This document is Addendum No. 1 for the Pewamo-Westphalia Community Schools construction project, dated April 18, 2025. The addendum extends the bid due date to Monday, May 5th, 2025, at 10am and provides several key updates to the project specifications. The project is Davis Bacon Compliant, and contractors are responsible for validating labor rates for Clinton County. The scope of work includes provisions for site logistics, such as contractor-provided dumpsters, portable toilets, fencing, and temporary storage, with flexibility in site layout.
Building drawing clarifications include specific technical specifications for foundation and wall construction, such as 3" rigid insulation at the foundation, insulation extending 2' from the wall's inside perimeter, and a minimum foundation depth of 40" below grade for frost protection. The addendum includes attachments such as Instructions to Bidders, Site Logistics Plans, Bid Form, Alternates, and an unofficial list of Clinton County labor rates. A gym pad alternate in the Multi-Purpose Room is also noted, along with requirements for Performance & Payment Bonds.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWCS Addendum 2.pdf | ||
| 00 11 13 Advertisement for Bids - Pewamo-Westphalia - SUBCONTRACTOR.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 2 Confidential & Proprietary Pewamo-Westphalia Community Schools - Addendum #1
Pewamo-Westphalia Community Schools Addendum No. 1 April 18, 2025
The following project documents have been added for reference. These have been added to the specifications and can also be found in the Addendum #1 folder on Procore.
Specifications:
00 21 13 Instructions to Bidders
1) This project is Davis Bacon Compliant. Rates for Clinton County are attached as a courtesy but it is the responsibility of the contractor to validate or confirm each rate that applies.
2) Bid due date has been extended to Monday, May 5th, 2025, at 10am.
00 41 00 Bid Form
1) Bid due date has been extended to Monday, May 5th, 2025, at 10am.
2) Gym pad alt in Multi-Purpose Room
3) Performance & Payment Bond
4) Use revised Quote Form attached.
00 30 00 Scope of Work
1) Contractor is responsible for dumpsters, portable toilets, fencing as required, and any temporary storage.
00 31 33 Site Logistics Plans
1) Site logistics plan denoting general parking, laydown, and fencing locations has been included for reference. Footprint of these areas can be adjusted to limit fencing requirements as necessary.
BUILDING DRAWING CLARIFICATIONS:
Sheet A310 Wall Sections
1) Drawing Detail 3 - Rigid Insulation at foundation shall be 3” in thickness. Insulation under the slab shall extend 2’ from the wall on the inside perimeter of the building.
Sheet S301 Foundation Details
1) Drawing Detail 5 Botton of foundation shall attain a minimum depth of 40” below grade for frost protection.
Page 2 of 2 Confidential & Proprietary Pewamo-Westphalia Community Schools - Addendum #1
Attachments:
1) 00 21 23 Instructions to Bidders
2) 00 31 33 Site Logistics Plans - Pewamo-Westphalia
3) 00 32 13 Instructions to Bidders - Pewamo-Westphalia
4) 00 41 00 Bid Form - Pewamo-Westphalia
5) 01 23 00 Alternates
6) Clinton County Rates - UNOFFICIAL
File details come from the government source that posted it. Updated .