This is a Statement of Work (SOW) for the procurement of cooling pumps for the Essayons HPU project. The contractor shall provide two (2) Flowserve 2K3x2V-10RV M3V Pumps with specified operating characteristics including 135 GPM capacity, 69 feet total head, 1750 RPM speed, 8.38-inch impeller diameter composed of 316 stainless steel, and a 460V/3/60Hz, 5HP motor with TEFC-W22, SD, and PE specifications. The pumps must meet all applicable state, local, and federal safety requirements, including EM 385-1-1 latest revision, and contractors must follow the vessel's Lockout/Tagout (LOTO) policy prior to commencing work.
Delivery shall occur at US Moorings, located at 8010 NW St Helens Rd, Portland OR 97210, with availability restricted to 0730-1500 Pacific Time, Monday through Thursday. Final inspection will be conducted upon delivery. No testing is required. Following satisfactory completion of delivery, contractors must submit an electronic PDF invoice to USACE Millington Finance Center at cefc-g2invoices@usace.army.mil with copies to Jamie L. Hardwick (Delivery POC, 971-409-6108) and Ian K. Lutjens (Contracting Officer). The document references no applicable pricing terms, set-asides, or contract vehicles.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| D1131 Replacement Datasheet.pdf | ||
| Solicitation - W9127N26QA130.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Essayons HPU Cooling Pump Procurement
01. General:
The contractor shall provide two (2) Flowserve 2K3x2V-10RV M3V Pumps.
02. References:
None
03. GFM:
None
04. Safety Precautions:
Prior to commencing work, follow vessel’s LOTO policy and procedures.
Follow all applicable state local and federal requirements including those specified in EM- 385-1-1 latest revision
05. Specifications:
Provide two (2) Flowserve 2K3x2V-10RV M3V Pumps with the following operating characteristics:
Capacity: 135 GPM Total Head – Feet: 69 Speed – RPM: 1750 Specific Gravity: 1.0 Impeller Diameter: 8.38in Impeller Material: 316 Stainless Steel
460 V / 3 / 60 Hz, 5HP, TEFC-W22, SD, PE Motor.
06. Delivery Information:
Availability 0730-1500 Pacific Time, Monday – Thursday
US Moorings 8010 NW St Helens Rd, Portland OR 97210.
07. Testing
None.
08. Inspection / Documentation Final inspection upon delivery at US Moorings.
09. Point of Contact (POC):
Delivery POC – Jamie Hardwick – 971-409-6108 – Jamie.L.Hardwick@usace.army.mil Contracting Officer (KO) – Ian Lutjens – Ian.K.Lutjens@usace.army.mil
10. Invoice Submittal:
Upon satisfactory completion of delivery, please submit an electronic PDF invoice to USACE Millington (the USACE Finance Center) via email address:
cefc-g2invoices@usace.army.mil;
The following shall be CC’d on the invoice submittal emails:
Jamie.L.Hardwick@usace.army.mil and Ian.K.Lutjens@usace.army.mil
File details come from the government source that posted it. Updated .