- 2000+ °C Furnace Complete System Federal contract opportunity
- Solicitation number
- 12444824Q0024
- Issued by
- Department of Agriculture Forest Service
About this file
This document is the Proposal Evaluation Criteria for a U.S. Department of Agriculture (USDA) solicitation to procure a 2000+ °C Furnace Complete System. The key evaluation factors include: 1) Technical factors such as maximum working temperature, ability to operate with reactive gases, and sample size; 2) Past Performance; and 3) Cost/Price. Proposals will be evaluated using adjectival ratings (Exceptional, Very Good, Satisfactory, Marginal, Unsatisfactory), Go/No Go ratings, and performance confidence assessments. The solicitation is a 100% small business set-aside under NAICS code 333994, with a Firm-Fixed Price contract to be awarded to the Lowest Price Technically Acceptable offeror. Offers are due by August 25, 2024 at 2:00 pm CST, and must be submitted via email. Any amendments to the solicitation will be posted on SAM.gov, and offerors are responsible for acknowledging them.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Statement of Work 2000 Degree Furnace.docx | DOCX document | |
| Sol_12444824Q0024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Proposal Evaluation Criteria
Contents
| Section 1: Evaluation Methodology | 3 | |
| Section 2: Evaluation Factors | 3 | |
| 1.1 | Factor 1 <Technical Factors> | 3 |
| 1.1.1 | Subfactor 1 <Maximum Working Temperature> | 3 |
| 1.1.2 | Subfactor 2 <Ability to operate using reactive gas atmosphere> | 3 |
| 1.1.3 | Subfactor 3 <Sample Size> | 4 |
| 1.2 | Factor 2: Past Performance | 4 |
| 1.2.1 | Past Performance | 4 |
| 1.3 | Factor 3: Cost/Price | 4 |
| 1.3.1 | Contract Cost/Price | 4 |
| Section 3: Definitions | 4 | |
| 2.1 | Go/No Go Ratings | 4 |
| 2.2 | Adjectival Ratings | 5 |
| 2.3 | Technical Confidence Rating | 5 |
| 2.4 | Past Performance Confidence | 5 |
| 2.5 | Performance Confidence Assessment | 6 |
| 2.6 | Quote/Proposal Metrics | 6 |
Section 1: Evaluation Methodology Ratings based on Technical aspects of a quote/proposal will utilize the Adjectival Rating, Go/No Go and/or Confidence Ratings systems (defined below).
Technical Evaluation Factors
· Maximum working temperature.
· Ability to operate using reactive gasses.
· Maximum sample size.
Section 2: Evaluation Factors The award decision is based on evaluation factors and significant subfactors that are tailored to the acquisition.
Evaluation factors and significant subfactors must:
1. Represent the key areas of importance and emphasis that directly relate to the purpose or objective of the acquisition; and
2. Support meaningful comparison and discrimination between and among competing proposals.
Select whether all evaluation factors other than cost or price, when combined, are:
1. Significantly more important than cost or price; or
2. Approximately equal to cost or price; or
3. Significantly less important than cost or price.
State whether the evaluation factors are:
1. “In ascending order of importance” (increasing in importance); or
2. “In descending order of importance” (decreasing in importance), or
3. “All of equal importance”
1.1 Factor 1 <Technical Factors>
1.1.1 Subfactor 1 <Maximum Working Temperature>
Submission Requirements:
What USDA will use to evaluate this subfactor
· The minimum requirement is for the furnace to reach 2000 °C working temperature. There is a desire, however, to exceed 2000 °C and approach a working temperature of approximately 2500 °C or greater. Greater rating is due for proposals that can offer temperatures exceeding the 2000 °C minimum.
Evaluation Criteria/Methodology:
Adjectival Rating, Go/No Go and/or Confidence Ratings, and the relationship between the methodology. For example: The adjectival rating and the confidence rating are of equal importance.
· Proposals with maximum working temperatures less than 2000 °C will be rated as unsatisfactory proposals.
· Proposals with maximum working temperature of 2000 °C will be rated as satisfactory proposals.
· Proposals with maximum working temperature of greater than 2000 °C but less than 2500 °C will be rated as very good proposals.
· Proposals with maximum working temperature of 2500 °C or greater will be rated as exceptional proposals.
1.1.2 Subfactor 2 <Ability to operate using reactive gas atmosphere> Submission Requirements:
What USDA will use to evaluate this subfactor
· There is a desire to use reactive gases such as 4% H2 / 96% Ar, 4% CH4 / 96% Ar, or 5% NH3 / 95% Ar in the furnace. Furnaces capable of operating under reactive gas atmospheres will receive a higher rating than furnaces only capable of operating under vacuum or inert gas (i.e. Ar, N2) atmosphere. The price is expected to increase if reactive gases can be used.
Evaluation Criteria/Methodology:
Adjectival Rating, Go/No Go and/or Confidence Ratings, and the relationship between the methodology. For example: The adjectival rating and the confidence rating are of equal importance.
· Proposals not allowing use of reactive gases will be rated as marginal.
· Proposals allowing use of one reactive gas type will be rated as satisfactory proposals.
· Proposals allowing use of two reactive gas types will be rated as very good proposals.
· Proposals allowing use of three or more reactive gas types will be rated as exceptional proposals.
1.1.3 Subfactor 3 <Sample Size>
· The desired sample size for material heated in the furnace is 3” diameter x 8” long/height. Furnace chamber must be able to accommodate samples this size.
Evaluation Criteria/Methodology:
· Proposals will be evaluated on a Go/No Go methodology. Specifically, for a vendor to be considered for an award, the proposed solution must meet the minimum technical criteria listed for sample size.
1.2 Factor 3: Cost/Price
1.2.1 Contract Cost/Price
Lowest Cost and within government estimate
Section 3: Definitions
2.1 Go/No Go Ratings
The term “Pass/Fail” will not be utilized in any rating; instead “Go/No Go” will be utilized. When Go/No Go ratings are utilized the following sentence shall appear in the request “Specifically, for a vendor to be considered for an award, the proposed solution must meet the minimum technical criteria listed.”
2.2 Adjectival Ratings
| Adjectival Rating |
| Definition |
| Exceptional |
| Quote/Offer contains no deficiencies and fully addresses all aspects of the criteria and demonstrates an excellent approach/solution and understanding of the requirements. Many strengths exist, far outweighing any weaknesses. The highest quality of contract performance is anticipated with very low risk. |
| Very Good |
| Quote/Offer contains no deficiencies; fully addresses all aspects of the criteria and demonstrates a very effective approach/solution and understanding of the requirements. Some weaknesses may exist; however, the weaknesses, if any, are outweighed by strengths. A high quality of contract performance is anticipated with low risk. |
| Satisfactory |
| Quote/Offer contains no deficiencies; addresses all aspects of the criteria and demonstrates an adequate approach/solution and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. A quality contract performance is anticipated with an acceptable amount of risk. |
| Marginal |
| Quote/Offer may contain deficiencies; fails to address all of the criteria and does not demonstrate an adequate approach/solution or understanding of the requirements. One or more weaknesses exist which are not offset by strengths. Contract performance is anticipated with high risk. |
| Unsatisfactory |
| Quote/Offer contains many deficiencies and does not address all aspects of the criteria and/or does not present evidence demonstrating an adequate approach/solution and understanding of the requirements. Many weaknesses and/or omissions exist creating an unacceptable risk. |
2.3 Technical Confidence Rating
| Confidence Rating |
| Definition |
High Confidence (Low Risk) The Government has high confidence the vendor understands the requirement, proposes a sound approach, and will be successful in performing the contract with little or no Government intervention.
Some Confidence (Moderate Risk) The Government has some confidence the vendor understands the requirement, proposes a sound approach, and will be successful in performing the contract with some Government intervention.
Low Confidence (High Risk) The Government has low confidence the vendor understands the requirement, proposes a sound approach, or will be successful in performing the contract even with Government intervention.
2.4 Quote/Proposal Metrics
When identifying the merits of a quote/proposal the following three terms shall be utilized along with the definitions.
| Narrative Element |
| Definition |
| Strength |
| A significant, outstanding, or exceptionally positive aspect of a Quote/Offer. |
| Weakness |
| Any aspect of a Quote/Offer increasing the potential for problems and issues with regard to contract performance. The Quote/Offer provides a minimally acceptable response to the Government’s requirements. The response leaves the evaluator with uncertainty as to the understanding of the work, capability to successfully perform the work, or capability to effectively manage the work effort. |
| Deficiency |
| A material failure of a Quote/Offer to meet a Government requirement or a combination of significant weaknesses in a Quote/Offer increasing the risk of unsuccessful contract performance to an unacceptable level. |
image1.png