & signature page in PDF format.

1.1.6. TAXES AND DUTIES IN FOREIGN LOCATIONS

The contract price is inclusive of all applicable taxes, duties, and levies imposed by the host nation government on the Contractor's operations, materials, equipment, and personnel. The Contractor shall be solely responsible for identifying and complying with all host nation tax laws, including but not limited to Value-Added Tax (VAT).

The Contractor is responsible for taking all necessary steps to determine the existence of any such tax exemptions and to secure them if available. The Contractor shall work with the Contracting Officer and the relevant U.S. Embassy or military component to obtain any required documentation, such as tax exemption certificates. The Government will provide reasonable assistance in obtaining such documentation, but the primary responsibility for securing tax relief rests with the Contractor. If the Contractor fails to obtain a tax exemption for which it is eligible and pays taxes that could have been avoided, the U.S. Government will not reimburse the Contractor for such payments. All invoices shall clearly state the amount of any VAT or other taxes paid, or alternatively, shall note that an exemption was claimed.

1.1.7. DESIGN & CONSTRUCTION STANDARDS AND REQUIREMENTS

A. Design and Construction Codes. All standards, building codes, and regulations as referenced in the Basic Contract, this PWS and attachments shall apply. Should there be a conflict between any contract requirement, referenced standard, code or regulation the most stringent requirement shall apply. All Federal Acquisition Regulation (FAR) clauses contained in the basic contract apply and are incorporated by reference. For the design and construction, the Contractor shall provide a list of the standards, building codes, and regulations required by the HN and local building codes. The design live & dead loads, wind loads, seismic loads, snow loads, etc. shall be in accordance with HN building code. The design and construction shall comply with HN requirements regarding threatened or endangered species, environmental protection, cultural and historical resources, and disability access. Should the HN not have buildings codes the International Building Code (IBC), and standards referenced therein shall apply.

B. FAR Clauses:

• 1.602-1 Authority

• 52.236-2 Differing Site Conditions

• 52.236-3 Site Investigation and Conditions Affecting the Work

• 52.236-5 Material and Workmanship

• 52.236-6 Superintendence by the Contractor

• 52.236-7 Permits and Responsibilities

• 52.236-8 Other contracts

• 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Structures

• 52.236-10 Operations and Storage Areas

• 52.236-11 Use and Possession Prior to Completion

• 52.236-12 Cleaning Up

• 52.236-15 Schedules for Construction Contracts

• 52.236-21 Specifications and Drawings for Construction

• 52.236-26 Preconstruction Conference

• 52.246-12 Inspection of Construction

C. Superstructure:

• Steel, concrete & masonry (non-combustible materials)

• Live & dead loads: In accordance with HN building code.

• Wind loads: Design wind speed HN building code

• Seismic (Earthquake) loads: HN building code

D. Language. The design drawings and specifications provided by the Contractor shall be submitted in English and HN language. Drawings are to be submitted in AutoCAD and Portable Document Format (PDF).

1.1.8. PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed, and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place.

The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site, and (2) on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor.

The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the CO may have the necessary work performed and charge the cost to the Contractor.

1.1.9. EXISTING CONDITIONS AND CONDITIONS AFFECTING THE WORK

The Contractor is responsible for thoroughly examining the site, prior to bidding, and ascertaining the nature and location of the work and the general and local conditions which can affect the work or its cost, and bears the risk of unanticipated cost increases, for factors including but not limited to:

• Conditions bearing upon transportation, disposal, handling, and storage of materials and equipment.

• Securing the site(s), material, equipment and work for safety and to prevent theft and/or vandalism.

• Availability of material, equipment, labor, lodging, transportation, water, electric power, sanitary sewer, and roads.

• Uncertainties of weather including historical weather data, river stages, tides, or similar physical conditions at the site.

• Conformation and conditions of the ground and structures.

• Character of equipment and facilities needed preliminary to and during work performance.

• Providing life support for all supporting personnel.

1.2. PERFORMANCE SCHEDULE AND LOCATION

1.2.1. PERFORMANCE SCHEDULE

The Contractor shall submit a detailed Integrated Master Schedule (IMS) in the form of a stand-alone Gantt chart in accordance with paragraph 1.13. This schedule must graphically illustrate all tasks, their logical order of performance, and respective durations in a manner that directly supports the Contractor’s technical approach for this entire Performance Work Statement. The schedule must be planned to achieve physical completion of all work no later than 14 calendar days before the contractual completion date. The contractual completion date represents the final deadline by which all project activities shall be fully completed and resolved.

1.2.2. PLACE(S) OF PERFORMANCE

The principal place(s) of performance are listed in paragraph 2.

1.3. PROJECT MANAGEMENT

The Prime Contractor shall provide, at its sole expense, qualified and experienced personnel to perform the functions of Quality Control Staff and Project Superintendent for the duration of this contract. To ensure direct responsibility and accountability for the quality and timely completion of the work, both the Quality Control Staff and Project Superintendent shall be direct employees of the Prime Contractor.

1.3.1. DEFINITION OF "DIRECT EMPLOYEE":

For the purpose of this section, a "direct employee" is defined as an individual who is:

• Listed on the Prime Contractor's payroll.

• Subject to the Prime Contractor's direct control and supervision.

• Eligible for benefits provided by the Prime Contractor to its employees.

1.3.2. QUALITY CONTROL STAFF REQUIREMENTS:

1. Employment Status: The individual(s) assigned to the Quality Control Staff shall be direct employees of the

Prime Contractor as defined in paragraph (a) above.

2. Experience: The Quality Control Staff shall possess a minimum of 5 years of documented experience in construction quality control, with demonstrated experience in concrete placement, structural steel erection, electrical systems installation, etc.

3. Responsibilities: The Quality Control Staff shall be responsible for implementing and maintaining the Quality Control Plan as approved by the Government. This includes, but is not limited to: performing inspections, documenting deficiencies, tracking corrective actions, and ensuring compliance with contract specifications and applicable codes and standards.

4. Certifications: The Quality Control Staff shall possess and maintain valid certifications relevant to their assigned responsibilities, including, but not limited to: ICC certifications, ASQ certifications. The Government reserves the right to request verification of certifications at any time.

1.3.3. PROJECT SUPERINTENDENT REQUIREMENTS:

1. Employment Status: The Project Superintendent shall be a direct employee of the Prime Contractor as defined in paragraph (a) above.

2. Experience: The Project Superintendent shall possess a minimum of 10 years of documented experience in construction project management, with demonstrated experience in managing schedules, coordinating subcontractors, resolving field issues, etc.

3. Responsibilities: The Project Superintendent shall be responsible for the overall on-site management of the project, including, but not limited to: coordinating subcontractors, managing schedules, ensuring compliance with safety regulations, and resolving field issues.

4. Authority: The Project Superintendent shall have the authority to make decisions on behalf of the Prime Contractor regarding on-site operations and shall be the primary point of contact for the Government's representatives at the job site.

5. Certifications: The Project Superintendent shall possess and maintain valid certifications relevant to their assigned responsibilities, including, but not limited to: OSHA 30-hour certification or HN equivalent, Project Management Professional (PMP) certification. The Government reserves the right to request verification of certifications at any time.

1.3.4. CONSTRUCTION SITE SUPERINTENDENT

The Contractor shall directly oversee the work and have a competent superintendent on the work site at all times when work is in progress. The superintendent shall have not less than ten (10) years of demonstrated experience with comparable size and scope of construction projects. The superintendent position shall not be dual tasked (i.e., QC lead, ES&H, etc.). The superintendent shall be capable of effective communication with all personnel and sub-contractors at any tier. The superintendent shall document the daily site activities (labor, materials, equipment, etc.), progress, permits obtained, weather, and QC activities, maintain record/as-built drawings, and ES&H related inspections or actions.

1.3.5. COMBINED ROLE (OPTIONAL):

An individual may fulfill both the roles of Quality Control Staff and Project Superintendent, provided that the individual meets all the experience, certification, and responsibility requirements outlined in paragraphs (1.4.2.) and (1.4.3.) above. The Prime Contractor shall provide clear documentation demonstrating that the individual possesses the necessary qualifications and has sufficient time and resources to effectively perform both roles without compromising the quality or timeliness of the work.

1.3.6. GOVERNMENT APPROVAL:

The Prime Contractor shall submit the resumes and qualifications of the proposed Quality Control Staff and Project Superintendent to the Government for approval within 14 calendar days of contract award. The Government reserves the right to disapprove any proposed personnel who do not meet the requirements of this section. Any changes to the assigned Quality Control Staff or Project Superintendent shall be submitted to the Government for approval prior to the change taking effect.

1.3.7. CONSEQUENCES OF NON-COMPLIANCE:

Failure to comply with the requirements of this section may result in Consequences such as- withholding of payments, issuance of cure notices, termination for default, etc..

1.4. CONSTRUCTION PROJECT DOCUMENTATION

The contractor shall prepare and keep accurate and up to date all necessary working (on-site) drawings for building construction, site construction and utilities. An accurate and current construction plan and schedule shall be maintained on the worksite for review by USG or any local officials at any time.

1.5. CONTRACTOR PAYMENT FOR CONSTRUCTION

a) The basis for payment shall be the SOV derived from the Defined Features of Work. The Contractor shall submit a SOV within 30 calendar days of contract award. The SOV will consist of a cost breakdown that incorporates the proposed contract price. The SOV will assign values to each major activity necessary to complete the work. Values shall include all direct and indirect costs. The SOV shall contain sufficient detail to enable the USG to evaluate applications for payment. The SOV shall include a breakdown of material, time, labor, and other direct costs (ODC). Lump sum pricing is not acceptable.

b) Contractor is authorized to invoice monthly per FAR 52.232-5. Any variations from the monthly requirement shall be approved, in writing, by the CO.

c) Invoices shall be submitted in Wide Area Workflow (WAWF).

d) Invoices shall be supported by monthly progress report, IMS and quality control (QC) documentation. QC documentation is objective evidence (i.e., tests, inspection reports, photos, operation reports, commissioning documents, etc.) that clearly show the work complies with all applicable HN regulations, drawing & specifications, contract, and PWS requirements.

e) Invoicing for materials shall be fully supported by copies of purchase orders and Proof of Delivery (photos, inventories, inspection documents, etc.).

f) Contractor shall notify the Program Manager (PM) and Contracting Officer’s Representative (COR), through WAWF, when invoice is submitted.

g) All materials and work covered by progress payments shall become the exclusive property of the U.S.

Government at the time of payment. However, this does not relieve the Contractor of full responsibility for the condition, completion, or restoration of such materials and work. Nor does it waive the Government’s right to enforce all terms of the contract.

1.6. TEMPORARY DUTY TRAVEL (TDY)

1.6.1. TRAVEL INSTRUCTIONS

The Contractor shall coordinate all travel for US citizens Outside Contiguous US (OCONUS) travel with the PM and COR per CNSP procedures and DoD Foreign Clearance Guide (FCG), including approval through Aircraft and Personnel Automated Clearance System (APACS). A current revision of the APACS and Travel authorization forms shall be provided at Kick-off. All travel expenses under this CONTRACT shall be part of the fixed price offer. The Contractor shall ensure that all (on foreign soil only, verify with COR) employees are loaded into the Synchronized Pre-deployment and Operational Tracker (SPOT) database, if applicable, and have a current DD Form 93, Record of Emergency Data Card, on file with the Contractor. Blanket SPOT request are authorized for the duration of this TO.

The Contractor shall ensure that all OCONUS travelers have country clearance and Letter of Authorization (LOA) approved by the CO prior to travel, as applicable. Travel requires PM or COR approval prior to APACS country clearance and SPOT submittal (OCONUS).

1.7. OTHER REQUIREMENTS

1.7.1. QUALIFICATIONS

All design, construction and construction related activities shall be accomplished by personnel qualified to perform the duties and tasks they perform. All construction, maintenance and/or repair shall be performed by, or under the direct supervision of, licensed/certified personnel. This includes, but is not limited to; electrical, plumbing, Heating, Ventilation Air Conditioning (HVAC), welding, crane operations, etc. The contractor shall retain copies of all licenses/certifications and make them available to the USG.

1.7.2. SAFETY

The Contractor shall comply with the referenced codes and standards and all HN and local safety and health requirements. The Contractor shall submit an ES&H Plan specific to this contract and the related construction activities. The ES&H plan shall place particular emphasis on the elements listed below:

• Accident prevention

• Control of Hazardous Energy (Lockout/Tagout)

• Activity Hazard Analysis (AHA)

• Personal Protective Equipment (PPE)

• Safety Data Sheets (SDS)

• Noise & Dust Control

• Fall Protection

• Confined Spaces

• Crane, forklift & heavy equipment operations

• Public/pedestrian safety

• Hot Work: Prior to engaging in any work that produces open flame, sparks, or heat that could provide a source of ignition (i.e., welding, soldering, brazing, grinding, etc.) the Contractor shall complete an activity hazard analysis to identify and mitigate risks associated with fire, personal injury, and damage to property.

o Housekeeping:

o All work areas, means of access, and laydown areas shall be maintained in a safe and orderly condition at all times.

o All stairways, hallways, passageways, and accessways shall be kept free of materials, trash/debris, and obstructions at all times.

o Trash/debris shall be removed promptly as required to prevent accumulation and/or safety or fire hazards.

• Fire Prevention

• Environmental - All work shall comply with HN and local environment regulations.

• Disposal of Debris: All debris shall be removed and disposed of, off the site/installation, by the Contractor

IAW all HN and local regulations.

• Accident (mishap) reporting procedures Note: Report all accidents to ACC AMIC within 24 hours of occurrence.

1.7.3. ENVIRONMENTAL

The design and construction shall comply with all HN environmental regulations. The contractor shall be responsible for coordinating, obtaining, or compiling data to obtain any required permits and/or permit modifications applicable to the performance and completion of the work within this PWS. The ES&H Plan shall include the applicable codes, regulations and permits required. The plan shall also address any applicable endangered species, cultural and historical resource protection actions required. The Contractor shall ensure the design and construction prevents or mitigates stormwater runoff and prevents erosion. The Contractor shall take necessary measures to protect the work site and surrounding area from erosion, rutting from vehicle traffic and construction operations, and flooding. The Contractor is responsible for designing and installing storm water related systems or structures that may include but are not limited to ditches, swales, culverts, retaining walls, retention ponds, etc., and providing proper grade and slope to prevent flooding and erosion to support the facilities and or infrastructure installed or impacted by this CONTRACT.

1.7.4. CONTRACTOR COMMUNICATION

In the interest of assuring and maintaining the highest order of foreign and diplomatic relations in the HN, the Contractor is instructed from having any direct or indirect negotiations, dealings, agreements, business or entreaties with officials of the HN, which would have a direct or indirect effect upon accomplishing or performing on this CONTRACT, and which could be construed by the HN government or HN citizens as having been officially or unofficially sanctioned, approved or constructively condoned by the USG. Contacts by the Contractor relating to the above shall be through appropriate USG channels as prescribed by the CO. Specifically excluded from the prohibition herein set forth is the incidental daily contacts of the Contractor or his employees, which they may reasonably be expected to have in the normal course of travel, daily work, labor disputes, customs clearances, and passport control.

All Contractor personnel shall communicate professionally and only with respect to CONTRACT business concerns with non-acquisition personnel. All CONTRACT information and communication shall flow through and be provided to the CO, PM and/or COR, as applicable, to affect appropriate contract action and address in-country issues. Only the CO, PM and/or COR or officially designated representative, will report and communicate contract performance status with other USG personnel and management chains.

1.7.5. ISSUE RESOLUTION

The Contractor shall monitor and report all situations that could cause delays in performance, increase in cost, or unsuccessful contract performance. The Contractor shall formally notify the CO immediately and CNSP org box (accamic_cnspconstruction@us.af.mil) in writing, prior to incurring additional cost or delay to the contract.

1.7.6. DEFENSE BASE ACT (DBA)

DBA insurance is required for all personnel performing work OCONUS (unless they are a citizen of the delivery country). The contractor shall provide DBA IAW FAR 52.228.3. In addition, the contractor shall provide medical evacuation insurance for all personnel performing duties.

1.7.7. TECHNICAL DISCUSSIONS

The Contractor shall present and participate in technical discussions and shall inform the CO, PM, Advisory and Assistance Service (A&AS) support contractor, and/or COR as soon as practicable to be any problems with contract execution and any proposed solutions. The Contractor shall produce and provide detailed minutes, including attendance to the USG within five (5) calendar days for all meetings.

1.7.8. ORGANIZATIONAL CONFLICT OF INTEREST (OCI)

Contractors shall address OCI as part of their on-going management.

1.7.9. CONTRACTOR FURNISHED SUPPLIES, EQUIPMENT, AND SERVICES

The Contractor shall furnish all required supplies and services needed to perform the requirements set forth in this

PWS.

1.7.10. USG-FURNISHED SUPPORT

Not Applicable (N/A)

1.8. SECURITY

All work performed under this CONTRACT shall be at the Unclassified level. Contractors shall provide their own insured transportation and security plan for delivery of all construction equipment and materials. Contractors are responsible for all aspects of security during performance of the requirement.

1.9. SUBMITTALS

The following are submittals required by this CONTRACT:

• Delivery Method shall be by Email or DoD SAFE for large files (I.e., Drawings)

• Recipients shall be CO, PM, A&AS support contractor, COR

• USG Review Time of Updates: Fourteen (14) Calendar Days

• Contractor Resubmittal Time: Seven (7) Calendar Days

* NOTES: This is not an all-inclusive list and does not relieve the contractor of responsibility for providing submittals and deliverables as required elsewhere in the PWS and/or other contract documents.

USG approval of a submittal does not relieve the contractor of responsibility for complying with the contract, PWS, or standards referenced therein.

Submittal Details

QC Plan (QCP)

Reference: Paragraph 1.12 Due Date: Within thirty (30) calendar days after contract award Updates: The Contractor shall provide any changes or updates to the USG PM/COR/CO for USG review and acceptance prior to Contractor implementation.

Submittal Registry

Reference: Paragraph 1.12 Due Date: Initial due within thirty (30) calendar days after contract award;

Update on a monthly basis with the concurrent Bi-Weekly Progress Report (or as otherwise directed by the CO/COR

Bill of Materials (BoM)

Reference: Paragraph 1.14 Due Date: Initial within 14 calendar days after NTP Updates: Resubmit monthly, or more frequently if material changes occur

Defined Features of Work (DFoW)

Reference: Paragraph 1.12.5 Due Date: Within thirty (30) calendar days after contract award Updates:

Integrated Master Schedule (IMS)

Reference: Paragraph 1.13 Due Date: Initial thirty (30) calendar days after contract award; Update on a monthly basis with the concurrent Bi-Weekly Progress Report (or as otherwise directed by the CO/COR

Bi-Weekly Progress Report

Reference: Paragraph 1.15 Due Date: Every 14 calendar days capturing data from the previous month

ES&H Plan Reference: Paragraph 1.8.4.

Due Date: Ten (10) calendar days prior to start of construction

Submittal Registry

Reference: Paragraph 1.11 Due Date: Within thirty (30) calendar days after contract award Updates: The Contractor shall provide any changes or updates to the USG PM/COR/CO for USG review and acceptance prior to Contractor implementation

Table 1: Submittals and Deliverables

1.10. SUBMITAL REGISTRY

The Contractor shall develop, maintain, and submit a comprehensive Submittal Registry covering all contract-required submittals. The Submittal Registry shall serve as a centralized tracking tool to ensure all deliverables are identified, scheduled, submitted, reviewed, and approved in accordance with contract requirements.

• Content. The Submittal Registry shall, at a minimum, include:

o Unique Submittal Number o Submittal Title/Description o Applicable Specification or PWS Paragraph Reference o Required Format: Adobe PDF o Initial Submission Due Date – within 30 calendar days of award o Updates. The Submittal Registry shall be updated and resubmitted on a monthly basis with the concurrent Bi-Weekly Progress Report (or as otherwise directed by the CO/COR). Updates shall accurately reflect the current status of all required submittals.

1.11. QUALITY CONTROL PLAN (QCP)

The Contractor shall submit a comprehensive QCP for this CONTRACT per the Deliverables schedule in Section

1.10. The plan shall detail the procedures & processes to be implemented and the objective evidence to be obtained to verify compliance with PWS requirements.

Submittal Details

Material Submittal Reference: Paragraph 1.15 Due Date: Forty-five (45) calendar days prior to turnover of equipment or facility acceptance

Warranty and Warranty Plan

Reference: Paragraph 1.17 Due Date: Forty-five (45) calendar days prior to turnover of equipment or facility acceptance

Designs & Drawings

Reference: Paragraph 1.19 & 1.20 Due Date: 15% Conceptual Layout, 35%, 95% and 100% design/drawing -as indicated on contractor’s schedule. 100% designs are due for HN approval NLT 14 days upon approval of 95% designs Designer of Record (DOR): Contact information and current license/certification information submitted with 10% Conceptual Layout.

Copies of HN permits/approvals: Submitted to the CO prior to construction start.

Drawings, As-Built – Delivered within fourteen (14) calendar days of final acceptance

- AutoCAD & Adobe files (soft) copies to USG. Paper (hard) copy to End User (EU) at final acceptance.

Operation and Maintenance Manuals

Reference: Paragraph 1.20.2.

Due Date: Fourteen (14) calendar days prior to final acceptance

EU Training Reference: Paragraph 1.20.3.

Due Date: Electronic copy upon completion and prior to final inspection/acceptance

Key Control Inventory Reference: Paragraph 1.20.4.

Due Date: At final acceptance per location and electronically seven (7) calendar days prior to final

Acceptance Inspection Request

Reference: Paragraph 1.19 Due Date: No later than forty-five (45) calendar days prior to final acceptance

Invoicing SOV Reference: Paragraph 1.6 Due Date: Prior to Invoicing

1.11.1. QC ORGANIZATION.

At a minimum, the plan shall include a description of the QC organization including a chart showing lines of authority for all aspects of the work. The plan shall identify personnel that will perform QC duties on site and report results to the Designer, Superintendent, and Contractor senior leadership. The contractor shall submit the name, qualifications, duties, responsibilities, and authorities of each person assigned a Contractor QC (CQC) function. The contractor shall provide a copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. This contract requires a dedicated Construction Inspector/Quality Control Manager to be on site at all times work is in progress.

1.11.2. QCP PROCEDURES

The QCP shall include procedures for scheduling, reviewing, inspecting, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, purchasing agents, designers, consultants and architect-engineers (AE).

1.11.3. QCP THREE PHASE CONTROL SYSTEM

The plan shall list the associated inspections, tests, and/or commissioning(s) to be accomplished to verify design and construction requirements are met. At a minimum the contractor shall use a three-phase control system (Preparatory, Initial, and Follow-up Phases) and provide a documentation record of such verifications. Copies of all inspection, test, and/or commissioning documents are to be provided to the USG. The Contractor shall provide objective evidence (i.e., tests, inspection reports, operation reports, commissioning documents, photos, etc.) that the work complies with all applicable host nation regulations, drawing & specifications, contract and PWS requirements. The Contractor shall support and provide copies of virtual site visits by the USG. The plan shall list the major definable features of work to be performed. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. The plan shall include procedures for tracking preparatory, initial, and follow-up control phases, control verification, and acceptance tests including documentation and other objective evidence.

Phase I Preparatory Phase—the preparatory phase will be performed prior to the start of any definable feature of work. The preparatory phase includes but is not limited to:

• Review all plans, specifications, submittals, and manufacturer’s installation instructions pertaining to the definable feature of work;

• Review Environmental, Safety, & Health hazards and controls (i.e., fall protection, Personal Protective Equipment, containment, Lock-Out/Tag-out, etc.) necessary to complete the work safely;

• Ensure that the design drawings have been fully reviewed, and personnel are fully aware of all aspects of the planned construction activities;

• Verify that all preliminary associated work has been completed and approved, and the subject task is ready to proceed;

• Inspect the materials and equipment required to ensure that they meet all required specifications and conform to the design drawings and ensure that the materials are in new & in good condition;

• Meet with any applicable subcontractors to discuss the details of the task and review the quality control procedures including workmanship and project schedules;

• Formally record and report the results of the preparatory phase

Phase II Initial Phase—the initial phase is performed at the start of any definable feature of work. The initial phase includes but is not limited to:

• Review the Preparatory Phase documentation for the specific task;

• Verify that all preliminary work is in compliance with the design drawings and specifications;

• Review and verify that construction methods and workmanship are acceptable;

• Verify that the work is being performed in accordance with all Environmental, Safety, and Health requirements;

• Ensure that all required inspection, testing, and quality control measures have been accomplished and that all work and material are acceptable;

• Reject any unsatisfactory materials and work, review & revise as necessary the quality control measures and procedures, re-accomplish and re-inspect as required;

• Formally record and report the results of the initial phase;

Phase III Follow-up Phase—the follow-up phase is performed periodically (routine and random) for each definable feature of work to ensure continuing compliance with the plans and specifications.

• Review and verify that the construction (quality of material and workmanship) is in compliance with the plans and specifications;

• Verify Environmental, Safety, and Health standards are complied with;

• Review and verify the results of test and inspections;

• Identify & document any work that does not conform to the plans, specifications, and required level of workmanship, and follow-up and record the date the deficiencies are corrected and who corrected them;

• Formally record and report the results of the follow up phase;

1.11.4. QCP SUBMITTAL MANAGEMENT

The QCP shall include procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, purchasing agents, designers of record, consultants, and AE.

1.11.5. DEFINABLE FEATURES OF WORK (DFOW)

The Contractor shall develop and maintain a comprehensive list of all Definable Features of Work (DFOW) for this project. A DFOW is a task which is separate and distinct from other tasks, has control requirements peculiar to itself, and is identifiable by a specific trade or discipline. The DFOW list shall be submitted as part of the Quality Control (QC) Plan for Government approval.

For each DFOW, the Contractor shall conduct and document the three phases of quality control: Preparatory, Initial, and Follow-up, in accordance with the approved QC Plan. The Contractor shall schedule and conduct a Preparatory Phase meeting for each of the above DFOWs prior to commencing any work. The start of each DFOW will trigger the Initial Phase inspection, and Follow-up inspections will occur throughout the duration of the work. All QC activities for each DFOW shall be documented in the daily QC Reports.

1.11.6. QCP INSPECTION/TESTS/ETC.

The QCP shall list the associated inspections, tests, and/or commissioning(s) to be accomplished to verify all construction requirements are met and to provide objective evidence of all verifications. Copies of all inspection, test, and/or commissioning documents are to be provided to the USG. The Contractor shall provide objective evidence (i.e., tests, inspection reports, operation reports, commissioning documents, etc.) that the work complies with all applicable HN regulations, drawing & specifications, contract and PWS requirements. The plan shall list the definable features of work (DFOW) to be performed and the QC to be performed to verify compliance. A DFOW is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. The plan shall include procedures for tracking preparatory, initial, and follow-up control phases, control verification, and acceptance tests including documentation and other objective evidence.

1.12. INTEGRATED MASTER SCHEDULE (IMS)

The Contractor shall prepare and submit a preliminary performance schedule for Government review and approval within 10 calendar days after contract award. A comprehensive, detailed Critical Path Method (CPM) network schedule shall be submitted within 30 calendar days after contract award. No work shall commence on-site until the preliminary schedule has been approved by the Contracting Officer.

The performance schedule shall be in the form of a Gantt chart created using standard industry scheduling software (e.g., Microsoft Project, Primavera). All tasks within the IMS shall be configured in 'auto-scheduled' mode to dynamically reflect dependencies, with the sole exceptions being the initial project 'award' and the final 'acceptance and turnover' milestones. The schedule shall, at a minimum:

• Identify all major tasks, sub-tasks, and milestones required for contract completion.

• Show the logical sequence of work and the critical path for the project.

• Include the start and finish dates for each activity.

• Assign resources and responsibilities for each task.

• Current percentage (%) of completion.

• Clearly identify all contract deliverables and their required submission dates.

• Incorporate milestones for Government inspections and approvals.

The Contractor shall update the performance schedule to reflect the actual progress of the work and submit it to the Contracting Officer's Representative (COR) with each bi-weekly progress report. The updated schedule shall show the original baseline, the current progress of each task against the baseline, and a forecast for the completion of all remaining work. Any proposed revisions to the baseline schedule must be submitted to the Contracting Officer for approval.

The Government will review the submitted performance schedule and provide comments or approval within 15 business days of receipt. If the schedule is disapproved, the Contractor shall revise the schedule to address the Government's comments and resubmit it for approval within 7 business days. Government approval of the schedule shall not relieve the Contractor of its responsibility for the timely completion of the work.

Simultaneously with the submission of the baseline performance schedule, the Contractor shall submit a detailed Schedule of Values. This schedule shall break down the total contract price into the major work activities identified in the performance schedule. The approved Schedule of Values will be used as the basis for determining progress payments.

1.13. BILL OF MATERIAL SUBMITTAL

The Contractor shall prepare and submit a Bill of Materials (BOM) for all equipment, materials, and major components required under this contract. The BOM shall ensure full visibility of material requirements, enable supply chain planning, and verify compliance with technical specifications.

1. Content. The BOM shall, at a minimum, include:

• Item Number/Line Item

• Nomenclature/Description

• Manufacturer and Model/Part Number

• Quantity Required

• Unit of Measure

• Contract Specification or PWS Reference

• Anticipated Source/Vendor (if known)

• Lead Time/Delivery Schedule

• Status (e.g., Planned, Ordered, Delivered, Installed)

2. Initial Submission. The Contractor shall submit the initial BOM to the CO and COR within 14 calendar days after NTP, aligned with project schedule milestones.

3. Updates. The Contractor shall update and resubmit the BOM on a monthly basis, or more frequently if material changes occur that impact schedule, availability, or compliance.

4. Format. The BOM shall be provided in Microsoft Excel (.xlsx) format, in English, and cross-referenced to the Submittal Registry to ensure consistency of data. The manufacturer’s installation instructions/recommendations shall be followed for all materials and equipment. All materials & equipment shall comply with HN building code, environmental safety, and health (ES&H) laws & regulations. The Contractor shall specify heavy duty commercial grade materials and equipment that are extremely durable and low maintenance in harsh, austere, and or remote conditions, the use of materials and equipment that are locally manufactured and supported (i.e., material and/or replacement parts available) in the HN or region is required. Non-combustible materials are required to the extent practical and consistent with HN building and fire codes.

All materials & equipment will comply with HN building code, environmental safety, and health (ES&H) laws & regulations.

The contractor shall specify heavy duty commercial-grade materials and equipment that are extremely durable and low maintenance in harsh, austere, and or remote conditions.

The use of materials and equipment that are locally manufactured and supported (i.e., material and/or replacement parts available) in the HN or region is required.

Non-combustible materials are required to the extent practical and consistent with HN building and fire codes.

1.14. BI-WEEKLY PROGRESS REPORT

The purpose of the Bi-Weekly Progress Report is to provide the Government with a management-level summary of project activities, covering progress made during the reporting period as well as cumulative progress since project initiation. These reports are a mandatory deliverable, with the first report due two (2) weeks after the Contracting Officer issues the Notice to Proceed (NTP). Subsequent reports shall be submitted every two (2) weeks thereafter for the duration of the project.

The Government will furnish a standardized Progress Report Template, which the contractor is strongly encouraged to use. However, contractors may submit their own format provided it contains, at a minimum, all required information outlined in this section and is approved by the Contracting Officer’s Representative (COR).

Each Bi-Weekly Progress Report shall include the following sections:

A. General Information o Contractor Name o Project Location o Report Number: Formatted as YYYYMMDDXXXX, where “YYYYMMDD” reflects the date of creation and “XXXX” is a four-digit sequential identifier.

o Period Covered: Indicate start and end dates in the format…