PS-7223-26_Draft_Agreement_.pdf
PDF 1 MB Posted
- Solicitation number
- PS-7223-26/LNF
- Issued by
- Seminole County, Florida
About this file
Summary
This is a Construction Manager at Risk (CMAR) Agreement for Design and Construction Services between Seminole County, Florida and a qualified construction manager for the Seminole County Indoor Sports Complex (Project ID: PS-7223-26/LNF). The project encompasses preconstruction phase services and construction phase services for a multi-use indoor sports and event facility designed to support athletic tournaments, community programming, large-scale gatherings, and simultaneous event operations. The facility will include indoor court and event hall spaces, outdoor beach volleyball courts, spectator and public support areas, administrative and operations spaces, food service and concession components, site parking and circulation improvements, utilities, landscaping, and related site infrastructure. The construction manager must commence preconstruction services upon execution of the agreement and construction services upon execution of Appendix I (Authorization for Construction) and receipt of a formal Notice to Proceed. The agreement establishes a five-year initial term with two optional renewal periods of up to one year each, at the owner's discretion. The owner retains sole discretion to determine whether to proceed with the construction phase following preconstruction services and may terminate the agreement at any time.
Compensation for preconstruction services is established as either a lump sum fixed fee or time-and-material not-to-exceed basis, as specified in Appendix A, payable monthly upon invoice submission. The construction manager must deliver a Guaranteed Maximum Price (GMP) proposal within 60 days of 100% completion of construction documents, which the owner may accept, reject, or use to terminate the contract. The construction price comprises allowable costs of the work, general conditions costs, and a fixed management fee as a negotiated percentage of the GMP. Any costs exceeding the GMP are the sole responsibility of the construction manager. Liquidated damages are assessed at $1,325 daily for failure to meet substantial or final completion dates due to the construction manager's fault. The construction manager must provide payment and performance bonds with penal sums equal to the GMP, maintain specified insurance coverage per Florida Statutes Section 218.735 (Florida Prompt Payment Act), and pre-qualify and competitively bid subcontractors with a minimum of five bidders per trade category. The owner's project manager authority is limited to established authorization levels, with changes exceeding those limits requiring approval from the Board of County Commissioners.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
i
CONSTRUCTION MANAGER AT RISK
(CMAR) AGREEMENT FOR DESIGN
AND CONSTRUCTION OF THE
SEMINOLE COUNTY INDOOR SPORTS
COMPLEX
(PS-7223-26/LNF)
ii
TABLE OF CONTENTS
Chapter 1: Introduction and Project Overview
• Article 1: Contract Documents
• Article 2: Notices
• Article 3: Scope of Construction Manager’s Services
• Article 4: Compensation of Construction Manager's Services
• Article 5: Specific Insurance Requirements
• Article 6: Personnel, Subcontractor, Supplier, and Consultant Charts
• Article 7: Construction Schedule, Specific Bond Requirements, Payment Schedule and
Quality Control and Testing
Chapter 2: Construction Manager’s Required Services
• Article 1: General Project Services
• Article 2: Pre-Construction Services and Deliverables
• Article 3: Construction Services
• Article 4: Extra Services
Chapter 3: General Terms and Conditions
• Article 1: Project Documentation
• Article 2: Construction Manager’s Reviews and Evaluations
• Article 3: Construction Manager’s Duties, Obligations and Responsibilities
• Article 4: Construction Manager’s Personnel, Subcontractors, Suppliers and Site
Facilities
• Article 5: Goods, Products and Materials
• Article 6: Articles Documents and Information
• Article 7: Submittals
• Article 8: Construction Manager’s Inspection and Correction of Defective or Incomplete
Work
• Article 9: Change Orders and Changes to the Work
• Article 10: Financial Claims and Liens
• Article 11: Owner’s Consultant(s), Professional(s), and Construction Administration iii
TABLE OF CONTENTS — CONTINUED
• Article 12: Inspection, Correction of Work, and Project Closeout
• Article 13: Construction Manager’s Warranties and Guarantees
• Article 14: Owner’s Duties, Obligations, and Responsibilities
• Article 15: Construction Manager’s Compensation
• Article 16: Schedule Requirements
• Article 17: Liquidated Damages
• Article 18: Concealed and Unforeseen Conditions
• Article 19: Construction Manager’s Records
• Article 20: Proprietary Documents and Confidentiality
• Article 21: General Insurance Requirements
• Article 22: General Bond Requirements
• Article 23: Owner’s Right to Stop Work or Right to Carry Out Work
• Article 24: Termination or Suspension of Agreement for Construction Management
• Article 25: Applicable Law and Dispute Resolution
• Article 26: Damages and Remedies
• Article 27: Miscellaneous Provisions
• Article 28: Definitions
Signatory and Execution Authority
Appendices
Appendix A: Preconstruction Services Fees
Appendix B: Index of Preliminary Plans and Specifications for the Project
Appendix C: Schedule for Performance of Pre-Construction Services
Appendix D: Schedule of Required Insurance for Pre-Construction Services
Appendix E: Schedule of Required Insurance for Construction of the Work
Appendix F: Construction Manager’s Preconstruction Services Team
Appendix G: Owner’s Consultant Chart
Appendix H: Required Form of Payment and Performance Bond
Appendix I: Authorization for Construction
Appendix J: Proposed Pricing Schedule
CONSTRUCTION MANAGER AT-RISK (CMAR) AGREEMENT FOR DESIGN AND
CONSTRUCTION OF SEMINOLE COUNTY INDOOR SPORTS COMPLEX
(PS-7223-26/LNF)
CHAPTER 1
INTRODUCTION AND PROJECT OVERVIEW
THIS CONSTRUCTION MANAGEMENT AT-RISK SERVICES AGREEMENT (“the
Agreement” or “Agreement for Construction Management Services”) is dated as of the _____ day of
___________ 20_____, by and between ________________________________________________, duly authorized to conduct business in the State of Florida, whose address is
____________________________________________________________________, in this
Agreement referred to as “CONSTRUCTION MANAGER”, and SEMINOLE COUNTY, a charter county and political subdivision of the State of Florida, whose address is Seminole County Services
Building, 1101 E. 1st Street, Sanford, Florida 32771, in this Agreement referred to as “OWNER”
(collectively, “Parties,” individually, “Party”).
The authorized representatives and addresses of OWNER, CONSTRUCTION MANAGER and Professional are:
OWNER/PROJECT MANAGER:
Representative: Seminole County Fleet & Facilities Department
Address: 205 W. County Home Road
City, State, Zip: Sanford, FL 32773
Telephone: 407-665-5282
CONSTRUCTION MANAGER:
Representative: TBD
Address:
City, State, Zip:
Telephone:
Email:
PROFESSIONAL:
Representative: TBD
Address:
City, State, Zip:
Telephone:
Email:
The Project shall be identified as:
PROJECT TITLE: Construction Management At-Risk Services for Design and
Construction of Seminole County Indoor Sports Complex
PROJECT LOCATION: Seminole County
PROJECT ID NUMBER: PS-7223-26/LNF
RECITALS
A. WHEREAS, OWNER desires to retain the services of a competent and qualified
CONSTRUCTION MANAGER to provide construction management services for the Design and
Construction of Seminole County Administration Building (“the Project”), that will include two phases: (1) preconstruction phase services (“Preconstruction Phase”); and construction phase services (“Construction Phase”), each of which are more fully described in this Agreement; and
B. WHEREAS, the OWNER’s engagement of the CONSTRUCTION MANAGER is based upon
CONSTRUCTION MANAGER’s representations to the Owner that CONSTRUCTION
MANAGER (i) is experienced in providing construction management services for projects of similar size and complexity to the Project; (ii) is authorized and licensed to perform the type of labor and services for which it is being engaged in the State and locality in which the Project is located; (iii) is qualified, willing and able to perform construction management services for the
Project; and (iv) has the expertise and ability to provide construction management services which will meet the OWNER’s objectives and requirements and which will comply with the requirements of all governmental, public and quasi-public authorities and agencies having or asserting jurisdiction over the Project, all as set forth herein; and
C. WHEREAS, CONSTRUCTION MANAGER has certified that it is competent and qualified and desires to undertake the Work according to the terms and conditions stated in this Agreement, including all of its contractual documents; and
D. WHEREAS, OWNER intends to engage, or has engaged, one or more Design Professionals
(“Professional”) to perform architectural services and/or engineering services for the Project, including preparation of Site-specific Construction Documents, and may desire to have the
CONSTRUCTION MANAGER involved in the selection process of such or other Professionals to ensure that their qualifications and capabilities align with the Project’s objectives and requirements.
NOW, THEREFORE, for and in consideration of foregoing recitals and the mutual covenants and conditions contained in this Agreement, OWNER and CONSTRUCTION MANAGER agree as follows:
PROJECT DESCRIPTION/OVERVIEW
The CONSTRUCTION MANAGER is hereby tasked with providing construction management services under the at-risk model for the ___________Project. As described in greater detail herein, the
Services provided by the CONSTRUCTION MANAGER for the Project shall consists of those performed at the Pre-Construction Phase and at the OWNER’s discretion, the Construction Phase (each
“Phase” or collectively the “Phases”). The estimated construction cost is $_________________ to
The CONSTRUCTION MANAGER shall provide overall coordination, management, supervision, and scheduling of the work of each contractor/subcontractor so as to complete the Project in accordance with the OWNER’s objectives of safety, cost, time, and quality. The CONSTRUCTION
MANAGER shall serve under the at-risk model and shall be responsible for the preparation of bid packages, as well as all claims of any nature arising from subcontractors' exceedance of the initially submitted bids, including but not limited to discrepancies in the scope of work or cost escalations. The
CONSTRUCTION MANAGER shall promptly address and resolve any such claims and shall indemnify and hold the OWNER harmless from any liability, costs, or damages incurred as a result of these claims.
The CONSTRUCTION MANAGER shall maintain accurate records to include direct and indirect costs of services and equipment, change orders, direct purchases, and both bidding and construction timelines.
Other general duties shall include, but are not limited to, Preconstruction Services and Value Engineering, as defined herein.
At the OWNER’s discretion, the CONSTRUCTION MANAGER, during the Preconstruction
Phase may participate in the evaluation of proposals for the Design Professional (“Professional”) and provide advisory services to OWNER. The CONSTRUCTION MANAGER shall provide input and recommendations during the selection process to ensure the Professional’s qualifications align with the project requirements and objectives. This collaboration aims to ensure the selected Professional meets the project’s design and constructability needs, facilitating a cohesive and efficient project delivery.
Notwithstanding the foregoing, the OWNER has the right to engage a Professional independently prior to or concurrently with the engagement of the CONSTRUCTION MANAGER. In such instances, the
CONSTRUCTION MANAGER shall collaborate fully and cooperatively with the OWNER’s selected
Professional, respecting and adhering to all design plans, specification, and directives provided by the
Professional. The CONSTRUCTION MANAGER’s responsibilities shall include the integration of the
Professional’s design into the Project and ensuring that all construction activities align with the
Professional’s specification.
CONSTRUCTION MANAGER shall not proceed with any work or any Phase, nor shall
CONSTRUCTION MANAGER be entitled to any compensation for any such work unless and until
OWNER has issued a written Notice to Proceed for that Phase. In entering into this Agreement, the Parties expressly agree that OWNER is under no obligation to issue a Notice to Proceed for any specific Phase.
ARTICLE 1
CONTRACT DOCUMENTS
1.1. The above referenced recitals are true and correct and are incorporated into this Agreement by reference. The Construction Management At-Risk Services Agreement with a Guaranteed
Maximum Price (“the Agreement” or the “Agreement for Construction Management”) includes and hereby incorporates in full by reference the following documents which are the
“Contract Document(s),” including all exhibits, drawings, specifications, and documents herein, and attachments and addenda thereto:
This Chapter 1, Introduction and Project Overview, including the foregoing recitals, and the Project Overview (hereinafter “Chapter 1”).
Chapter 2, Construction Manager’s Required Services (hereinafter “Chapter 2”).
Chapter 3, General Terms and Conditions (hereinafter “Chapter 3”).
Appendices
Appendix A: Preconstruction Services Fees
Appendix B: Index of Preliminary Plans and Specifications for the Project
Appendix C: Schedule for Performance of Pre-Construction Services
Appendix D: Schedule of Required Insurance and Contractor’s Certificate of Insurance for Pre-Construction Services
Appendix E: Schedule of Required Insurance for Construction of the Work
Appendix F: Construction Manager’s Pre-Construction Services Team
Appendix G: Owner’s Consultant’s Chart
Appendix H: Required Form of Payment and Performance Bond
Appendix I: Authorization for Construction
Exhibit 1: Index of Final Plans and Specifications
Exhibit 2: Construction Schedule
Exhibit 3: Construction Manager’s Project Team
Exhibit 4: Schedule of Values
Exhibit 5: Unit Prices
Exhibit 6: Construction Manager’s Subcontractors and
Suppliers Chart
Exhibit 7: Qualifications and Assumptions
Exhibit 8: Schedule of Allowances
Appendix J: Proposed Pricing Schedule
Any amendment or addenda executed by OWNER and CONSTRUCTION
MANAGER hereafter; and
Approved Change Order(s) or field orders.
These documents, as outlined above, collectively form an integral part of the RFP package.
1.2. Documents not included or expressly contemplated by this Chapter, do not and shall not form part of this Agreement.
1.3. Capitalized terms used in this Agreement shall have the meaning ascribed to them in Chapter
3, Article 28, the Definitions section of this Agreement, unless otherwise specified.
1.4. The OWNER shall: [Select and complete as appropriate]
□ Furnish the CONSTRUCTION MANAGER with one (1) reproducible copy of the
Construction Documents.
□ Furnish the CONSTRUCTION MANAGER with electronically formatted
Construction Documents
× Not furnish the CONSTRUCTION MANAGER with a copy of the Construction
Documents; provided, however, the CONSTRUCTION MANAGER may obtain copies of the plans and specifications from Professional, if any.
ARTICLE 2
NOTICES
2.1. Unless otherwise provided, all notices shall be in writing and considered duly given if the original is (i) hand delivered, including delivery by independent delivery service, including
Federal Express, United Parcel Service or United States Postal Service; (ii) sent by U.S. Mail, postage prepaid; or (iii) emailed to the authorized representative provided by this Agreement.
Notices hand delivered, delivered by independent delivery services, or emailed to the authorized representative designated by Agreement, shall be deemed given on the date of delivery. Notices given by U.S. Mail shall be deemed given as of the second business day following the date of posting.
2.2. The place for giving of notice will remain such until it has been changed by written notice in compliance with the provisions of this Section. For the present, the parties designate the following as the respective places for giving of notice:
For OWNER:
Seminole County Facilities Management Division
205 W. County Home Road
Sanford, FL 32773
With a copy to:
Seminole County Purchasing & Contracts Division
1301 E. Second Street
Sanford, FL 32771
For CONSTRUCTION MANAGER:
For PROFESSIONAL:
2.3. Either party may change the addresses or persons for receipt of notices by written notice.
ARTICLE 3
SCOPE OF CONSTRUCTION MANAGER’S SERVICES
3.1. General Scope of Services. Upon execution of this Agreement, the CONSTRUCTION
MANAGER shall commence the performance of Pre-Construction Phase Services
(“Execution Date”), and upon execution of Appendix “I,” Authorization for Services, the
CONSTRUCTION MANAGER shall commence the Construction Phase and/or Renovation
Services, in accordance with the scheduled start date provided in Appendix I and the subsequent Notice to Proceed. The Parties acknowledge that (i) the OWNER, in its sole discretion, may determine that it shall not proceed with the Construction Phase; (ii) performance of the Pre-Construction Phase Services may overlap performance of the
Construction Phase Services; (iii) categories of Work performed during the Construction
Phase may be performed in separate phases; and (iv) payment of the CONSTRUCTION
MANAGER for Pre-Construction Services shall be separate from payment, if any, for
Construction Services.
3.1.1. Scope of Pre-Construction Services. The CONSTRUCTION MANAGER shall furnish and pay for out of the Pre-Construction Services Fee, all Pre-Construction
Services required by this Agreement. All such services are hereinafter referred to
“Pre-Construction Services” or “the Pre-Construction Phase.”
3.1.2. Scope of Construction Services. Upon execution of Appendix I, Authorization for Construction, the CONSTRUCTION MANAGER shall furnish and pay for out of the Construction Price all Construction Services required by this Agreement. All such services shall hereinafter be referred to as “Construction Services” or
“the Construction Phase.”
3.2. Self-Performance by the CONSTRUCTION MANAGER. [select as appropriate]:
□ The CONSTRUCTION MANAGER shall not be allowed to self-perform any category of the Work without prior written approval of the OWNER.
× The CONSTRUCTION MANAGER shall be allowed to bid for subcontract work, and, if it is the lowest acceptable bidder of a minimum of three (3) competing bids, perform those categories of Work which the OWNER agrees, said categories to be incorporated into the Authorization for Construction (Appendix “I”).
□ The CONSTRUCTION MANAGER shall be allowed, with the prior written approval of the OWNER, to perform categories of Work for which there is no acceptable bidder or if a subcontractor fails to execute an acceptable contract with the CONSTRUCTION MANAGER.
3.3. Renewal. The Construction Management At-Risk Services Agreement with a Guaranteed
Maximum Price takes effect on the date of its execution by OWNER and shall remain in effect until completion of the Project, unless terminated earlier in accordance with this Agreement.
If additional time is required to complete the Project, the OWNER and the CONSTRUCTION
MANAGER may mutually agree to renew the term of this Agreement for two (2) successive periods not to exceed one (1) year each.
3.3.1. Preconstruction Phase. The Preconstruction Phase shall begin on the Execution Date and shall continue until all preconstruction services outlined in this Agreement are completed to the satisfaction of OWNER. The estimated duration for the completion of preconstruction services is determined at issuance of preconstruction Work Order. The
CONSTRUCTION MANAGER shall complete all pre-construction services within this estimated duration, unless otherwise agreed in writing by OWNER. In the event the
CONSTRUCTION MANAGER fails to complete the preconstruction services within the specified duration, the OWNER reserves the right to terminate this Agreement or to impose penalties as set forth in this Agreement.
3.3.2. Construction Phase. Upon the satisfactory completion of the Preconstruction Phase, and upon the execution of Appendix “I”, Authorization for Construction, the
Construction Phase shall continue until Substantial Completion and Final Completion as defined in this Agreement.
3.3.3. Renewals. This Agreement takes effect on the date of its execution by the COUNTY, and continues for a period of five (5) years. If additional time is required to complete the
Project, the OWNER and the CONSTRUCTION MANAGER may mutually agree to renew the term of this Agreement for two (2) successive periods not to exceed one (1) year each. Such renewals shall be documented in writing and shall specify the new completion date and any other terms and conditions relevant to the renewal. Continuation of the contract beyond the initial period and any renewal option subsequently exercised is an OWNER prerogative and not a right of the CONSTRUCTION MANAGER. This prerogative will be exercised only when such continuation is clearly in the best interest of the OWNER at OWNER’s sole discretion. The prices stated herein shall prevail for the full duration of the initial contract term and any optional term subsequently exercised.
ARTICLE 4
COMPENSATION OF CONSTRUCTION MANAGER
4.1. Compensation for Pre-Construction Phase. The OWNER shall pay, and the
CONSTRUCTION MANAGER shall accept, as full and complete payment for the
CONSTRUCTION MANAGER’s timely and complete performance of Pre-Construction
Services, the Pre-Construction Services Fee. The compensation for Pre-Construction Services shall either be based on a lump sum fixed fee or a time and material not-to-exceed basis, as forth in Appendix “A”.
4.1.1. Pre-Construction Service Fee – Payment. CONSTRUCTION MANAGER shall render to OWNER, at the close of each calendar month, an itemized invoice and OWNER shall make payment as following: [Select one of the following]:
× The lump sum fixed Pre-Construction Services Fee shall be paid in accordance with Appendix “A.” The lump sum fixed Pre-Construction Services Fee shall be set and paid pursuant to the time schedule in Appendix “C” when executed by the parties.
□ The time and material not to exceed Pre-Construction Services Fee shall be paid in accordance with the labor and material rates set forth in Appendix “C.”
□ Other:
4.2. Guaranteed Maximum Price. As more particularly described in Chapter 2, Article 2, the
CONSTRUCTION MANAGER shall prepare and deliver to the OWNER, with a copy to the
PROFESSIONAL, a Guaranteed Maximum Price (“GMP”) proposal for which the
CONSTRUCTION MANAGER proposes to provide Construction Services [Select one (1) and complete as appropriate]:
□ Upon completion of percent ( %) of the Construction Documents.
× Sixty (60) calendar days after 100% completion of the Construction Documents for the entire project.
□ No later than_ , 20__ .
□ Other:
If the GMP proposal is accepted by the OWNER, the CONSTRUCTION MANAGER shall execute Appendix “I”, Authorization for Construction. An executed Appendix I, Authorization for Construction, and a subsequent Notice to Proceed, shall serve as written notice to the CONSTRUCTION MANAGER establishing the date construction is to commence (“the Commencement Date”).
4.3. Compensation for Construction Phase. The OWNER shall pay, and the CONSTRUCTION
MANAGER shall accept, as full and complete payment for Construction Services, the
Construction Price as agreed by the parties (“the Construction Price”). The Construction Price shall not exceed the Guaranteed Maximum Price (GMP) agreed by the Parties. Any costs that would result in the Construction Price exceeding the GMP shall be the sole responsibility of the
CONSTRUCTION MANAGER, with no obligation on the part of the OWNER to provide additional reimbursement.
4.3.1. Construction Price – Amount. The Construction Price shall include, and is limited to, the total of:
(i) Costs of the Work. The Costs of the Work for the Project as defined in Chapter 2, Article 2, Section 2.7.2.1 incorporated herein.
(ii) General Conditions. The OWNER shall pay, and the CONSTRUCTION
MANAGER shall accept as complete payment for General Conditions, as defined in
Chapter 2, Article 2, Section 2.7.2.2. The method of payment, however, shall be set forth in Appendix “I.”
(iii) Fixed Management Fee. The OWNER shall pay, and the CONSTRUCTION
MANAGER shall accept as complete payment for the performance of Construction
Management Services, a negotiated fixed fee in the amount of _____________
(___%) of the GMP for the Project.
4.3.2. Construction Price – Payment and Retainage. Payment requests shall be processed and paid in accordance with Part VII, Chapter 218, Florida Statutes, known as the Florida
Prompt Payment Act, and the terms of this Agreement. CONSTRUCTION MANAGER shall render to OWNER, at the close of each calendar month, an itemized invoice. The date on which payment is due shall be referred to as the “Payment Date.”
4.3.2.1 For Projects with an estimated cost of less than $10 million. The
OWNER or its agent shall, pursuant to Section 218.735(7), Florida Statutes, prepare and deliver to the CONSTRUCTION MANAGER a single list of items, including the estimated cost to complete each item, to be rendered complete, satisfactory, and acceptable within thirty (30) calendar days after reaching substantial completion. For projects having an estimated cost of
$10 million or more, within thirty (30) calendar days, or, if extended by change order, up to sixty (60) calendar days after reaching substantial completion.
4.3.2.2 Multi-Phased Projects. For projects with multiple phases, the
OWNER or its agent must provide for the development of a list of items required to render complete, satisfactory, and acceptable for each building, structure, or phase of the Project within the time limitations stated in subsection 4.3.2.1 above.
4.3.2.3 The final completion date must be at least thirty (30) days after the
CONSTRUCTION MANAGER receives the list of items. If the list is not provided within the required timeframe, the final completion date shall be extended by the number of days the OWNER’s delivery was delayed.
4.3.2.4 Failure of the CONSTRUCTION MANAGER to include any corrective work or pending items not yet completed on the list developed pursuant to this section does not alter the responsibility of the CONSTRUCTION
MANAGER to complete all construction services set forth herein. If a good-faith dispute exists as to whether one or more items have been completed pursuant to this Agreement, the OWNER may continue to withhold an amount not to exceed one hundred fifty percent (150%) of the total costs to complete the remaining items. The CONSTRUCTION MANAGER’s project representative shall be required to review these estimates with the
OWNER and sign the estimate in agreement.
4.3.2.5 Retainage shall be released as set forth in Section 218.735, Florida Statutes.
4.4. Billing and Payment: Preconstruction and Construction Services. CONSTRUCTION
MANAGER shall render to Owner, at the close of each calendar month, an itemized invoice, properly dated including, but not limited to, the following information:
(i) The name and address of CONSTRUCTION MANAGER
(ii) Contract Number.
(iii)A complete and accurate time record of services performed by CONSTRUCTION
MANAGER for all services performed by CONSTRUCTION MANAGER during that month and for which Owner is billed.
(iv) A description of the services rendered, corresponding to the 1/10 time increment, with sufficient detail to identify the exact nature of the work performed. As an example of the specificity required, it would not be appropriate to list the service performed simple as “research.” Instead, it is required that the specific matter being researched be specified in such detail as would permit a determination being made as to the necessity for the research and whether the time attributable to it as reasonable.
(v) Any such information as may be required by this Agreement or requested by OWNER from time to time.
4.4.1. Submittal Instructions for invoices are as follows:
(i) The original invoice must be emailed to:
AP@SeminoleClerk.org
(ii) The original invoice may also be mailed or delivered to:
Director of County Comptroller’s Office
Seminole County Board of County Commissioners
P.O. Box 8080
Sanford, Florida 32772-8080
(iii)A copy of the invoice must be sent to:
Seminole County Facilities Management Division
205 W. County Home Road
Sanford, FL 32773
4.4.2. OWNER shall make payment after OWNER’s review and approval and within thirty (30) days of receipt of a proper invoice from CONSTRUCTION
MANAGER.
4.5. Compensation for Change Orders. Amounts owed by the OWNER to the
CONSTRUCTION MANAGER, and the amount of the GMP for Construction Services for the Project established in the executed Appendix “I,” Authorization for Construction, shall only be adjusted by duly authorized Change Orders.
4.5.1. Change Order – Increase in Scope or Costs. For change orders increasing the
CONSTRUCTION MANAGER’s scope of services or costs, the
CONSTRUCTION MANAGER shall be compensated in the amount of the
Cost of the Work added by the Change plus the CONSTRUCTION
MANAGER’s Management Fee in the amount as set forth above.
4.5.2. Change Order – Decrease in Scope or Cost. For change orders decreasing the
CONSTRUCTION MANAGER’s scope of services or costs, the OWNER shall receive a credit in the amount of the Cost of the Work which is decreased by mailto:AP@SeminoleClerk.org the Change plus a deduction of the CONSTRUCTION MANAGER’s
Management Fee in the amount as set forth above.
4.5.3. Change Orders and General Conditions. For the purposes of Changes to the
Work, those items described in Chapter 2, Article 2, Section 2.7.2.2 (General
Conditions) shall not be included in the calculation of the increased or decreased
Cost of the Work unless the Change directly increases or decreases the cost of a line item therein in a direct and documentable manner and, in that case, only the line item directly increased or decreased shall be included in the calculation. An increase or decrease in the scope of supervisory or staff personnel’s responsibility shall not be considered to increase/decrease the cost of line items relating to supervisory or staff personnel.
4.5.4. Change Orders for Extension of Time. If the project duration is impacted for excusable delays such as abnormal weather, OWNER delays, etc., CONSTRUCTION
MANAGER is entitled to request a change order for consideration within fifteen (15) days of the delay event, for time which shall be the sole remedy. After fifteen (15) days of the delayed event, the CONSTRUCTION MANAGER waives any right to claim.
The OWNER shall respond in writing to the CONSTRUCTION MANAGER’s claim within fifteen (15) days of receipt, or such longer period as may be mutually agreed, either approving or denying the claim. Any adjustment to the Contract Price or Contract
Time resulting from such claim shall be authorized by Change Order.
4.5.5. Change Order – Disputed.
(i) If the CONSTRUCTION MANAGER disputes a change order decision pursuant to Chapter 3, Article 9, Section 9.7, it must give the OWNER its written notice of dispute, including the reasons, therefore, within seven (7) calendar days of the disputed decision.
(ii) For change orders directed by a Professional to be performed by the
CONSTRUCTION MANAGER on a time-and-materials basis pursuant to
Chapter 3, Article 9, Section 9.5.1, the OWNER shall pay the
CONSTRUCTION MANAGER the actual reasonable incurred cost and expenses paid to those subcontractors and suppliers performing the Work plus the CONSTRUCTION MANAGER fee.
4.6. Time is of the Essence. Both the OWNER and CONSTRUCTION MANAGER acknowledge that time is of the essence in this project. The OWNER requires beneficial occupancy of the building at the conclusion of each phase to sustain normal operations. Failure to achieve timely occupancy will result in additional costs for the OWNER. Hence, the liquidated damages specified in this paragraph are not considered penalties but are designed as a mechanism for the OWNER to cover the additional costs incurred due to any delays. Liquidated Damages. If liquidated damages are assessed pursuant to Chapter 3, Article 17, such damages shall be imposed where the delay to the Substantial or Final Completion date is due to the fault of the
CONSTRUCTION MANAGER. For failure to meet Substantial Completion, liquidated damages shall be calculated at the following daily rates: $1,325. For failure to meet the Final
Completion Date, liquidated damages shall be calculated at $1,325.
4.7. Limitations on OWNER’s PROJECT MANAGER. The OWNER’s PROJECT
MANAGER is limited in their authority to authorize changes to the Scope of Services. They may only approve modifications that fall within their specific authorization level, as established during the Agreement’s approval process, and in accordance with OWNER’s
Procurement Policies and Procedures. Any changes that exceed these established limits require prior approval from the Board of County Commissioners. The CONSTRUCTION
MANAGER must not rely on any approvals from the PROJECT MANAGER that go beyond these established limits, and any such reliance will be deemed unreasonable. A copy of the
Procurement Policies and Procedures will be provided upon request.
ARTICLE 5
SPECIFIC INSURANCE REQUIREMENTS
5.1 Insurance Requirements. All insurance obligations under this Agreement, including the types of coverages and minimum limits of liability required, shall be governed by the provisions set forth in Chapter 3, Article 21. The CONSTRUCTION MANAGER shall adhere to the insurance requirements as outlined in that section.
5.2 CONSTRUCTION MANAGER’s Obligations. The CONSTRUCTION MANAGER shall provide insurance as required by Chapter 3, Article 21, and in accordance with the terms set forth therein. The OWNER will communicate and cooperate with the CONSTRUCTION
MANAGER and the CONSTRUCTION MANAGER’s insurance broker, as required.
5.2.1 In accordance with Chapter 3, Article 21, the CONSTRUCTION MANAGER shall purchase and maintain at all times that it is performing services under this
Agreement from a company or companies authorized to do business in the State of
Florida, insurance policies containing the types of coverages and minimum limits of liability as set forth in Appendix “D” and Appendix “E,” protecting against claims that may arise out of or result from the performance or non-performance of services under this Agreement.
ARTICLE 6
PERSONNEL, SUBCONTRACTOR,
SUPPLIER AND CONSULTANT CHARTS
6.1 Pre-Construction Service Team. Attached hereto as Appendix “F” is the
CONSTRUCTION MANAGER's Personnel Chart for Pre-Construction services, which lists by name, job category, and responsibility, the CONSTRUCTION MANAGER’s primary employees who will perform those services.
6.2 Construction Service Team. In addition, during the performance of Pre-Construction
Services, the CONSTRUCTION MANAGER shall provide the OWNER with the
CONSTRUCTION MANAGER’s Personnel Chart for Construction, as described in
Chapter 2, Article 2, Section 2.7.5.11.
6.3 OWNER’s Approval of Service Teams. The OWNER shall review and approve the personnel chart prior to the commencement of the Work, both for Pre-Construction and
Construction. The OWNER reserves the right to request the immediate replacement of any personnel, with or without providing reasons, and the CONSTRUCTION MANAGER shall propose the replacement within 48 hours for the OWNER’s review and approval.
With respect to both lists, the CONSTRUCTION MANAGER shall promptly inform the
OWNER in writing of any proposed replacements, the reasons therefore, and the name(s) and qualification(s) of proposed replacement(s). The OWNER shall have the right to reject any proposed replacement for good cause.
6.4 CONSTRUCTION MANAGER’s Subcontractors and Suppliers. During the performance of Pre-Construction Services, the CONSTRUCTION MANAGER shall provide the
OWNER with the CONSTRUCTION MANAGER’s Subcontractors and Suppliers Chart, as described in Chapter 2, Article 2, Section 2.7.5.10. The Chart shall list by name and general Project responsibility each entity that will be utilized by the CONSTRUCTION
MANAGER to provide goods or services with respect to the Project. The
CONSTRUCTION MANAGER shall promptly inform the OWNER in writing of any proposed replacements, the reasons therefore, and the name(s) and qualification(s) of proposed replacement(s). The OWNER shall have the right to reject any proposed replacement for good cause.
6.5 OWNER’s CONSULTANT CHART. The OWNER shall prepare and attach as
Appendix “G” to this Contract the OWNER's Consultants Chart which lists by name and general duties each consultant retained by the OWNER to provide services with respect to the Project. The OWNER reserves the right to engage any other consultants which it may deem necessary or desirable, or to replace any Consultant listed thereon.
ARTICLE 7
CONSTRUCTION SCHEDULE, SPECIFIC BOND
REQUIREMENTS, PAYMENT SCHEDULE AND
QUALITY CONTROL AND TESTING
7.1 Time for Performance. OWNER and CONSTRUCTION MANAGER acknowledge that time is of the essence.
7.1.1 Delivery of Pre-Construction Services. The CONSTRUCTION MANAGER shall commence delivery of its Pre-Construction Services on an agreed-upon date reflected in the Appendix “C” submitted with the Project-specific scope of services and shall deliver such services in a prompt and expeditious manner so as not to delay the OWNER or the Professional(s).
7.1.2 Commencement of Construction. As provided by Appendix “I,” Authorization for Construction, and the Construction schedule incorporated therein, CONSTRUCTION MANAGER shall have an expected date for commencement of the construction activities. Notwithstanding, OWNER will issue a formal Notice to Proceed (NTP), and only upon receipt of the NTP will CONSTRUCTION
MANAGER commence its construction services (the “Commencement Date”).
7.1.3 Substantial Completion. The CONSTRUCTION MANAGER shall accomplish
Substantial Completion of the Work of the Project on or before a date to be agreed upon and set forth in Appendix “I” and shall prosecute the Work pursuant to the
Construction Schedule incorporated therein. In the event that the original substantial completion date specified in the contract cannot be met, the substantial completion date shall be determined by the issuance of the Certificate of Occupancy
(CO) by the building official. This date shall serve as the official substantial completion date, allowing the OWNER to legally take beneficial occupancy of the building.
7.1.4 Final Completion. The CONSTRUCTION MANAGER shall achieve Final
Completion of the Work of the Project on or before the date established in Chapter
1, Article 4, Section 4.3.2.1 (the “required date of Final Completion”) or within 30 days after substantial completion, if any extensions to the contract are executed.
7.2 Construction Schedule. The CONSTRUCTION MANAGER shall prepare an estimate of construction time for the Project as part of Pre-Construction Services as described in Chapter
2, Article 2, Section 2.6. The actual Construction Schedule shall be incorporated into the
Authorization for Construction (Appendix “I”).
7.3 Schedule of Values. The CONSTRUCTION MANAGER shall prepare a preliminary
Schedule of Values for the Construction Work as part of Pre-Construction Services as described in Chapter 2, Article 2, Section 2.7.5.5 with a Project-specific Schedule of
Values to be incorporated into the Authorization for Construction (Appendix “I”).
7.4 Bond Requirements.
7.4.1 The CONSTRUCTION MANAGER shall be required to provide payment and performance bonds each having a penal sum equal to the GMP. The amount of the premiums for such bonds shall be included in the estimate of OWNER’s Costs provided to the OWNER and the same shall be incorporated into the Authorization for Construction (Appendix “I”).
Performance and Payment Bonds shall meet all requirements of Section 255.05, Florida Statutes, for public construction bonds. Additionally, upon execution of this
Agreement, all original Performance and Payment bonds will be submitted to the
OWNER for recording of said bonds. The bonds will be acceptable to the OWNER only if the following conditions are met:
(i) The Surety is licensed to do business in the State of Florida;
(ii) The Surety holds a Certificate of Authority authorizing it to write surety bonds in this State;
(iii) The Surety has twice the minimum surplus and capital requirements required by the Florida Insurance Code at the time the invitation to bid is issued;
(iv) The Surety is otherwise in compliance with the Florida Insurance Code;
(v) The Surety holds a currently valid Certificate of Authority issued by the
United States Department of Treasury under 31 U.S.C. § 9304;
(vi) The Surety shall have the following minimum qualifications in accordance with the latest edition of A.M. Best’s Insurance Guide: Financial Stability
A- to A+. If the rating of the insurer or surety should fall below this standard, the CONSTRUCTION MANAGER shall cause the policy to be replaced promptly by an acceptable insurer or surety.
(vii) The Payment and Performance Bonds are in the same or substantially and materially identical form to Appendix “H”.
If the Surety for any bond furnished by the CONSTRUCTION MANAGER is declared bankrupt, becomes insolvent, its right to do business is terminated in the
State of Florida, or it ceases to meet the requirements imposed by this Agreement, the CONSTRUCTION MANAGER shall, within thirty (30) calendar days thereafter, substitute another bond and surety, both of which shall be subject to the
OWNER’s approval.
The CONSTRUCTION MANAGER shall use the OWNER’s bond forms attached hereto as Appendix “H”.
7.4.2 The CONSTRUCTION MANAGER ( shall) ( shall not) be required to provide a maintenance bond. If so, the penal sum of the bond shall be ($_______).
7.4.3 Payment for bonds shall be as follows: [Select one (1) as appropriate]
(i) The cost of required bonds shall be identified in the Schedule of Values and shall be incorporated into the Authorization for Construction (Appendix
“I”).
(ii) Other
7.4.4 Quality Control and Testing [Select one as appropriate]:
□ The OWNER shall select the quality control and testing agencies.
□ The CONSTRUCTION MANAGER shall select the quality control and testing agencies.
(Select as appropriate)
□ The cost of specified measures and tests required by the Construction Documents shall not be included in the Guaranteed Maximum Price and shall be paid by the
OWNER to the testing company as OWNER’s Costs pursuant to Chapter 2, Article
2, Section 2.7.3. CONSTRUCTION MANAGER will not provide threshold inspections.
□ Other.
CHAPTER 2
CONSTRUCTION MANAGER’S REQUIRED SERVICES
GENERAL PROJECT SERVICES
1.1 Essential Services. The CONSTRUCTION MANAGER agrees to provide all services required to professionally complete the Work in accordance with the Construction
Documents and in an expeditious and economical manner consistent with this Agreement for Construction Management and the best interests of the OWNER.
1.2 Compliance with Contractual Requirements. At all times the CONSTRUCTION
MANAGER is performing services, it shall comply with the requirements set forth in
Chapter 1, Chapter 2, and Chapter 3 of this Agreement for Construction Management.
1.3 Cooperative Effort. The CONSTRUCTION MANAGER shall, in consultation with the
OWNER, Professional(s), and the subcontractors, endeavor to develop, implement, and maintain a spirit of cooperation, collegiality, and open communication among the parties so that the goals and objectives of each are clearly understood, potential problems are resolved promptly, and, upon completion, the Project is deemed a success by all parties.
1.4 Additional or Modified Required Services. Additional or modified required services, if any, shall be included Index of Preliminary Plans and Project Specifications, Appendix B, and incorporated herein by reference.
PRE-CONSTRUCTION SERVICES AND DELIVERABLES
2.1. Project and Program Review and Knowledge.
2.1.1 CONSTRUCTION MANAGER shall review the Project documents, including plans and specifications at minimum intervals directed by the OWNER, developed and issued by the Professional from time to time and shall possess the knowledge relating thereto necessary for the performance of its services. A written
Constructability Review of the documents shall be provided at each phase so the
Professional can also provide written responses to each item.
2.1.2 CONSTRUCTION MANAGER shall review the Project Site, including any features or aspects of the Site which may affect the constructability of the Project as designed and shall possess the knowledge relating thereto necessary for the performance of its services.
2.1.3 CONSTRUCTION MANAGER shall review the OWNER's program for the intended use of the Project, including, without limitation, the intended purposes and uses of the facility and each element, and the scope and extent of use of the Project and shall possess the knowledge relating thereto necessary for the performance of its services.
2.2 Project Meetings and Consultation.
2.2.1 The CONSTRUCTION MANAGER shall attend any and all such meetings with representatives of the OWNER, the Professional or others as are reasonably requested by the OWNER throughout the CONSTRUCTION MANAGER’s performance of this Contract. At a minimum, the CONSTRUCTION MANAGER shall attend one meeting per week, at such date, time, and place as scheduled by the
OWNER during the construction of the Project, upon reasonable notice. Other meetings may be scheduled by upon request of the OWNER.
2.2.2 CONSTRUCTION MANAGER shall regularly consult with the OWNER and the
Professional regarding issues relating to the Project and the Project program, including, without limitation:
(i) Site use and improvements;
(ii) The selection of materials, equipment, finishes, and color schedules;
(iii) Construction feasibility and issues relating to the constructability of various designs and alternatives;
(iv) Opinion and recommendations regarding the constructability of the Project documents with regard to life safety requirements, Fair Housing Act requirements and requirements of the Americans with Disabilities Act
(ADA), including, without limitation, the CONSTRUCTION MANAGER's recommendations for the means and methods required to construct the
Project in accordance with these requirements of the Project documents;
(v) Analysis and recommendations for the Project services and systems, including, without limitation, mechanical, electrical, plumbing, and computer, phone, and cabling systems;
(vi) Time requirements for procurement, installation, and construction completion, with a special emphasis on long-lead time items;
(vii) Strategies for managing competitive bidding for the Project, including generating subcontract and vendor interest in the Project;
(viii) Factors related to construction cost, including estimates of alternative designs or materials; and
(ix) General consultation and written analysis regarding issues relating to the
Project and Project program are included in the Consideration described in
Chapter 1, Article 4, relating to compensation. In the event OWNER requests a written analysis or a substantial and detailed analysis in relation to the requested consultation, the CONSTRUCTION MANAGER shall request that a change order be issued prior to incurring any time or costs in excess of the compensation described herein.
2.3 Preliminary Design Review.
2.3.1 The CONSTRUCTION MANAGER shall actively and jointly participate with the
OWNER and the Professional(s) in the formation of the final Project design.
2.3.2 The Professional is required, in accordance with the schedule requirements, to provide preliminary design drawings. The CONSTRUCTION MANAGER shall promptly and in accordance with the schedule requirements:
(i) Familiarize itself with the preliminary design drawings;
(ii) Analyze and evaluate the constructability of the preliminary design drawings;
(iii) Analyze and evaluate the preliminary design drawings in regard to the completeness of intended bid categories, conflicts or overlaps in the divisions of the Work, design details affecting construction, value engineering, identification of long-lead materials affecting the Construction
Schedule, availability of labor and other factors affecting construction; and
(iv) Estimate total project cost formatted by the Construction Specifications
Institute (CSI) Master Format.
2.3.3 The CONSTRUCTION MANAGER and the Professional(s) shall jointly schedule and attend both physical and virtual meetings with the OWNER to review and evaluate the preliminary design drawings.
2.3.4 The CONSTRUCTION MANAGER shall, in accordance with schedule requirements, notify the designated Professional in writing and assist the
Professional(s) with the resolution of all problems, conflicts, defects, or deficiencies identified during the review and evaluation of the preliminary design drawings.
2.3.5 Upon completion of the preliminary design drawings, the CONSTRUCTION
MANAGER is required, in accordance with the schedule requirements, to prepare and submit a preliminary estimate of Total Project Construction Cost broken down by line item into major construction disciplines and systems, and prepare a Critical
Path Method (CPM) Schedule from Notice to Proceed to Final Completion.
The CONSTRUCTION MANAGER shall, in accordance with schedule requirements, review the preliminary estimate of the Total Project Construction Cost and promptly inform the OWNER and
Professional of recommended adjustments, if any.
2.4 Construction Documents Review.
2.4.1 The Professional is required, in accordance with the schedule requirements, to provide Construction Documents and other information.
2.4.2 The CONSTRUCTION MANAGER shall, in accordance with schedule requirements, prepare applicable Construction Schedule(s), the estimate of Total
Project Construction Cost, the cost of local utilities, fees for permits and licenses, any modifications necessitated by local conditions, and other information necessary for a full understanding of the Project, and the Construction Documents. The
CONSTRUCTION MANAGER shall undertake the following:
(i) Examine the Construction Documents for clarity, adequacy of detail, consistency, accuracy, and completeness;
(ii) Identify all discovered conflicts, omissions or overlaps in the proposed divisions of the Work, evaluate the completeness of intended bid categories, and identify unusual design details affecting construction cost and schedules;
(iii) Apply established value engineering principles and practices to reduce the cost of the Project;
(iv) Identify factors with the potential to impact the Construction Schedule, such as materials with long lead time, the unavailability of required labor, and other factors, and make suggestions for acceptable alternatives;
(v) Evaluate and make suggestions to optimize Site utilization;
(vi) Recommend proposed modifications or alternatives to the Construction
Documents based on evaluation and review;
(vii) Notify the OWNER and the Professional(s) in writing of any variances between the Construction Documents and applicable laws, statutes, building codes, rules, and regulations of which it is aware; and
(viii) Notify the OWNER and the Professional(s) in writing of all problems, conflicts, defects or deficiencies in the Construction Documents of which it is aware.
2.4.3 The CONSTRUCTION MANAGER shall, in accordance with schedule requirements, assist the Professional with resolving all problems, conflicts, defects or deficiencies identified during the review and evaluation of the Construction
Documents.
2.4.4 Upon completion of the review and examination of the Construction Documents, the Professional is required, in accordance with schedule requirements, to prepare and submit a final estimate of Total Project Construction Cost.
2.4.5 Upon completion of review and examination of the Construction Documents, the
CONSTRUCTION MANAGER, in accordance with schedule requirements, shall prepare and submit a final estimate of Total Project Construction Cost.
2.4.6 If the final estimates of Total Project Construction Cost by the CONSTRUCTION
MANAGER and the Professional differ materially, the CONSTRUCTION
MANAGER and Professional shall meet promptly to reconcile the discrepancies between their estimates. This will permit submission to the OWNER of a final estimate of Total Project Construction Cost on which both the Professional and the
CONSTRUCTION MANAGER agree, or where the parties cannot agree, identify to the OWNER the specific portions that differ.
2.4.7 In performing the Preconstruction Services, the CONSTRUCTION MANAGER is not assuming responsibilities of the Professional(s) for design of…