PRS.docx

DOCX document 13 KB Posted

Attached to
USNS COMFORT (T-AH 20) Lifeboat Systems
Solicitation number
N3220522Q0120
Issued by

About this file

This Performance Requirements Summary outlines the requirements for procuring Fassmer and Global Davit lifeboat systems for the USNS COMFORT (T-AH 20). Key performance standards include meeting the schedule for contract deliverables as outlined in the Performance Work Statement, successfully completing all testing with acceptance of results by the U.S. Coast Guard and ABS, and ensuring the accuracy of all manuals, operating procedures, technical documentation and other deliverables with no more than four errors per document. Lifeboat systems must also meet storage, outfitting and expiration date requirements for all associated equipment and provisions as defined in the Performance Work Statement. The Department of the Navy Military Sealift Command is the contracting agency.

View the file

Other files

File Type Posted
N3220522Q0120-0002.docx DOCX document
N3220522Q0120-0001.docx DOCX document
PWS.docx DOCX document
CSS.docx DOCX document
Technical Data Non-Disclosure.docx DOCX document
JA COMFORT Lifeboat System_Redacted.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Requirements Summary (PRS) The performance standards for this PWS are stated in the PRS Below:

Performance Objective and PWS Paragraph
Metric Type
Performance Standards*
Frequency
Acceptable

Quality level

(AQL)

Method of Inspection /Surveillance Method

Para 14 POAM

Deliverables required by the Contract meet the schedule provided in the PWS.

Schedule
Contract deliverables shall be submitted to the COR in accordance with the POAM times required by the PWS.
Continual
100% of the deliverables are submitted on schedule.
COR Tracking

Para 7 Testing

Successful completion of testing and the acceptance of the test results by Regulatory Bodies.

Quality
Contractor shall successfully complete Testing and; gain USCG and ABS acceptance of the test results.
Continual
100% of testing will be completed successfully on the first attempt with test results accepted by USCG and ABS.
COR

Tracking / USCG and ABS acceptance of Test results.

Para 8 Manuals/Operating Procedures/Training and Attachment 2 of PWS

Accuracy of Deliverables Required by the Contract

Quality
Material/Part Lists, Tech Manuals, Maintenance Plan and Other Deliverables associated with Para 8.
Continual
No more than 4 Errors per

Deliverable

COR

Review for completion and accuracy

Para 10 (10.1 and 10.2) Delivery Requirements

Quality of Deliverables Required by the Contract submitted to MSC and to USCG and ABS approval.

Quality
Reports, Drawings, Cost Estimates, and other Deliverables associated with Para 10.1 and 10.2. are Correct when submitted.
Continual
No more than 4 Errors per

Deliverable

COR

Review for completion and accuracy

Para 10 (10.3) Lifeboat Systems

Contractor shall meet the requirements for storage, outfitting and expiration dates of associated equipment and provisions provided in the PWS.

Quality
Reports, Drawings, Cost Estimates, and Deliverables are Correct when submitted.
Continual
No more than 4 Errors per

Deliverable Inspection at storage location and delivery location.

File details come from the government source that posted it. Updated .