This Request for Proposals (RFP-24-049616) is issued by the City of Marietta, Georgia for the construction of a lean-to roof addition to the Fleet Maintenance Building. The project scope involves designing and constructing a metal lean-to structure measuring approximately 48 feet wide by 30 feet long by 18 feet high to cover an existing adjacent slab and provide additional covered vehicle work area. The addition requires attachment to the existing building at or about the first purlin height above existing bay doors, with engineered sealed design and construction drawings to be provided by the contractor after bid award and permit acquisition. Sealed proposals are due by 11:00 P.M. on Thursday, September 21, 2023, at the City of Marietta Purchasing Division, 205 Lawrence Street, Marietta, Georgia 30060. A mandatory pre-proposal conference will be held on Wednesday, September 6, 2023, at 9:00 A.M. at the City of Marietta Public Works Complex, 725 North Marietta Parkway, Marietta, Georgia 30060; only registered attendees' proposals will be accepted. Vendor names will be read publicly at 11:00 A.M. on the proposal closing date.

Proposals must remain valid for 90 days following the proposal closing date. Award will be made to the lowest responsive and responsible proposer based on evaluation criteria including proposal pricing (50%), contractor experience (20%), previous similar applications and construction (20%), and project timeline (10%). The successful contractor must furnish a performance bond and payment bond each for the full contract amount, with maintenance provisions remaining in effect for twelve months after work acceptance. Required insurance coverage includes workers' compensation (statutory limits), comprehensive general liability ($1,000,000 per person/$1,000,000 per occurrence for bodily injury and property damage), and automobile liability ($1,000,000 combined single limit). Contractors must comply with Georgia's E-Verify work authorization requirements and provide drug-free workplace certification. Three original signed proposals and three copies must be submitted in a sealed package addressed to Rick Churbock, CPPB, at the Purchasing Division. All applicable Georgia state laws, City of Marietta ordinances, and federal codes and standards including OSHA, EPA, and ANSI ASTM requirements apply to the resulting contract.

Text of this file

REQUEST FOR PROPOSALS

FLEET MAINTENANCE BUILDING LEAN-TO

ADDITION

RFP-24-049616

CITY OF MARIETTA

PURCHASING DIVISION

205 Lawrence Street

Marietta, Georgia 30060

TABLE OF CONTENTS

REQUEST FOR PROPOSAL NO. RFP-24-049616

FOR

FLEET MAINTENANCE BUILDING LEAN-TO ADDITION

TITLE _____ PAGE

INSTRUCTIONS TO PROPOSERS 1 - 14

EXHIBIT A: DRUG FREE WORKPLACE CERTIFICATION 10

EXHIBIT B: ALTERATIONS/EXCEPTIONS 11

EXHIBIT C: WORK AUTHORIZATION PROGRAM 12-14

EXHIBIT D: SPECIFICATIONS S –1 - S-2

Instructions to proposers Page 1

INSTRUCTIONS TO PROPOSERS

FOR INVITATION FOR PROPOSALS

ARTICLE 1 TIME AND DATE DUE

The City of Marietta, a political subdivision of the State of Georgia (hereinafter "City of Marietta" or the "City") shall receive sealed proposals from individuals, corporations, partnerships, and other legal entities organized under the laws of the State of Georgia or authorized to conduct business in the State of Georgia until 11:00 P.M., Thursday, September 21, 2023 for the following:

All proposal requirements shall be in accordance with Scope of Work (Pages S-1 through S-2) dated August 8, 2023 and attached hereto.

ARTICLE 2 OPENING LOCATION & TIME

Names of vendors submitting proposals shall be read at 11:00 PM., Thursday, September 21, 2023 at the City of Marietta Purchasing Division, First Floor, 205 Lawrence Street, Marietta, Georgia 30060.

ARTICLE 3 PRE-PROPOSAL CONFERENCE

There shall be a Mandatory Pre‐Proposal Conference to be held at 9:00 a.m. on Wednesday, September 6, 2023 at City of Marietta, Public Works Complex, 725 North Marietta Parkway, Marietta, Georgia 30060. This is a Mandatory Pre-Proposal Conference and only registered attendee’s proposals will be accepted.

ARTICLE 4 DELIVERY REQUIREMENTS

Any proposals received after the stated time and date shall not be considered. It shall be the sole responsibility of the proposer to have their proposal delivered to the City of Marietta Purchasing Division for receipt on or before the above stated time and date. If a proposal is sent by the U.S. Postal Service, the proposer shall be responsible for its timely delivery to the Purchasing Division. Proposals delayed by the mail shall not be opened at the public opening, and arrangements shall be made for their return at the proposer's request and expense.

Instructions to proposers Page 2

ARTICLE 5 CLARIFICATION & ADDENDA

Each proposer shall examine all invitation for proposal documents and shall judge all matters relating to the adequacy and accuracy of such documents. Any inquiries, suggestions, or requests concerning interpretation, clarification or additional information pertaining to the invitation to proposal shall be made through the City of Marietta, Purchasing Division. The City shall not be liable for oral interpretations given by any City employee, representative, or others. The issuance of a written addendum is the only official method whereby interpretation, clarification or additional information can be given.

If any addenda are issued to this invitation for proposal, the City shall attempt to notify all prospective proposers who have secured the same, however, it shall be the responsibility of each proposer prior to submitting their proposal to contact the City of Marietta, Purchasing Division at (770) 794-5257 72 hours prior to proposal due date to determine if any addenda were issued and to make sure such addenda is a part of their proposal.

EACH PROPOSER SHALL ACKNOWLEDGE ALL ADDENDA BY SIGNING A COPY

ADDENDA RECEIVED AND ATTACHING WITH PROPOSAL.

ARTICLE 6 USE, CLARIFICATION AND RETURN OF SPECIFICATIONS AND SERVICE

All Proposals are the sole property of the Owner and intended solely for use in the work contemplated in such Proposal. Except for a proposer whose proposal is accepted, said Proposals shall be returned in good condition immediately upon receipt of notification that a proposal has been accepted or that no award of said proposal shall be accepted.

If there are any discrepancies in, or omissions from, the Proposal, or if the proposer is in doubt as to the true meaning of any part of the Contract Document, he shall request clarification from The Purchasing Division. Such request shall be in writing and shall be made not less than forty-eight hours prior to the time scheduled for the termination of proposal. Interpretations in response to inquiries for any proposer, clarifications or corrections issued in the form of addenda shall be mailed to each proposer. If the proposer fails to request clarification regarding methods of performing work or the material required, his proposal shall be deemed to include the method requiring the greater quantity of work or material or upon the material of greatest cost indicated.

ARTICLE 7 BUSINESS LICENSE /OCCUPATIONAL LICENSE

The proposer shall provide appropriate proof of an Occupational Tax license

Instructions to proposers Page 3

ARTICLE 8 SEALED & MARKED

THREE (3) ORIGINAL SIGNED PROPOSALS AND THREE (3) COPIES OF YOUR

PROPOSAL SHALL BE SUBMITTED IN ONE SEALED PACKAGE, CLEARLY MARKED

ON THE OUTSIDE:

REQUEST FOR PROPOSAL

and addressed to:

City of Marietta, Purchasing Division 205 Lawrence Street

Marietta, Georgia 30060 Attention: Rick Churbock, CPPB

ARTICLE 9 LEGAL NAME

Proposals shall clearly indicate the legal name, address and telephone of the respective proposer (company, firm, partnership, individual). Proposals shall be signed above the typed or printed name and title of the signer. The signer shall have the authority to bind the proposer to the submitted proposal.

ARTICLE 10 PROPOSAL EXPENSES

All expenses for making proposals to the City are to be borne by the proposer.

ARTICLE 11 IRREVOCABLE OFFER

Any proposal may be withdrawn up until the date and time set above for the opening of proposal. Any proposal not withdrawn shall, upon opening, constitute an irrevocable offer for a period of 90 days to sell to The City of Marietta the goods or services set forth in the attached specifications until one or more of the proposals have been duly accepted by the City. All prices shall be quoted F.O.B. City of Marietta, Georgia.

Proposal modifications shall be accepted from a proposer only if received prior to the scheduled proposal opening, in writing, properly signed by the authorized representative of the proposer’s (company, firm, partnership, individual). Proposal modifications shall be submitted as referenced in Article No. 8 and clearly marked “PROPOSAL

MODIFICATIONS.”

Mathematical errors shall be corrected by the City, i.e.: misplaced decimal points shall be corrected; in discrepancies between unit price vs. extended price, unit price shall govern;

errors in extension of unit prices shall be corrected and mathematical errors shall be corrected.

Instructions to proposers Page 4

ARTICLE 12 RESERVED RIGHTS

The City reserves the right to accept or reject any and or all proposals, to waive irregularities and technicalities, award the contract in the best interest of the City of Marietta or to request re-proposal. The City reserves the right to accept all or any part of the proposal and to increase or decrease quantities to meet additional or reduced requirements of the City

For each item or for all items combined, the proposal of the lowest, responsible and responsive proposer shall be accepted, unless all proposals are rejected. The lowest responsive proposer shall mean the proposer who makes the lowest proposal to sell goods and/or services of a quality which conforms closest to the quality of goods/and or services set forth in the attached specifications or otherwise required by the City, and conforms to all material aspects of the requirements set forth in the invitation for proposal. To be a responsible proposer, the proposer shall be fit and capable to perform the work as required, shall have the capability in all respects to perform fully the contract requirements, and shall have the tenacity, perseverance, experience, integrity, reliability, capacity, facilities, equipment, and credit which shall assure good faith performance.

Also, the City reserves the right to make such investigations as it deems necessary to determine the ability of any proposer to deliver the goods or service requested.

Information the City deems necessary to make this determination shall be provided by the proposer. Such information may include, but shall not be limited to current financial statements; verification of availability of equipment and personnel; and past performance records.

ARTICLE 13 APPLICABLE LAWS

Proposers shall be authorized to transact business in the State of Georgia. All applicable laws and regulations of the State of Georgia and ordinances and regulations of the City of Marietta shall apply to any resulting agreement.

ARTICLE 14 CODE OF ETHICS

With respect to this proposal, if any proposer violates or is a part to a violation of the State of Georgia, Code of Ethics for Public Officers and Employees, such proposer may be disqualified from furnishing the goods or services for which the proposal is submitted and shall be further disqualified from submitting any future proposals for goods or services for the City of Marietta.

Instructions to proposers Page 5

ARTICLE 15 COLLUSION

By offering a submission to this invitation for proposal, the proposer certifies that the proposer has not divulged to, discussed or compared his proposal with other proposers and has not colluded with any other proposer or parties to this proposal whatsoever.

Also, proposer certifies, and in the case of a joint proposal each party thereto certifies as to his/her own organization, that in connection with this proposal:

15.1 Any prices and/or cost data submitted have been arrived at independently, without consultation, communication, or agreement, for the purpose of restricting competition, as to any matter relating to such prices and or cost data, with any other proposer or with any competitor;

15.2 Any prices and/or cost data quoted for this proposal have not been knowingly disclosed by the proposer and shall not knowingly be disclosed by the proposer prior to the scheduled opening directly or indirectly to any other PROPOSER or to any competitor;

15.3 No attempt has been made or shall be made by the PROPOSER to induce any other person or firm to submit a proposal for the purpose of restricting competition;

15.4 The only person or persons interested in this proposal, principal/principals is/are named therein and that no person other than therein mentioned has any interest in his proposal or in the contract to be entered into; and

15.5 No person or agency has employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or established commercial agencies maintained by the Purchaser for the purpose of doing business.

ARTICLE 16 CONTRACT FORMS

Any agreement, contract or Purchase Order resulting from the acceptance of a proposal shall be on forms provided by the City. Each proposer shall state in his proposal, in words and numerical, written in ink or typed, the price for which he shall perform the work or supply the items required by the specifications, plans and contract documents. Any erasures, delineations or alterations are to be clear and initialed by the person signing.

ARTICLE 17 NOTICE OF ACCEPTANCE

Owner shall notify the successful proposer of its acceptance of the proposal by depositing an executed copy thereof in the United States mail. Such notice shall be sent by certified mail, with postage prepaid, to the name and address of such proposer as stated in the proposal.

Instructions to proposers Page 6

ARTICLE 18 PROPOSAL FORMS, VARIANCES, ALTERNATES

Proposals shall be submitted with attached City forms. PROPOSERS SHALL SUBMIT

PROPOSAL DOCUMENTS, ALL DOCUMENTS REQUIRING SIGNATURES AND ANY

OTHER ATTACHMENTS (LICENSES, SPECIFICATIONS, ETC.) REQUIRED FOR THIS

PROPOSAL WITH ORIGINAL SIGNATURES WHERE APPLICABLE AND SEVEN

COPIES.

Proposers shall indicate any and all variances/exceptions from the City requested specifications, terms, and conditions on sheet entitled “EXHIBIT C” Providing there has been no variances/exceptions or alterations attached to said proposal, it shall be assumed that the proposer is meeting all requirement of the specifications. Alternate proposals may or may not be considered at the sole discretion of the City.

ARTICLE 19 DISCOUNTS

Any and all discounts shall be incorporated as a reduction in the proposal price and not shown separately. The price as shown on the proposal shall be the price used in determining awards.

ARTICLE 20 DESCRIPTIVE INFORMATION

Unless otherwise specifically provided in the specifications, reference to any equipment, material, article or patented process, by trade name, make or catalogue number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. If the proposer wishes to make substitution to the specifications, proposer shall furnish to the City the name of the manufacturer, the model number, and other identifying data and information necessary to aid the City in evaluating the substitution, and such substitution shall be subject to City approval. Substitutions shall be approved only if determined by the City to be equivalent to the specifications. A proposal containing a substitution is not accepted until such time as it is approved by the City.

ARTICLE 21 TAXES

The City of Marietta is exempt from Federal Excise and State Sale Taxes; therefore the proposer is prohibited from delineating a separate line item in his proposal for any sales or service taxes. The City of Marietta does not intend to imply that a proposer has no independent tax liability.

Instructions to proposers Page 7

ARTICLE 22 USE OF TRADE NAMES

Brand or trade names referenced in specifications are for comparison purposes only.

Proposers may submit proposals on items manufactured by other than the manufacturer specified. In these instances, proposals shall be accompanied with all descriptive information necessary for a through evaluation of the proposed materials, equipment such as detailed drawings and specifications, certified operation and test data, and experience records, as well as an itemized list of any variance from, or exception taken to the specifications.

Failure of any proposer to furnish this data shall be cause for rejection of specified item(s) to which it pertains.

ARTICLE 23 REGULATIONS, CODES AND STANDARDS

It shall be the responsibility of each supplier to assure compliance with any and all Codes & Standards including but not limited to OSHA, EPA LIFESAFETY, ANSI ASTM, UA and/or other Federal or State of Georgia rules, regulations or other requirements, as each may apply.

When applicable, and as required under the provisions of Georgia's Right-To-Know-Law, the manufacturer, importer or distributor of a toxic substance shall provide a material safety sheet with the proposal.

ARTICLE 24 AUTHORIZED PRODUCTION REPRESENTATION

The successful proposer(s) by virtue of submitting the name and specifications of a manufacturer's product, shall be required to furnish the named manufacturer's product.

By virtue of submission of the stated documents it shall be presumed by the City that the proposer(s) is/are legally authorized to submit, and the successful proposer(s) shall be legally bound to perform according to the documents.

ARTICLE 22 BONDS

22.1 PERFORMANCE BOND

Upon execution and delivery of the contract, the bidder shall furnish the City a performance bond for the full amount of the contract. Maintenance provisions of the bond shall remain in effect for a period of twelve (12) months after acceptance of the work by the City. The surety shall be a reputable bonding company authorized to transact business in the State of Georgia.

22.2 PAYMENT BOND

Upon execution and delivery of the contract, the bidder shall furnish the City of Marietta a payment bond for the full amount of the contract. Maintenance provisions of the bond shall remain in effect for a period of twelve (12) months after acceptance of the work by the City. The surety shall be a reputable bonding company authorized to transact business in the State of Georgia.

Instructions to proposers Page 8

ARTICLE. 25 EQUAL EMPLOYMENT OPPORTUNITY CLAUSE

The City of Marietta, Marietta, Georgia, in accordance with the provisions of Title VI of The Civil Rights Act of 1964(78 Stat. 252) and the Regulations of the Division of Commerce (15 CFR, Part 8) issued pursuant to such Act, hereby notifies all proposers that it shall affirmatively ensure that in any contract entered into pursuant to this advertisement, minority business enterprises shall be afforded full opportunity to submit proposals in response to this advertisement and shall not be discriminated against on the grounds of race, color, disability or national origin in consideration for an award.

ARTICLE 26 DRUG FREE WORKPLACE

The City of Marietta is a DRUG FREE WORKPLACE. It is strongly suggested that the attached Drug Free Workplace Form (Exhibit A) be signed and returned to this office with the proposal. In the event of a tie proposal, receipt of a valid and accurate form may be used as basis for awarding the contract.

Instructions to proposers Page 9

ARTICLE 29 INSURANCE, INDEMNIFICATION, AND LIABILITY

Owner requires the vendor to have and maintain the following insurance coverage and indemnification provisions:

A. INSURANCE

The Contractor agrees to provide and maintain insurance coverage until the contract is completed and to furnish certificates from its insurance carriers, showing that it carries insurance in the following minimum limits:

I. Workmen’s Compensation Insurance Statutory

II. Comprehensive General Liability Insurance including:

Bodily Injury $1,000,000 per person $1,000,000 per occurrence

Property Damage $1,000,000 per person $1,000,000 annual aggregate

III.. Automobile Liability Insurance including:

$1,000,000 combined single limit

B. INDEMNIFICATION

The Contractor agrees to indemnify and save harmless the Owner, its agents, assigns, and employees from and against all claims, demands, liabilities, suits, judgments and decrees, losses and costs and expenses of any kind or nature whatsoever on account of injuries to or death of any person or persons or damage to any property occurring directly or indirectly from performance of work hereunder by contractor or his employees, agents, servants, associates or subcontractors however such injuries or death or damage to property may be caused.

C. LIMITATIONS OF LIABILITY

Owner shall not be liable in contract or in tort (including negligence) to Vendor, subcontractor or suppliers of Vendor, regardless of tier, for incidental or consequential damages arising out of or resulting from Owner’s performance or nonperformance of its obligations under this Agreement, or from Owner’s termination or suspension of the services under this Agreement.

Instructions to proposers Page 10

EXHIBIT A

DRUG FREE WORK PLACE CERTIFICATION

Identical Tie Proposals - Preference shall be given to businesses with drug-free workplace program. Whenever two or more proposals which equal with respect to price, quality and service are received by the State or by any political subdivision for the procurement of commodities or contractual services, a proposal received from a business that certifies that has implemented a drug-free work place program shall be given preference in the award process.

Established procedures processing tie proposals shall be followed if none of the tied vendors have drug-free workplace program. In order to have a drug-free workplace, a business shall:

1) Publish a statement notifying employees that the unlawful manufacture, distribution, dispensing, possession, or use of controlled substances is prohibited in the workplace and specifying the actions that shall be taken against employees for violation of such prohibition.

2) Inform employees about the dangers of drug abuse in the workplace, the business’s policy of maintaining a drug-free workplace, any available drug counseling, rehabilitation, and employee assistance programs, and the penalties that may be imposed upon employees for drug abuse violations.

3) Give each employee engaged in providing the commodities of contractual services that are under proposal a copy of the statement specified in the subsection (1).

4) In the statement specified in subsection (1), notify the employee that, as a condition of working on the commodities or contractual services that are under proposal, the employee shall abide by the terms of the statement and shall notify the employer of any conviction of, or plea of guilty or nolo contendere to, any violation of Chapter 893 or of any controlled substance law of the United States or any state, for a violation occurring in the workplace no later that five

(5) days after such conviction.

5) Impose a sanction on, or require that satisfactory participation in a drug abuse assistance or rehabilitation program if such is available in the employee’s community, by any employee who is so convicted.

6) Make a good faith effort to continue to maintain a drug-free workplace through implementation of this section.

As the person authorized to sign this statement, I certify that this firm complies fully with the above requirements.

COMPANY NAME AUTHORIZED SIGNATURE

Instructions to proposers Page 11

EXHIBIT B

ALTERATIONS /EXCEPTIONS

SPECIAL INSTRUCTION: ALL ITEMS SHALL BE TYPED OR PRINTED

Instructions to proposers Page 12

EXHIBIT C

Contractor Affidavit under O.C.G.A. § 13-10-91(b)(1)

By executing this affidavit, the undersigned contractor verifies its compliance with O.C.G.A. § 13-10-91, stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of services on behalf of THE CITY OF MARIETTA, GEORGIA has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91.

Furthermore, the undersigned contractor will continue to use the federal work authorization program throughout the contract period and the undersigned contractor will contract for the physical performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the contractor with the information required by O.C.G.A. § 13-10-91(b).

Contractor hereby attests that its federal work authorization user identification number and date of authorization are as follows:

Federal Work Authorization User Identification Number Date of Authorization Name of Contractor Name of Project Name of Public Employer

I hereby declare under penalty of perjury that the foregoing is true and correct.

Executed on ______, ___, 201__ in _____(city), ______(state).

Signature of Authorized Officer or Agent

Printed Name and Title of Authorized Officer or Agent

SUBSCRIBED AND SWORN BEFORE ME

ON THIS THE ______ DAY OF ______________,201__.

NOTARY PUBLIC

My Commission Expires:

Instructions to proposers Page 13

Subcontractor Affidavit under O.C.G.A. § 13-10-91(b)(3)

By executing this affidavit, the undersigned subcontractor verifies its compliance with O.C.G.A. § 13-10-91, stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of services under a contract with _____________________________________________(name of subcontractor) on behalf of THE CITY OF MARIETTA, GEORGIA has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the undersigned subcontractor will continue to use the federal work authorization program throughout the contract period and the undersigned subcontractor will contract for the physical performance of services in satisfaction of such contract only with sub-subcontractors who present an affidavit to the subcontractor with the information required by O.C.G.A. § 13-10-91(b). Additionally, the undersigned subcontractor will forward notice of the receipt of an affidavit from a sub-subcontractor to the contractor within five business days of receipt. If the undersigned subcontractor receives notice of receipt of an affidavit from any sub-subcontractor that has contracted with a sub-subcontractor to forward, within five business days of receipt, a copy of such notice to the contractor. Subcontractor hereby attests that its federal work authorization user identification number and date of authorization are as follows:

Federal Work Authorization User Identification Number Date of Authorization Name of Subcontractor Name of Project Name of Public Employer

I hereby declare under penalty of perjury that the foregoing is true and correct.

Executed on ______, ___, 201__ in _____(city), ______(state).

Signature of Authorized Officer or Agent Printed Name and Title of Authorized Officer or Agent

SUBSCRIBED AND SWORN BEFORE ME

ON THIS THE ______ DAY OF ______________,201__.

NOTARY PUBLIC

Instructions to proposers Page 14

Sub-subcontractor Affidavit under O.C.G.A. § 13-10-91(b)(4)

By executing this affidavit, the undersigned sub-subcontractor verifies its compliance with O.C.G.A. § 13-10-91, stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of services under a contract for _____________________________________________(name of subcontractor or sub-subcontractor with whom such sub-subcontractor has privity of contract) and ____________________________(name of contractor) on behalf of THE CITY OF MARIETTA, GEORGIA has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-

91. Furthermore, the undersigned sub-subcontractor will continue to use the federal work authorization program throughout the contract period and the undersigned sub-subcontractor will contract for the physical performance of services in satisfaction of such contract only with sub-subcontractors who present an affidavit to the sub-subcontractor with the information required by O.C.G.A. § 13-10-91(b). The undersigned sub-subcontractor shall submit, at the time of such contract, this affidavit to___________________________________ (name of subcontractor or sub-subcontractor with whom such sub-subcontractor has privity of contract).

Additionally, the undersigned sub-subcontractor will forward notice of the receipt of any affidavit from a sub-subcontractor to (name of subcontractor or sub-subcontractor with whom such sub-subcontractor has privity of contract). Sub-subcontractor hereby attests that its federal work authorization user identification number and date of authorization are as follows:

Federal Work Authorization User Identification Number Date of Authorization Name of Sub-subcontractor Name of Project Name of Public Employer

I hereby declare under penalty of perjury that the foregoing is true and correct.

Executed on ______, ___, 201__ in _____(city), ______(state).

Signature of Authorized Officer or Agent Printed Name and Title of Authorized Officer or Agent

SUBSCRIBED AND SWORN BEFORE ME

ON THIS THE ______ DAY OF ______________,201__.

NOTARY PUBLIC

S-1 08/09/2023

SPECIFICATIONS :

SPECIFICATIONS

CITY of MARIETTA

FLEET MAINTENANCE LEAN-TO ADDITION

The City of Marietta is requesting proposals for a lean-to roof addition to our existing fleet maintenance building. The purpose of this roof is to cover an existing slab adjacent to the building in order to provide additional covered vehicle work area. The approximate size of the lean-to roof is 48’W X 30’L X 18’H. Project components and or materials shall be metal and attachment to existing building shall be at or about the first purlin height above the existing bay doors.

Engineered sealed design and construction drawings shall be required after bid award and permit obtained by contractor. Design shall take into consideration the following and not limited to:

Attachment to the main structure All existing building components needing adjustment, relocation, modification Color matching, prime coat, and painting Gutter and downspouts for new lean-to Fascia and termination of roof deck panels, three sides Footings, support columns

S-2 08/09/2023

BID EVALUATIONS

A. All responsive proposals will be evaluated to determine which represents the lowest and best proposal. A proposal will be considered responsive if it contains all completed forms and attachments and bonds required by the proposal documents.

The factors considered when determining the lowest and best proposal include the following:

Proposal Pricing (50%)

Contractors’ proposal price shall be evaluated to ensure all labor and materials are covered in the scope of this project and that the city is receiving the best and lowest price.

Contractors Experience (20%)

Contractor’s references shall be evaluated to determine experience and knowledge of work necessary to preform and deliver a completed project as outlined in the scope and request for proposal.

Previous Similar Applications/Construction (20%)

Contractors shall provide previous projects that are similar in scope and nature for this project evaluation. Previous projects and or construction should be of similar material type and building attachments.

Project length (10%)

Contractor shall provide a realistic start date once a NTP is issued by the city and realistic substantial completion date for this project. Evaluation of this item shall be based upon reference information of similar projects.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .