This document includes a Performance Requirement Summary and Contract Discrepancy Report template for refuse and recycling collection and disposal services. The Coast Guard Sector New York requires collection of solid waste and recyclable materials from facility, commercial, and residential areas under Solicitation 70Z08420Q1GV87401. Critical tasks like on-time container delivery, site maintenance, and container upkeep allow no more than 2 defects monthly. All other tasks permit up to 4 defects for acceptable performance. The Contracting Officer's Representative will issue Contract Discrepancy Reports for unacceptable performance deducting 25% of one day's pay from the contractor's monthly invoice. Deductions over 4 in a fiscal year may negatively affect performance evaluations. The solicitation period and award date are not specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 70Z08420Q1GV87401 Amendment 1.pdf | ||
| 70Z08420Q1GV87401 NY Refuse.pdf | ||
| QASP - Attachment 4.pdf | ||
| Schedule B - Attachment 1.xlsx | XLSX spreadsheet | |
| PWS Enclosure 1.docx | DOCX document | |
| PWS - Attachment 2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REFUSE AND RECYCLING COLLECTION AND DISPOSAL SERVICES 70Z08420Q1GV87400
USCG SECTOR NEW YORK, STATEN ISLAND, NEW YORK Attachment 3
PERFORMANCE REQUIREMENT SUMMARY
1. The Government exprects the Contractor to perform all services required in the Performance Work Statement (PWS) at an acceptable level. Whenever the Government learns of substandard performance, either through periodic inspections, direct observation, customer complaints, or any other mechanism, the preferred course of action will be discussions with the Contractor to inform the Contractor of a problem. Discussions should effectively prevent recurrences of substandard performance. However, this Performance Requirement Summary (PRS) provides an alternative mechanism by which the Government’s payment to the Contractor may be reduced in the event of substandard performance.
2. Criteria for acceptable and unacceptable levels of performance are as follows: Certain tasks will be considered critical to the Government’s performance of its duty to its personnel as well as for safety, well being and health and welfare. Because of this, the Government has listed certain tasks as critical and must be completed properly every time as scheduled. Coast Guard Sector New York identified the below listed items as critical contract requirements:
a. On Time Delivery of On-Call Containers (PWS Item 3.)
b. Site Maintenance and Cleanup (PWS Item 6.)
c. Container Construction and Maintenance (PWS Item 8.)
The standards for the above items must not exceed 2 defects per month because of this criticality. All other tasks per the contract may have up to 4 defects and will still be considered acceptable. However, any complaints received thereafter will cause the services to be unacceptable for that month.
3. The Government’s primary quality assurance procedures are based on validated customer complaints and periodic inspections by the Contrating Officer’s Representattive (COR). One complaint will be counted for each reported and verified unacceptable performance of service (as listed in the PWS). Thus, if one person complains that the 6 cubic yard container outside the galley was not emptied during a one week period and that the immediate vicinity of any containers was not cleaned during collection, this would count as two complaints, one for each unsatisfactory performance of service. However, if two different people complain about the same 6 cubic yard container outside the galley not emptied during a one week period; this would only count as one complaint because both complaints stemmed from the same unsatisfactory performance.
4. When the number of defect in the Contractor’s performance exceeds the allowable number of defects, the COR shall initiate a Contract Discrepancy Report (CDR). In response to the CDR the Contractor will be required to explain, in writing, why performance was unsatisfactory, how performance will be returned to satisfactory levels, and how recurrence of the problem will be prevented. The Contractor’s payment shall be 25% of one days pay. If the Contractor is required to rework services found by the Government to be unsatisfactory, it will be at the contractor’s expense.
5. The Contractor shall be paid for all work performed to the contract standards. Monthly payment may be reduced for unsatisfactory performance, using the following computations:
Example: The Contractor performs required services during the month. The COR receives 4 complaints in a non critical area. These 4 errors computer as unacceptable. The COR takes the Contract Price (Total invoiced amount for the month) and divides it by the number of days worked that month; then multiplies that number by the deduction rate (25%) which becomes the deduction for that month.
Contract Price: $1,000.00/4 times in the month = $250.00 X 25% = $62.50
6. A defect will not be counted when the service is re-performed within 2 hours after notification by the COR and receives an acceptale rating by the COR.
7. Deductions shall not be deemed to waive or limit any right of the Government under the clauses entitled “Default” and “Inspection of Services”.
8. If more than 4 deductions are taken per fiscal year, Contractor Performance Evaluations may reflect poor performance ratings.
CONTRACT DISCREPANY REPORT (CDR)
1. Contract No._______________DO#___________2. FY________3. Report # _____
4. TO: (Contractor)________________________________________
5. FROM: (COR) _____________________________________________
6. DATES:
Prepared | Oral Notification | Returned by Contractor | Action Complete
7. Discrepancy or Problem [Describe in detail; include references to PWS paragraph or other contract clause or provision; attach continuation sheet if necessary; COR shall cite applicable QC program procedure(s)]
8. TO: (COR)_____
9. FROM: (Contractor)________________________________________________
10. Contractor’s response as to cause, corrective action and actions to prevent reoccurrence (attach continuation sheet if necessary):
11. Signature of Contractor’s Representative:
________________________________________________Date____________________
12. Government Evaluation; acceptance, partial acceptance, rejection (attach continuation sheet if necessary):
13. Government Actions: payment deductions, performance evaluation meetings, other actions)
14. Close-out Actions (contractor notified; by whom/date; follow-up actions pending):