Chattahoochee Water Treatment Plant SCADA Improvements - Scope of Work
This is a Draft Scope of Work (SOW) document issued by the City of Atlanta Department of Watershed Management for SCADA system upgrades at the Chattahoochee Water Treatment Plant (WTP). The project involves comprehensive modernization of outdated control system architectures and hardware, replacing the current GE iFix SCADA HMI system with AVEVA System Platform (formerly Wonderware) and upgrading obsolete programmable logic controllers (PLCs), remote input/output (RIO) stations, and operator interface terminals (OITs) to current standards. The supplier must provide all labor, equipment, materials, programming, testing, commissioning, and startup services. Key deliverables include replacement of multiple control panels across the facility including raw water pump stations, chemical buildings, filter building systems, sedimentation basins, and finished water pump stations, along with conversion of all ControlNet networks to Ethernet/IP architecture with fiber ring connectivity. The project is organized into eight primary tasks spanning 360 days from Notice to Proceed (NTP), with intermediate milestones including implementation plan submission (30 days), submittals and test plans (90 days), equipment purchase (180 days), Factory Acceptance Test and storage (210 days), equipment delivery (240 days), installation and onsite testing (330 days), training (345 days), and operations and maintenance manuals delivery (360 days).
The contract requires the supplier to submit a detailed proposal including project approach, compliance with technical specifications, three previous project references, resumes of the project manager and lead programmer, and project costs organized within a Schedule of Values framework. The supplier must conduct a pre-submittal site survey to verify specifications at no additional cost to the City. Additional requirements include background checks for all programming personnel before accessing City equipment, submission of shop drawings and submittals for approval prior to hardware purchase, preparation of a Factory Acceptance Test plan with four days of testing including COA attendance and lodging/meals for three employees, and organization of five consecutive days of operational site testing with 14 days advanced notice. The Schedule of Values must separately identify costs for the Finished Water Pump Station (CP-11-700) upgrade, FAT lodging and meals, and contingency items to allow independent removal from scope if required. The supplier shall provide approximately 2,000 feet of Ethernet CAT 5E and multimode fiber cable as a basis of bid, with coordination required for any additional cabling needs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOQ _ Chattahoochee WTP _ Evaluation _ PHASE .pdf | ||
| Chattahoochee Network Diagram.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Chattahoochee Water Treatment Plant
SCADA IMPROVEMENTS
DRAFT
1 INTRODUCTION
The City of Atlanta Chattahoochee WTP SCADA control system and its networks have outdated architectures and obsolete hardware and software. Updates to network and control system components are required. This includes installation of firmware and software versions required to protect against the most recent vendor security advisory vulnerabilities identified at the time of installation. This Scope of Work (SOW) defines the efforts required to achieve this modernization.
2 LOCATION
The Chattahoochee WTP is located next to the Atlanta RM Clayton Water Reclamation Plant at the corner of Plant Rd and Bolton Rd NW:
3 BACKGROUND
Per the City’s SCADA Master Plan (SMP), the Department of Watershed Management (DWM) is standardizing on AVEVA Wonderware in all water and wastewater SCADA HMI systems to maximize operational and maintenance efficiency. The current system at the Chattahoochee WTP is an outdated version of GE iFix.
Discontinued programmable logic controllers (PLCs) and operator interface terminals (OITs) exist in the filter building, chemical building, settled solids, and finished water process areas. In addition to old hardware and software, all ControlNet networks within the plant require replacement with Ethernet/IP.
4 SCOPE OF WORK (SOW)
SUPPLIER shall provide all labor, equipment, materials, programming, testing, commissioning, and start-up as necessary to provide the control system upgrades at the Chattahoochee WTP. During a pre-submittal site survey, SUPPLIER shall verify the items listed in this SOW and provide all required equipment and services, whole and complete, at no additional cost to the City of Atlanta (COA). The following equipment and services shall be provided:
4.1 Control Panels – Programmable Logic Controllers
4.1.1 CP-10-101 Raw Water Pump Station PLC-101
The CP-10-101 1756-L62 redundant ControlLogix PLCs shall be replaced with equivalent or better 5580 ControlLogix controllers, 1756 I/O, and communication modules. I/O network redundant ControlNet cabling and taps shall be removed and replaced with a device level ring (DLR) to each RIO rack. ControlNet connection and messaging to PLC-100 shall be upgraded to Ethernet. Existing Ethernet switches and rings, one for SCADA and one for PLC peer-to-peer, shall remain in place. The following PLC, RIO, and related key components shall be replaced:
1. Rack 0 (PLC-101 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENBT – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
2. Rack 1 (PLC-101 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-EN2T – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
3. Rack 2 (RIO-101 Node 3)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 9 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4. Rack 3 (RIO-101 Node 4)
a. Qty. 1 – 1756-A17 – 17 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 8 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 4 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
5. Qty. 1 – 2711P-B12C4D1 PanelView Plus 1250
4.1.2 CP-10-102 Raw Water Intake PLC-102
The CP-10-102 1756-L62 ControlLogix PLC shall be replaced with equivalent or better 5580 ControlLogix controller, 1756 I/O, and communication modules. The following PLC and related key components shall be replaced:
1. Rack 0 (PLC-102)
a. Qty. 1 – 1756-A17 – 17 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-L62 – ControlLogix Processor, 8 MB Memory
d. Qty. 1 – 1756-ENBT – Ethernet/IP Module
e. Qty. 3 – 1756-IF6I – 6 Point Isolated Analog Input Module
f. Qty. 5 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
g. Qty. 3 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
4.1.3 CP-11-300 Chemical Building PLC-300
The CP-11-300 1756-L62 redundant ControlLogix PLCs shall be replaced with equivalent or better 5580 ControlLogix controllers and 1756 I/O. I/O network redundant ControlNet cabling, taps, and fiber adapters shall be removed and replaced with a fiber Ethernet ring through each associated RIO rack.
Existing Ethernet switches and rings, one ring for SCADA and one for PLC peer-to-peer and PanelView OITs, shall remain in place. Only one of the two redundant PLCs is still installed in the panel. The following PLC, RIO, and related key components shall be upgraded:
1. Rack 0 (PLC-300 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge– already removed
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory– already removed
e. Qty. 2 – 1756-EN2T – Ethernet/IP Module– already removed
f. Qty. 1 – 1756-RM – Redundancy Module
2. Rack 1 (PLC-300 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-EN2T – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
3. Rack 2 (RIO-300 Node 3)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 3 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-EN2T Ethernet/IP Bridge
e. Qty. 1 – MVI56-MCMR Prosoft Modbus RTU Comm Module (RS-422 connection to two
(2) polymer pumps, two (2) fluoride pumps, and two (2) phosphoric acid pumps. RS-485 connection to two (2) alum pumps)
f. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4. Rack 3 (RIO-300 Node 4)
a. Qty. 1 – 1756-A17 – 17 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 12 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 3 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
f. Qty. 1 – 1756-EN2T Ethernet/IP Bridge
5. Qty. 1 – 2711P-B12C4D1 PanelView Plus 1250
4.1.4 CP-11-300-1 Floc/Sed Basins 1,2,3 RIO-300-1
CP-11-300-1 RIO panel redundant ControlNet cabling, taps, and fiber repeater modules shall be removed and replaced with Ethernet to insert the RIO rack into a fiber DLR from PLC-300. The following RIO and related key components shall be replaced:
1. Rack 0 (RIO-300-1)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
d. Qty. 3 – 1756-IF6I – 6 Point Isolated Analog Input Module
e. Qty. 5 – 1756-IA16 - 16 Point 120 VAC Digital Input Module
f. Qty. 1 – 1756-EN2T Ethernet/IP Bridge
4.1.5 RIO-XXX Chemical Building Existing I/O
The RIO-XXX panel Flex Ethernet/IP adaptor and associated Flex I/O shall be replaced with Flex 5000 series modules and connected into a fiber DLR from PLC-300. The existing Prosoft Modbus Flex module shall also be replaced with a Prosoft Modbus EIP to Serial Gateway. The following RIO and related key components shall be replaced:
1. Rack 0 (RIO-XXX)
a. Qty. 1 – 1794-PS13 Flex Power Supply
b. Qty. 1 – 1794-AENT – Flex Ethernet/IP Adapter
c. Qty. 3 - 1794-IA16 – 16 Point 120 VAC Digital Input Module
d. Qty. 1 – 1794-OA8 – 8 Point 120 VAC Digital Output Module
e. Qty. 2 – 1794-IE8 - 8 Point Analog Input Module
f. Qty. 1 – MVI94-MCM Prosoft Modbus RTU Comm Module
4.1.6 CP-11-300-2 Floc/Sed Basins 4,5,6 RIO-300-2
CP-11-300-2 RIO panel redundant ControlNet cabling, taps, and fiber repeater modules shall be removed and replaced with Ethernet to insert the RIO rack into a fiber DLR from PLC-300. The following RIO and related key components shall be replaced:
1. Rack 0 (RIO-300-2)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
d. Qty. 3 – 1756-IF6I – 6 Point Isolated Analog Input Module
e. Qty. 5 – 1756-IA16 - 16 Point 120 VAC Digital Input Module
f. Qty. 1 – 1756-EN2T Ethernet/IP Bridge
4.1.7 CP-11-300-3 Sodium Hypochlorite Building RIO-300-3
CP-11-300-3 RIO panel redundant ControlNet cabling, taps, and fiber repeater modules shall be removed and replaced with Ethernet to insert the RIO rack into a fiber DLR from PLC-300. The following RIO and related key components shall be replaced:
1. Rack 0 (RIO-300-3)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
d. Qty. 2 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
e. Qty. 1 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
f. Qty. 1 – 1756-EN2T Ethernet/IP Bridge
4.1.8 SHBPLC1 Sodium Hypochlorite Existing I/O
The Sodium Hypochlorite SHBPLC1 RIO panel Flex Ethernet/IP adaptor and associated Flex I/O shall be replaced with Flex 5000 series modules and connected by fiber Ethernet to insert the RIO rack into a DLR from PLC-300. The existing PLX31-EIP-MBS Prosoft Modbus modules shall remain in place.
All old ControlNet hardware shall be removed. The following PLC and related key components shall be replaced:
1. Rack 0 (SHBPLC1)
a. Qty. 1 – 1794-PS13 Flex Power Supply
b. Qty. 1 – 1794-AENT – Flex Ethernet/IP Adapter
c. Qty. 2 - 1794-IA16 – 16 Point 120 VAC Digital Input Module
d. Qty. 2 – 1794-IE8 - 8 Point Analog Input Module
e. Qty. 1 – MVI94-MCM Prosoft Modbus RTU Comm Module – remove. Already replaced with PLX31-EIP-MBS Gateway. (Modbus connection to seven (7) sodium hypochlorite pumps)
f. Qty. 1 – PLX31-EIP-MBS4 Prosoft Ethernet/IP to Modbus Serial Gateway
4.1.9 CP-11-300-4 Calcium Hydroxide Building RIO-300-4
CP-11-300-4 RIO panel redundant ControlNet cabling, taps, and fiber repeater modules shall be removed and replaced with Ethernet to insert the RIO rack into a fiber DLR from PLC-300. The following RIO and related key components shall be replaced:
1. Rack 0 (RIO-300-4)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
d. Qty. 5 – 1756-IA16I - 16 Point 120 VAC Digital Input Module
e. Qty. 2 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
f. Qty. 1 – 1756-EN2T Ethernet/IP Bridge
4.1.10 CBPLC1 Calcium Hydroxide Existing I/O
The Calcium Hydroxide CBPLC1 RIO panel Flex Ethernet/IP adaptor and associated Flex I/O shall be replaced with Flex 5000 series modules and connected into a fiber DLR from PLC-300. The existing Prosoft Modbus Flex module shall also be replaced with a Prosoft EIP to Serial Gateway. All old ControlNet hardware shall be removed. The following PLC and related key components shall be replaced:
1. Rack 0 (CBPLC1)
a. Qty. 1 – 1794-PS13 Flex Power Supply
b. Qty. 1 – 1794-AENT – Flex Ethernet/IP Adapter
c. Qty. 2 - 1794-IA16 – 16 Point 120 VAC Digital Input Module
d. Qty. 1 - 1794-OA8 – 8 Point 120 VAC Digital Output Module
e. Qty. 2 – 1794-IE8 - 8 Point Analog Input Module
f. Qty. 1 – MVI94-MCM Prosoft Modbus RTU Comm Module (RS-485 connection to three
(3) calcium hydroxide pumps)
4.1.11 CP-11-470 Filter Building Control Room
The CP-11-470 cabinet in the filter control room contains three redundant PLCs. PLC-401 for Filters 1 through 6, PLC-407 for filters 7 through 13, and PLC-470 for Filter Backwash. The 1756-L62 redundant ControlLogix PLCs in all three PLCs shall be replaced with equivalent or better 5580 ControlLogix controllers and 1756 modules. I/O network redundant ControlNet cabling, taps, and fiber repeater modules shall be removed and replaced with a fiber switch ring through each associated RIO rack. For the PLC-401 and PLC-407 I/O networks, a new Cisco IE3500-8P3S-A switch shall be provided in each filter RIO cabinet. For the PLC-470 I/O network an Ethernet fiber DLR shall be connected through each associated RIO rack. Existing Ethernet switches and rings in CP-11-470, one ring for SCADA and one for PLC peer-to-peer and PanelView OITs, shall remain in place. The following PLC and related key components shall be upgraded or replaced if missing:
1. Rack 0 Filters 1 – 6 (PLC-401 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENBT – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
2. Rack 1 Filters 1 – 6 (PLC-401 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 1 – 1756-ENBT – Ethernet/IP Module
f. Qty. 1 – 1756-EN2T – Ethernet/IP Module
g. Qty. 1 – 1756-RM – Redundancy Module
3. Rack 0 Filters 7 – 13 (PLC-407 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENET – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
4. Rack 1 Filters 7 – 13 (PLC-407 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENET – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
5. Rack 0 Filter Backwash (PLC-470 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENET – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
6. Rack 1 Filter Backwash (PLC-470 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENET – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
7. Rack 2 Filter Backwash (RIO-470 Node 3)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 2 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-OF6I – 6 Point Isolated Analog Input Module
e. Qty. 1 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
f. Qty. 1 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
g. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.12 CP-11-401-1 Filters 1 and 2 Pipe Gallery RIO-401-1
CP-11-401-1 RIO panel redundant ControlNet cabling and taps shall be removed and replaced with Ethernet to insert the RIO rack into a fiber switch ring from PLC-401. A new Cisco IE3500-8P3S-A switch shall be provided for connection to the ring. The following RIO and related key components shall be replaced:
1. Rack 2 (RIO-401-1 Node 3)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 5 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-OF6CI – 6 Point Isolated Analog Current Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
2. Rack 3 (RIO-401-1 Node 4)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 5 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 2 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.13 CP-11-401-2 Filters 3 and 4 Pipe Gallery RIO-401-2
CP-11-401-2 RIO panel redundant ControlNet cabling and taps shall be removed and replaced with Ethernet to insert the RIO rack into a fiber switch ring from PLC-401. A new Cisco IE3500-8P3S-A switch shall be provided for connection to the ring. The following RIO and related key components shall be replaced:
1. Rack 4 (RIO-401-2 Node 5)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 6 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-OF6CI – 6 Point Isolated Analog Current Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
2. Rack 5 (RIO-401-2 Node 6)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 5 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 2 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.14 CP-11-401-3 Filters 5 and 6 Pipe Gallery RIO-401-3
CP-11-401-3 RIO panel redundant ControlNet cabling and taps shall be removed and replaced with Ethernet to insert the RIO rack into a fiber switch ring from PLC-401. A new Cisco IE3500-8P3S-A switch shall be provided for connection to the ring. The following RIO and related key components shall be replaced:
1. Rack 6 (RIO-401-3 Node 7)
a. Qty. 1 – 1756-A17 – 17 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 4 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-OF6CI – 6 Point Isolated Analog Current Output Module
e. Qty. 5 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
f. Qty. 2 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
g. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.15 CP-11-407-1 Filters 7, 8 and 9 Pipe Gallery RIO-407-1
CP-11-407-1 RIO panel redundant ControlNet cabling and taps shall be removed and replaced with Ethernet to insert the RIO rack into a fiber switch ring from PLC-407. A new Cisco IE3500-8P3S-A switch shall be provided for connection to the ring. The following RIO and related key components shall be replaced:
2. Rack 2 (RIO-407-1 Node 3)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 8 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-OF6CI – 6 Point Isolated Analog Current Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
3. Rack 3 (RIO-407-1 Node 4)
a. Qty. 1 – 1756-A17 – 17 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 8 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 4 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.16 CP-11-407-2 Filters 10 and 11 Pipe Gallery RIO-407-2
CP-11-407-2 RIO panel redundant ControlNet cabling and taps shall be removed and replaced with Ethernet to insert the RIO rack into a fiber switch ring from PLC-407. A new Cisco IE3500-8P3S-A switch shall be provided for connection to the ring. The following RIO and related key components shall be replaced:
1. Rack 4 (RIO-407-2 Node 5)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 6 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-OF6CI – 6 Point Isolated Analog Current Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
2. Rack 5 (RIO-407-2 Node 6)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 5 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 3 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.17 CP-11-407-3 Filters 12 and 13 Pipe Gallery RIO-407-3
CP-11-407-1 RIO panel redundant ControlNet cabling and taps shall be removed and replaced with Ethernet to insert the RIO rack into a fiber switch ring from PLC-407. The following RIO and related key components shall be replaced:
1. Rack 6 (RIO-407-3 Node 7)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 5 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 – 1756-OF6CI – 6 Point Isolated Analog Current Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
2. Rack 7 (RIO-407-3 Node 8)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 5 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 3 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.18 CP-11-470-1 Air Blowers Settled Solids Building RIO-470-1 CP-11-470-1 RIO panel redundant ControlNet cabling, taps, and fiber repeater modules shall be removed and replaced with Ethernet to insert the RIO rack into a fiber ring from PLC-470. The following RIO and related key components shall be replaced:
1. Rack 0 (RIO-470-1 Node 4)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 2 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
e. Qty. 1 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
f. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4.1.19 05-LCP-501 Sedimentation Basin Draw-Off Valves PLC-501 05-LCP-501 is a newer PLC that is already Ethernet capable and communicating over fiber to the plant network. Only the 1756-L75 processor shall be replaced to achieve upgrade standardization.
4.1.20 CP-11-700 Finished Water Pump Station PLC-700
The CP-11-700 redundant 1756-L62 ControlLogix PLCs shall be replaced with equivalent or better 5580 ControlLogix controllers, 1756 I/O, and communication modules. I/O network redundant ControlNet cabling and taps shall be removed and replaced with a fiber DLR through each associated RIO rack. Existing Ethernet rings, one for SCADA and one for PLC peer-to-peer and PanelView OITs, shall remain in place. NOTE: CP-11-700 may potentially be replaced under a separate project. Please separate the cost for this item so it can easily be removed from scope if required. The following PLC and related key components shall be replaced:
1. Rack 0 FWPS (PLC-700 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENET – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
2. Rack 1 FWPS (PLC-700 Node 21/22)
a. Qty. 1 – 1756-A7 – 7 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 1 - 1756-CN2R –Redundant ControlNet Bridge
d. Qty. 1 - 1756-L62 – ControlLogix Processor, 4 MB Memory
e. Qty. 2 – 1756-ENET – Ethernet/IP Module
f. Qty. 1 – 1756-RM – Redundancy Module
3. Rack 2 (RIO-700 Node 3)
a. Qty. 1 – 1756-A10 – 10 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 5 – 1756-IF6I – 6 Point Isolated Analog Input Module
d. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
4. Rack 3 (RIO-700 Node 4)
a. Qty. 1 – 1756-A13 – 13 Slot Chassis
b. Qty. 1 – 1756-PA75 120 VAC Power Supply
c. Qty. 6 – 1756-IA16I - 16 Point 120 VAC Isolated Digital Input Module
d. Qty. 2 – 1756-OA16 - 16 Point 120 VAC Digital Output Module
e. Qty. 1 - 1756-CNBR – Redundant ControlNet Bridge
5. 2711P-B12C4D1 - PanelView Plus 1250
4.1.21 Dechlorination PLC 05-LCP-403
The Dechlorination PLC and OIT shall be replaced with a CompactLogix 5069 series PLC and a 10” PanelView Plus 7 Standard, respectively. Replace the unmanaged Ethernet switch with a 5-port Stratix 2000. Due to size constraints in the existing panel, the entire 05-LCP-403 panel shall be replaced. Drawings provided in Appendix A. The following components shall be included:
6. Qty. 1 – 1766-L32BWAA MicroLogix 1400
7. Qty. 1 – 2711PC-T10C4D1 10” PanelView Plus Compact Terminal
8. Qty. 1 – Hirschmann Spider 5TX Unmanaged Ethernet Switch
4.1.22 Filter Consoles 1 - 13
PanelView Plus 1250 operator interface terminals (2711P-K12C4D1) are installed for each filter (24VDC, Ethernet). All OITs shall be replaced with an equivalent PanelView Plus 7 Performance terminal. Each PanelView terminal shall be connected in a star configuration to the new filter RIO Cisco IE3500-8P3S-A switch associated with its assigned filter.
4.1.23 SCADA HMI System Replacement
Due to facility-wide COA standardization requirements, the iFix SCADA HMI system shall be replaced with AVEVA System Platform, formerly Wonderware. The current system at the Chattahoochee WTP is iFix version 6.1. Servers, workstations, and AVEVA Licensing shall be provided by the COA. The following computers located in the filter building are included:
1. Filter Building
a. COMP-11-1 Primary SCADA Server
b. COMP-11-2 Secondary SCADA Server
c. HIS-11-1 Historian Server
d. OWS-11-1 Operator Workstation
e. OWS-11-2 Operator Workstation
f. OWS-11-3 I&C Supervisor Workstation
g. OWS-11-4 Plant Supervisor Workstation
h. OWS-11-5 Engineering Workstation
i. OWS-11-6 Superintendent Workstation
2. MWS-11 Mobile Workstation
3. Chemical Building
a. OWS-11-7 Operator Workstation
b. OWS-11-8 Operator Workstation
4. Raw Water Pump Station
a. OWS-11-9 Operator Workstation
4.2 Products and Services
The following list is a summary of the products and services required for the upgrades in this SOW:
1. Prior to any programming or connection to COA equipment, all VENDOR programming personnel shall be subject to a background check with results provided to the COA. Connection to COA computers, PLCs, OITs, or online programming services prior to successful completion of the background check is prohibited.
2. Perform a site survey to retrieve the iFix application, PanelView applications, all programs from existing PLCs, and assess the entire existing control system to confirm consistency with the SOW as described herein. If necessary, additional site visits may be coordinated by the VENDOR with the COA during the project at no additional cost to the COA.
3. Provide shop drawings, hardware submittals, and software submittals in PDF format for all panel and programming modifications for approval by the COA.
4. Upgrade all programming to the latest firmware version available at the time of purchase to be compatible with new hardware. Any required program instruction modifications, communication configuration changes, and I/O configuration changes shall be included.
5. Perform a witnessed Factory Acceptance Test (FAT) of the entire new control system infrastructure at the VENDOR’s facility. VENDOR shall stage all servers, workstations, PLCs, and OITs, networked together, and confirm all AVEVA screen functionality. Due to actual servers being in use at the plant, VENDOR shall provide the servers and workstations as virtual machines for the test.
6. All fiber and CAT 5E cables shall be provided by the VENDOR
7. Installation, commissioning, and start up all new control panel components and programming.
AVEVA servers shall be provided as virtual machines to be installed on existing COA servers.
8. Train COA personnel on any operational and maintenance differences between the existing and upgraded system
9. Attend weekly progress meetings and additional technical coordination meetings as needed.
10. Ship of all equipment included in the scope of supply to the WTP. Coordinate climate controlled storage at the plant with the COA if time is required between delivery and installation.
4.3 Task Breakdown
The project shall be delivered and invoiced according to the following Task schedule.
4.3.1 Task 1 – Implementation Plan, Schedule, Field Survey
1. VENDOR will submit an Implementation Plan and Schedule to COA for review and approval
2. VENDOR shall perform a one day field assessment panel survey with VENDOR personnel who will be involved with the on-site work and submit a memo to the COA outlining assessment.
3. VENDOR will attend a weekly progress meeting online with the COA.
4.3.2 Task 2 – Submittals and Test Plans
1. VENDOR will provide shop drawing submittals and equipment data sheets with equipment identified by tag number for all work to be performed. Submittals to be reviewed and approved by the COA before any hardware is purchased.
2. During the field survey, VENDOR shall identify long-lead items and expedite related submittals to facilitate early approval and purchase.
3. Based on the site survey and best practice design, VENDOR shall confirm manufacturer’s recommended replacements, actual required quantities, model numbers
4. PLC Program Upgrade Plan - VENDOR shall submit an Upgrade Plan for review and approval by the COA. The Plan shall include descriptions of all PLC configuration modifications required.
Description shall also be provided for any changes to Prosoft programming as required for communication to the existing Modbus devices
5. For any PLC tag references that change as a requirement for this hardware update, VENDOR shall provide programming services to update existing PanelView applications and include such changes in the HMI screen replacements.
6. VENDOR shall submit new AVEVA HMI screens for review and approval.
7. Factory Acceptance Test (FAT) Plan - VENDOR shall provide and submit a FAT Plan for review and approval by the COA. The FAT Plan shall include an item by item checklist for each new AVEVA HMI screen.
8. Commissioning and Startup (C&SU) - Plan VENDOR will submit a C&SU Plan for review and approval by the COA. The Plan shall include a detailed sequence in checklist format for replacing, installing, and testing all hardware and software.
4.3.3 Task 3 – Equipment Purchase
1. After submittal approval, VENDOR shall purchase and provide component quantities for the plant as outlined in Sections 4.1 and 4.2 above and in accordance with approved submittals
2. Long lead items identified during Task 2 shall be expedited for purchase
3. Ethernet Cat 5E and multimode fiber cable shall be included in equipment purchase. Two thousand feet of cable shall be used as the basis of bid to be provided and installed by the VENDOR. Excess fiber shall remain the property of the COA. If it is determined that additional fiber is needed, the VENDOR shall coordinate with the COA to determine cost and source.
VENDOR to confirm routing and length required during the field survey.
4.3.4 Task 4 - FAT and Equipment Storage
1. VENDOR shall successfully complete witnessed factory testing of the control system at the
VENDOR’s facility based on the approved FAT plan utilizing the actual components purchased for the project.
2. VENDOR shall plan for four (4) days for the FAT with COA and COA’s Program Manager CONSULTANT in attendance. VENDOR shall provide expenses for lodging and meals for three
(3) COA employees for the four (4) days. VENDOR shall provide 14 days advanced notice for the
FAT.
3. VENDOR shall lead coordination to integrate communications between all PLCs, OITs, and the SCADA system. Systems shall be connected as replica of the plant network at the factory test location to the extent possible to test and demonstrate all network, control, and monitoring capabilities. This shall include simulated MODBUS communications for chemical pumps.
4. VENDOR shall submit a summary of the FAT results to the COA for review and comment.
5. VENDOR shall package, store, and provide moisture protection for all provided equipment and supplies until the COA is ready to accept delivery at the project sites.
6. VENDORCOA
4.3.5 Task 5 – Equipment Delivery
1. VENDOR shall be responsible for delivering equipment provided from storage to the
Chattahoochee WTP.
4.3.6 Task 6 – Installation, Replacement and Onsite Testing
1. VENDOR shall remove all existing PanelView OITs, PLCs, and any other affected control panel equipment in accordance with the sequence described in the C&SU Plan and return to the COA
2. VENDOR shall provide all labor, material, equipment, and supplies to successfully install and commission the new system described in this SOW and submit a report summarizing the commissioning results to the COA
3. VENDOR shall provide five (5) consecutive days of operational testing at the project site with COA field staff on the operation of the new system. VENDOR shall provide 14 days advanced notice of the testing.
4.3.7 Task 7 - Training
1. VENDOR shall provide three (3) training sessions for operations personnel to cover all shifts for the new AVEVA HMI screens
2. VENDOR shall provide One (1) day of maintenance training for system configuration and maintenance to cover any new features of upgraded hardware and software
4.3.8 Task 8 – O&M Manuals and As-Builts
1. VENDOR shall update and submit new as-built PLC panel, communication, and network drawings to the COA for approval.
2. VENDOR shall provide new hardware and software O&M Manuals for all supplied components.
3. VENDOR shall submit applicable reports, drawings, O&M manuals, product information, warranties and As-Builts in electronic format within 30 days of commissioning of all systems to the COA.
4.4 Clarifications and Assumptions
1. Existing PLC control logic and functions will not be modified unless required due to deprecated or modified PLC instruction support in new software/firmware versions.
2. VENDOR shall follow UL-508A requirements and practices but is not responsible for re-labeling the panels UL-508A compliant.
3. The VENDOR shall notify and schedule all activities with the COA.
4. The VENDOR shall verify all information provided and notify the COA of any potential changes needed in the SOW. VENDOR shall provide all requests for deviation in writing and shall not deviate from the SOW without prior approval from the COA
5. All work is to be performed by the VENDOR in coordination with COA Operations in a manner that will maintain the required plant operations.
6. The following Equipment and Services are NOT part of the VENDOR’s scope of supply and will be provided by the COA if required:
a. All Utilities
b. Electrical and Mechanical Installation Services not specifically mentioned in this SOW.
c. Except for communication cable, any wiring and tubing external to control panels.
d. Piping and valves
7. All parts and equipment removed shall remain the property of the COA
8. Latest firmware upgrades and patches shall be applied prior to connection to the plant Network.
5 PROPOSAL
1. Proposal shall include a description of the intended project approach for replacing the ControlNet network with Ethernet/IP and iFix with AVEVA System Platform.
2. Proposal should include a description of the intended project approach for adherence and compliance with Technical Specifications (Exhibit A – Technical Specifications)
3. Proposal shall include three (3) project references for previous control system upgrades of similar size and scope performed by the bidder
4. Proposal shall include resumes of the bidder’s intended project manager and lead programmer.
5. Bid shall be delivered using the Schedule of Values breakdown shown below.
6. Proposal shall include project costs and contingencies for project delays
6 DELIVERABLES AND SCHEDULE OF VALUES
Task Description Days From
NTP Amount 1 Implementation Plan, Schedule, Field Survey 30 2 Submittals and Test Plans 90 3 Equipment Purchase 180 4 FAT and Equipment Storage 210 5 Equipment Delivery 240 6 Installation and Onsite Testing 330 7 Training 345 8 O&M Manuals and As-Builts 360 9 CP-11-700 FWPS PLC-700 Upgrade n/a
10 Contingency n/a 11 FAT Lodging and Meals for COA n/a
7 APPENDIX A
1. iFix Screen List (or provide a screen count to help with estimates)
2. Dechlorination PLC 05-LCP-403 Drawings
| 1 INTRODUCTION |
| 2 LOCATION |
| 3 BACKGROUND |
| 4 SCOPE OF WORK (SOW) |
| 4.1 Control Panels – Programmable Logic Controllers |
| 4.1.1 CP-10-101 Raw Water Pump Station PLC-101 |
| 4.1.2 CP-10-102 Raw Water Intake PLC-102 |
| 4.1.3 CP-11-300 Chemical Building PLC-300 |
| 4.1.4 CP-11-300-1 Floc/Sed Basins 1,2,3 RIO-300-1 |
| 4.1.5 RIO-XXX Chemical Building Existing I/O |
| 4.1.6 CP-11-300-2 Floc/Sed Basins 4,5,6 RIO-300-2 |
| 4.1.7 CP-11-300-3 Sodium Hypochlorite Building RIO-300-3 |
| 4.1.8 SHBPLC1 Sodium Hypochlorite Existing I/O |
| 4.1.9 CP-11-300-4 Calcium Hydroxide Building RIO-300-4 |
| 4.1.10 CBPLC1 Calcium Hydroxide Existing I/O |
| 4.1.11 CP-11-470 Filter Building Control Room |
| 4.1.12 CP-11-401-1 Filters 1 and 2 Pipe Gallery RIO-401-1 |
| 4.1.13 CP-11-401-2 Filters 3 and 4 Pipe Gallery RIO-401-2 |
| 4.1.14 CP-11-401-3 Filters 5 and 6 Pipe Gallery RIO-401-3 |
| 4.1.15 CP-11-407-1 Filters 7, 8 and 9 Pipe Gallery RIO-407-1 |
| 4.1.16 CP-11-407-2 Filters 10 and 11 Pipe Gallery RIO-407-2 |
| 4.1.17 CP-11-407-3 Filters 12 and 13 Pipe Gallery RIO-407-3 |
| 4.1.18 CP-11-470-1 Air Blowers Settled Solids Building RIO-470-1 |
| 4.1.19 05-LCP-501 Sedimentation Basin Draw-Off Valves PLC-501 |
| 4.1.20 CP-11-700 Finished Water Pump Station PLC-700 |
| 4.1.21 Dechlorination PLC 05-LCP-403 |
| 4.1.22 Filter Consoles 1 - 13 |
| 4.1.23 SCADA HMI System Replacement |
| 4.2 Products and Services |
| 4.3 Task Breakdown |
| 4.3.1 Task 1 – Implementation Plan, Schedule, Field Survey |
| 4.3.2 Task 2 – Submittals and Test Plans |
| 4.3.3 Task 3 – Equipment Purchase |
| 4.3.4 Task 4 - FAT and Equipment Storage |
| 4.3.5 Task 5 – Equipment Delivery |
| 4.3.6 Task 6 – Installation, Replacement and Onsite Testing |
| 4.3.7 Task 7 - Training |
| 4.3.8 Task 8 – O&M Manuals and As-Builts |
4.4 Clarifications and Assumptions
| 5 PROPOSAL |
| 6 DELIVERABLES AND SCHEDULE OF VALUES |
| 7 APPENDIX A |
| 8 EXHIBIT A – TECHNICAL SPECIFICATIONS |
| 01260 Contract Modification Procedures.pdf |
| PART 1 - GENERAL |
| 1.1 SCOPE |
| A. Without invalidating the Contract and without notice to any surety, Owner may, at any time or from time to time, order additions, deletions, or revisions in the Work by a Change Order, or a Work Change Directive. Upon receipt of any such document, ... |
| 1. Owner may, in anticipation of possibly ordering an addition, deletion or revision to the Work, request Contractor to prepare a proposal of cost and times to perform Owner’s contemplated changes in the Work. Contractor’s written proposal shall be tr... |
| 2. Contractor is not authorized to proceed on an Owner contemplated change in the Work prior to Contractor’s receipt of a Change Order (or Work Change Directive) incorporating such change into the Work. |
| 3. Owner’s request for proposal or Contractor’s failure to submit such proposal within the required time period will not justify a claim for an adjustment in Contract Price or Contract Time (or Milestones). |
| 4. The Owner shall not be liable to the Contractor for any costs associated with the preparation of proposal associated with the Owner’s contemplated changes in the Work. |
| B. If Owner and Contractor are unable to agree on entitlement to, or on the amount or extent, if any, of an adjustment in the Contract Price or Contract Times, or both, that should be allowed as a result of a Work Change Directive, a Claim may be made. |
| C. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented, except in the case ... |
| PART 2 - PRODUCTS (NOT USED) |
| PART 3 - EXECUTION |
| 3.1 EXECUTION OF CHANGE ORDERS |
| A. Owner and Contractor shall execute appropriate Change Orders recommended by the City’s Authorized Representative covering: |
| 1. changes in the Work which are: (i) ordered by Owner, (ii) required because of acceptance of defective Work or Owner’s correction of defective Work, or (iii) agreed to by the parties; |
| 2. changes in the Contract Price or Contract Times which are agreed to by the parties, including any undisputed sum or amount of time for Work actually performed in accordance with a Work Change Directive; and |
| 3. changes in the Contract Price or Contract Times which embody the substance of any written |
| 4. decision rendered by Engineer; provided that, in lieu of executing any such Change Order, an appeal may be taken from any such decision in accordance with the provisions of the Contract Documents and applicable Laws and |
| 5. Regulations, but during any such appeal, Contractor shall carry on the Work and adhere to the Progress Schedule. |
| B. In signing a Change Order, the Owner and Contractor acknowledge and agree that: |
| 1. The stipulated compensation (Contract Price or Contract Time, or both) set forth in the Change Order includes payment for: |
| a. the Cost of the Work covered by the Change Order, |
| b. Contractor’s fee for overhead and profit, |
| c. interruption of Progress Schedules, |
| d. delay and impact, including cumulative impact, on other work under the Contract Documents, and extended home office and jobsite overhead; |
| 2. the Change Order constitutes full mutual accord and satisfaction for the change to the Work; |
| 3. No reservation of rights to pursue subsequent claims on the Change Order will be made by either party; and |
| 4. No subsequent claim or amendment of the Contract Documents will arise out of or as a result of the Change Order. |
| C. Notification of Surety: |
| D. Claims and Disputes: |
| 1. City’s Authorized Representative’s Decision Required: All Claims shall be referred to the City’s Authorized Representative for decision. A decision by the City’s Authorized Representative shall be required as a condition precedent to any exercise b... |
| 2. Notice: Written notice stating the general nature of each Claim shall be delivered by the claimant to City’s Authorized Representative to the Contract promptly (but in no event later than 30 calendar days after the start of the event giving rise th... |
| 3. City’s Authorized Representative may allow additional time for claimant to submit additional or more accurate data in support of such Claim. A Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of Paragrap... |
| 4. City’s Authorized Representative Action: City’s Authorized Representative will review each Claim and, within 30 calendar days after receipt of the last submittal of the claimant, if any, and take one of the following actions in writing: |
| 5. deny the Claim in whole or in part; |
| 6. approve the Claim; or |
| 7. notify the party that the City’s Authorized Representative is unable to resolve the Claim if, in the City Authorized Representative’s sole discretion, it would be inappropriate for the City’s Authorized Representative to do so. For purposes of furt... |
| 8. In the event that the City’s Authorized Representative does not take action on a Claim within said 30 days, the Claim shall be deemed denied. |
| 9. City’s Authorized Representative’s written action will be final and binding. |
| 10. No Claim for an adjustment in Contract Price or Contract Times will be valid if not submitted in accordance with this specification. |
| 3.2 CHANGE OF CONTRACT PRICE |
| A. Change of Contract Price: |
| 1. The Contract Price may only be changed by a Change Order. Any Claim for an adjustment in the Contract Price shall be based on written notice submitted by the party making the Claim to the City’s Authorized Representative. |
| 2. The value of any Work covered by a Change Order or of any Claim for an adjustment in the Contract Price will be determined as follows: |
| a. where the Work involved is covered by unit prices contained in the Contract Documents, by application of such unit prices to the quantities of the items involved; or |
| b. where the Work involved is not covered by unit prices contained in the Contract Documents, by a mutually agreed lump sum value fixed by the Owner or by unit price values fixed by the Owner (which may include an allowance for overhead and profit); or |
| c. where the Work involved is not covered by unit prices contained in the Contract Documents and agreement to a lump sum is not reached on the basis of the Cost of the Work plus a Contractor’s fee for overhead and profit. |
| 3. Contractor’s Fee: The Contractor’s fee for overhead and profit shall be determined as follows: |
| a. a mutually acceptable fixed fee; or |
| b. if a fixed fee is not agreed upon, then a fee based on the Section 01200 Measurement and Payment, Item - Time and Materials. |
| B. Change of Contract Times: |
| 1. The Contract Times may only be changed by a Change Order. Any Claim for an adjustment in the Contract Times shall be based on written notice submitted by the party making the Claim to the Engineer and the other party to the Contract. |
| 2. Any adjustment of the Contract Times covered by a Change Order or any Claim for an adjustment in the Contract Times will be determined in accordance with the provisions of this specification. |
| C. Delays: |
| 1. Where Contractor is prevented from completing any part of the Work within the Contract Times due to delay beyond the control of Contractor, the Contract Times will may be extended in an amount equal to the time lost due to such delay if a Claim is ... |
| 2. If Owner or other contractors or utility owners performing other work for Owner, or anyone for whom Owner is responsible, delays, disrupts, or interferes with the performance or progress of the Work, then Contractor shall be entitled to an equitabl... |
| 3. If Contractor is delayed in the performance or progress of the Work by fire, flood, epidemic, abnormal weather conditions, acts of God, acts or failures to act of utility owners not under the control of Owner, or other causes not the fault of and b... |
| 4. Owner, Engineer, and their officers, directors, members, partners, employees, agents, consultants, or subcontractors shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of e... |
| 5. Contractor shall not be entitled to an adjustment in Contract Price or Contract Times for delays within the control of Contractor. Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the ... |
| 01297 Applications for Payment.pdf |
| PART 1 - GENERAL |
| 1.1 REQUIREMENTS INCLUDED |
| A. Submit Applications for Payment to the City’s Authorized Representative in accordance with the schedule established by Conditions of the Contract and Agreement Between City and Contractor. |
| 1.2 RELATED REQUIREMENTS |
| A. Agreement Between City and Contractor. |
| B. Conditions of the Contract: Progress Payments, Retainages and Final Payment. |
| C. Section 01350 Project Document Tracking and Control System |
| D. Section 01720: Project Record Documents. |
| 1.3 FORMAT AND DATA REQUIRED |
| A. Submit applications in E-builder software. |
| B. Provide itemized data on continuation sheet: |
| 1.4 PREPARATION OF APPLICATION FOR EACH PROGRESS PAYMENT |
| A. Application Form: |
| 1. Fill in required information, including that for Change Orders executed prior to date of submittal of application. |
| 2. Fill in summary of dollar values to agree with respective totals indicated on continuation sheets. |
| 3. Execute certification with signature of a responsible officer of Contract firm. |
| 4. Application shall be incorporated into the latest version of E-builder software. |
| B. Continuation Sheets: |
| 1. Fill in total list of all scheduled component items of Work, with item number and scheduled dollar value for each item. |
| 2. Fill in dollar value in each column for each scheduled line item when work has been performed or products stored. |
| 3. Round off values to nearest dollar, or as specified for Schedule of Values. |
| 4. List each Change Order executed prior to date of submission, at the end of the continuation sheets. |
| 5. List by Change Order Number, and description, as for an original component item of work. |
| 6. To receive approval for payment on component material stored on site, submit copies of the original invoices with the application for payment first made for these materials. Copies of paid invoices must be submitted for all materials stored longer... |
| 1.5 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS |
| A. When the City’s Authorized Representative requires substantiating data; Contractor shall submit suitable information, with a cover letter identifying: |
| 1. Project. |
| 2. Application number and date. |
| 3. Detailed list of enclosures. |
| 4. For stored products: |
| a. Item number and identification as shown on application. |
| b. Description of specific material. |
| B. Submit one copy of data and cover letter for each copy of application. |
| C. As a prerequisite for payment, Contractor is to submit a "Surety Acknowledgment of Payment" letter showing amount of progress payment, which the Contractor is requesting. |
| D. The Contractor is to maintain an updated set of drawings to be used as record drawings in accordance with Section 01720 Record Documents. As a prerequisite for monthly progress payments, the Contractor is to exhibit the updated Record Drawings for... |
| E. The Contractor shall submit all applicable test reports of installed products in order to request payment for that product. |
| F. The Contractor shall maintain an updated construction schedule. As a prerequisite for monthly progress payments, Contractor shall submit the updated construction schedule with the applications for progress payments. If the Contractor fails to sub... |
| G. The Contractor shall demonstrate, as a prerequisite for monthly progress payments, compliance with all requirements specified in Erosion and Sedimentation Control requirements of this project to the City. If the Contractor fails to demonstrate com... |
| H. The Contractor shall provide, as a prerequisite for monthly progress payments, an accumulating cost curve (tabular and diagram), indicating schedule, forecast and actual progress. |
| 1.6 PREPARATION OF APPLICATION FOR FINAL PAYMENT |
| A. Fill in Application form as specified for progress payments. |
| B. Use continuation sheet for presenting the final statement of accounting. |
| 1.7 SUBMITTAL PROCEDURE |
| A. Submit Applications for Payment to the City at the times stipulated in the Agreement. Application for Payment request shall be submitted through eBuilder. |
| B. Number: Five copies of each Application. |
| C. When the City’s Authorized Representative finds Application properly completed and correct, he/she will transmit certificate for payment to City for approval and processing. |
| PART 2 - PRODUCTS (NOT USED) |
| PART 3 - EXECUTION (NOT USED) |
| 01300 Submittal Procedures.pdf |
| PART 1 - GENERAL |
| 1.1 DESCRIPTION |
| A. This Section specifies the general methods and requirements of submissions applicable to the following work-related Submittals: Shop Drawings, Product Data, Samples, Requests For Information, Construction Schedules, Work Plan, and Submittal Schedul... |
| 1.2 GENERAL PROCEDURES FOR SUBMITTALS |
| A. Coordination of Submittal Times: Prepare and transmit each submittal sufficiently in advance of performing the related work or other applicable activities, or within the time specified in the individual work sections of the Specifications, so that... |
| 1.3 SHOP DRAWINGS, WORKING DRAWINGS, PRODUCT DATA, SAMPLES, PRECONSTRUCTION VIDEO |
| A. Shop Drawings: |
This is the start of the file's text. The full file is on GovTribe.