pump scope.docx

DOCX document 31 KB Posted

Attached to
FINISH PUMP REPAIR
Solicitation number
BD-25-1239-DPW11-DPW11-115651
Issued by
Essex County, Massachusetts

About this file

This is a Scope of Work Statement for a water pump repair project issued by the City of Amesbury Department of Public Works (DPW) in Massachusetts, with a project number designated as "water 1". The project involves removing, field repairing, and reinstalling a water supply vertical turbine pump, with bid sets available on 4/21/2025, a pre-bid conference scheduled for 4/30/2025, and a bid deadline of 5/7/2025. The planned project start date is 5/12/2025, with a contract duration of one week until substantial completion. The project scope includes electrically and physically decoupling the pump motor, assessing pump failure (initially believed to be a broken shaft coupling), replacing the coupling with material capable of withstanding free chlorine residual, reinstalling and testing the pump, and ensuring proper installation and wiring.

The estimated total project cost is approximately $75,950-$85,950, with labor costs at $49,950 and materials and equipment ranging from $26,000 to $36,000. The project falls under Massachusetts General Law Chapter 149 for projects with labor costs between $10,000 and $49,999. Bidders are required to submit various forms including a General Bid Form, Certificates of Insurance and Non-Collusion, OSHA Certificates, and performance bonds if the total contract exceeds $25,000. The project contact is Tom Rogers, Chief Water Operator, who can be reached at 978-388-0853 or tom@amesburyma.gov, and the project is categorized under OSD Trade Category TRD04.

View the file

Other files

File Type Posted
20210622_100302~1.jpg JPG image
Water meeting.docx DOCX document
20241205_110546.jpg JPG image
20210622_090419.jpg JPG image
SWater dept24120511270.pdf PDF
P1012240.JPG JPG image
P1012241.JPG JPG image
20241205_110654.jpg JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amesbury Water Finish Pump water 1

Scope of Work Statement MGL Chapter 149 Projects: With Labor Costs of $10,000 to $49,999

AWARDING ENTITY

Awarding Entity: City of Amesbury DPW Agency Name and Address: City of Amesbury DPW 39 South Hunt Road, Amesbury, MA 01913 Project Number: water 1 Estimated Construction Cost: $

· Labor = $49,950.00

· Materials & Equipment = $26,000-$36,000

CONTACT INFORMATION

Name and Title: Tom Rogers, Chief Water Operator Phone: 978-388-0853 Email Address: tom@amesburyma.gov

CONTRACT AND BIDDING INFORMATION

Project Name: water 1 Project Description (brief overview): Remove, field repair, and reinstall a water supply vertical turbine pump Bid Sets Available (place, date and time): 4/21/2025 Pre Bid Conference (place, date and time):4/30/2025 Bid Deadline: 5/7/2025 OSD Trade Category: TRD04 Additional Information:

SCOPE OF WORK

Detailed Scope of Work: Provide detailed scope of work of sufficient detail to bid on the project. Provide additional drawings, sketches, notes or specifications as needed and check he appropriate boxes below.

· Drawings or sketches attached

· Notes or specification attached

· Other attachment, if so, indicate: information on pump instillation, previous repairs

Rough scope of work:

1.) Vendor needs electrically and physically decouple the pump motor from the pump assembly.

2.) Vendor needs to provide crane services to move pump motor from pump assembly and pull out pump to be removed outside building.

3.) Vendor needs to assess the pump failure. Initial belief of failure is a broken shaft coupling.

4.) Assuming failure is due to broken coupling; the replacement coupling must be made of a material to withstand a free chlorine residual up to 4.0 ppm at a pH of 6.0.

5.) Any other failure assessment must be quoted out to satisfy the above criteria.

6.) Repaired pump must be delivered and installed by vendor.

7.) The pump must be installed and shimmed to satisfy correct level specs.

8.) The pump motor must re-installed and wired by someone with electrical experience.

9.) The pump must be tested and satisfactorily run before job is complete.

PROJECT SCHEDULE

Planned Start Date: 5/12/2025 Contract Duration Until Substantial Completion: one week Contract Duration Until Final Completion:

ATTACHMENTS

The following sections are included in the appendices and are part of this contract:

· Instruction to Bidders

· Owner-Contractor Agreement

· General Conditions of the Contract

· Supplemental Conditions of the Contract

· Prevailing Wage Rate Requirements

FORMS

It is the responsibility of the awarding entity to ensure that they obtain the required licenses/certifications from all workers who will be assisting with the work. The following forms are to be completed and submitted with the bid:

· Form for General Bid

· Required Licenses /Certificates

· Certificate of Insurance

· Certificate of Non-Collusion

· Contractor Authorized Signatory Form

· Payment Bond and Performance Bond

· 50% payment bond if total contract is >$25,000

· OSHA Certificates for all employees

Sample Scope of Work Statement Page 2 of 2

File details come from the government source that posted it. Updated .