Project_Specifications.pdf

PDF 30 MB Posted

Attached to
REPLACE BACKWASH POND LINER Federal contract opportunity
Solicitation number
140P8124Q0036
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

The provided document appears to be a Project Specifications document related to a federal contract opportunity to REPLACE BACKWASH POND LINER AT ECHO BAY, LAKE MEAD NATIONAL RECREATION AREA IN NEVADA. The solicitation number is 140P8124Q0036 and the Department of the Interior National Park Service Pacific West Region is the federal agency involved. The document details the required products and services, including replacing the backwash pond liner. No further details on response dates, award dates, pricing terms, set asides, incumbents, or other salient information are provided in the given information.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE BACKWASH POND LINER, newest first.
File Type Posted
Construction_Contract_Administration_Notice.pdf PDF
Wage_Determination_Clark_County.pdf PDF
Sol_140P8124Q0036.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LAKE MEAD

NATIONAL RECREATION AREA

Boulder City, Nevada

PMIS No. 248827

Replace Echo Bay Water Plant Backwash Pond Liner

CONTRACT SPECIFICATIONS

NATIONAL PARK SERVICE

PACIFIC WEST REGION

March 1, 2024

TABLE OF CONTENTS

NO. OF PAGES

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 11 40 Work Restrictions

01 27 00 Definition of Contract Price Items

01 31 00 Project Management

01 32 16 Construction Schedule

01 33 00 Submittal Procedures

01 35 23 Safety Requirements

01 40 00 Quality Requirements

01 50 00 Temp Facilities & Controls

01 67 00 Product Requirements

01 73 40 Execution

01 74 19 Waste Management

01 56 00 Barriers

01 77 00 Closeout Procedures

DIVISION 31 � EARTHWORK

31 38 10 Geomembrane Liner

31 38 25 Geotextiles

APPENDIX

LAKE Map and Distances

Echo Bay Pond Site Maps

Concept Drawing

Anchor Trench Typical Section

Description of Site

Transmittal Form CM-16

DIVISION 01

GENERAL REQUIREMENTS

LAKE � PMIS #248827 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00

SUMMARY OF WORK

PART 1 � GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

PROJECT LOCATION:

The project location is the Lake Mead National Recreation Area. The site is located in Echo Bay developed area outside of Boulder City, Nevada.

EXISITING CONDITIONS:

The backwash pond is located to the east of the water treatment plant off Echo Bay Road. The pond system consists of an approximately 960 square foot pond with 28,000 gallons of storage capacity.

The water treatment plant performs routine backwashing through the system to remove accumulated particles and debris, helping maintain the efficiency of the filters. The backwash water flows east by gravity to the backwash water pond through approximately 85 feet of 6-inch PVC pipe and past a 6-inch flapper valve where it drops into the pond. There is a small continuous flow of water into the pond, and every time the water plant performs a cleaning, it sends approximately 1000 gallons of chlorinated water into the pond where it has time to slow down the outflow and dilute before flowing out through the overflow drain and pipe into the nearby wash to the southeast side.

The pond structure is approximately 32 feet by 30 feet and has a maximum depth of 4 feet. There is a layer of geotextile fabric and a single membrane liner layer. The liner was damaged and ripped apart and a large amount of sediment has settled on top of the liner layer. Many tall reed plants have grown through the liner and various other vegetation debris surrounding the pond have fallen in as well, such as tree branches and shrubs. The liner is secured by an anchor trench around the perimeter of the pond

(2 feet deep and 2 feet wide). There is an overflow drain in the middle of the pond and approximately

35 feet of piping to the outlet into the wash.

The project requires construction services to repair and remedy the current deficiencies to the existing operation of the Backwash Pond. Annual inspections from the State of Nevada have determined the damaged liner as being out of compliance with holes in the liner. The installation of new liner in the backwash pond will allow the water plant to discharge to the pond as the permit states keeping the facility within the regulations. The National Park Service will not have to be concerned with possible state enforcing a violation order for not meeting the requirements for groundwater protection and possible groundwater contamination issues.

LAKE � PMIS #248827 01 11 00 - 2

A. The Work consists of the following:

1. Contractor will submit schedule, work plan, safety plan and product proposed to be used;

all for approval by CO.

2. Conduct Pre-work site visit to coordinate work areas and logistics of traffic plan.

3. Dewater pond and remove existing sediment, plants, and other debris inside pond to properly dispose of outside the park boundaries.

i. Plants inside pond have grown over 10 feet tall.

ii. The estimated depth of sediment is approximately 6-12� deep. Contractor shall verify quantity in field.

iii. No farming or burial of the removed sediment/debris is allowed on park property.

4. Clear vegetation/brush around perimeter of pond, approximately 5 feet from edge of pond, or required distance to perform proper preparation of site and installation of liner system.

5. Remove and dispose of the existing membrane liner system.

i. The existing material is a single layer geomembrane system on a soil base with a geotextile felt layer underneath.

6. Properly prepare, grade, and compact base beneath the liner material per industry standard.

7. Install new liner system.

i. The system shall consist of a base underlay felt layer and a geomembrane top layer

(a minimum of 60-mil thick).

ii. The preferred method of installation and anchoring of the liner material is the use of an anchor trench. The contractor shall be responsible for the excavation and installation of the anchor materials. Storage of the excavated materials along the trench is acceptable as long as the spoil piles so not block any other site access.

Alternate installation methods shall be submitted by the transmittal for review and approval.

1. Existing anchor trench is 2 feet wide by 2 feet deep, new anchor trench can be backfilled with material on site and properly compacted. See

Exhibit Anchor Trench Typical Section for more detail.

8. Replace 6-inch overflow drain located in pond and full length of outlet PVC pipe that discharges water out to the nearby wash.

i. New drain shall match the existing in type, service, and location. Approved equal submittals shall be reviewed and approved.

9. Replace two existing 6-inch PVC inlet pipes coming into lagoon from water plant.

LAKE � PMIS #248827 01 11 00 - 3

i. There are two existing inlet pipes which penetrate through membrane liner system which include two flapper valves.

ii. Flapper valves shall be replaced with two new duck bill valves located at the end of the pipes.

iii. A minimum of 10 feet of each inlet pipe shall be replaced from edge of pipe towards water treatment plant and properly installed per PVC pipe manufacturer�s installation standards.

1. The preferred method of tying in new piping to existing system is to glue or use bell ends.

2. New pipes shall be SDR 35 or C900. Approved equal submittals shall be reviewed and approved.

10. Pipe penetrations through the newly installed liner shall be properly sealed per industry standards. Pipe boots with stainless steel bands shall be installed per industry standard.

11. The water plant will have continuous flow during construction. Contractor shall divert water around the site while construction occurs to the downstream wash.

12. Permit for construction shall be obtained from the Nevada Department of Environmental

Protection prior to the start of construction.

13. Permit for construction shall be obtained (if needed) from the State of Nevada Division of Environmental Protection (NDEP) prior to the start of construction.

i. Contractor shall manage any permit application and closeout process with NDEP.

ii. Any engineering work that is needed to prepare closeout of the application shall be included in this proposal.

iii. Any engineering support shall be licensed in the State of Nevada to facilitate the application process. NDEP requires a Nevada Professional Engineer (PE) license and signature in their sections requiring PE signatures.

14. A daily log shall be prepared by the contractor representing the work that was performed that day.

i. The log shall describe the tasks performed that day and the contractor staff working.

ii. Two or more representative photos of the tasks being performed that day shall be included in each daily log.

iii. The submitted daily logs shall be in a PDF format. Emailing the CO/COR is acceptable.

LAKE � PMIS #248827 01 11 00 - 4

iv. The daily logs shall be sent to the CO/COR once a week. For every week working in the field, the daily log shall be sent to the CO/COR.

15. Return pond to service and clean site, properly disposing of any debris outside of park boundaries.

1.2 GOVERNMENT-FURNISHED ITEMS

A. No materials are government furnished.

1.3 PUBLIC USE OF THE SITE

A. General: The project site is not open to the public.

1.4 CONTRACTOR USE OF SITE

A. General: The site is located in a secured gated Maintenance area of the park. Security of site shall be maintained during construction. Limit use of the site during the construction period to the project area limits as outlined on the attached site map. Do not disturb portions of the site beyond the project area limits. Contractor shall at all times conduct his operations to ensure the least inconvenience to the recreation area visitors and employees. Contractor shall at all times maintain function of the water plant backwash flow operations by using piping or bypass pumping to divert the flow of water.

B. Park Entry: The contractor shall furnish a list of personnel with phone contact information.

Vehicles associated with the contractor shall be waived entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicles. The entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.

C. Site Access: The contractor shall access the project site as outlined on the attached site map or work with the COR for agreed upon use of those access points. Do not drive vehicles off road or access non-project areas without permission from the contracting officer or COR.

D. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

E. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until

5:00 p.m. Monday through Friday, excluding government holidays. Overtime will be paid per Davis Bacon Wages Regulations. Work outside regular hours requires approval from the

LAKE � PMIS #248827 01 11 00 - 5

contracting officer. No work will be performed on weekends or on federal holidays without the advanced written authorization of the CO.

1. Request for alternate work schedules shall be submitted to the CO/COR for approvals at least 3 business days before the requested work day.

F. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

G. Staging and Storage: Confine storage of equipment and materials to the staging / lay-down / storage areas identified at the preconstruction meeting.

H. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along roads or in associated overlooks / pull-outs.

I. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.

J. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.

K. Refer also to Section 01 11 40 Work Restrictions.

L. Field Verification: The Contractor shall field verify all new and existing dimensions affecting the work in this contract before ordering any materials, equipment, or parts. The scheduling of field verification site visits to the water plant backwash pond shall be coordinated with the

COR.

M. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for interruption of existing utility service, if appropriate.

1. Contractor shall be responsible for locating and preventing damage to known utilities.

If damage occurs, repair of the utility at no additional expense to the Government.

2. If damage occurs to an unknown utility, the utility shall be repaired. An equitable adjustment will be made in accordance with the Changes clause of the General

Provisions.

LAKE � PMIS #248827 01 11 00 - 6

N. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent.

O. Care shall be taken to ensure that fuel, oil, and other spills do not occur. If spills occur, cleanup will be completed at no additional expense to the Government.

1.5 SPECIAL PROVISIONS

A. Permitting and Fees:

1. The Contractor is responsible for obtaining and paying for all fees and costs for necessary permits and approvals for all construction activities associated with this

Project.

2. Permits from the Nevada Department of Environmental Protection (NDEP) are expected to be needed.

3. Scott Bell, Environmental Protection Specialist shall be listed as the owner/operator for all NDEP applications and permits.

4. Prior to beginning site construction, apply for and receive any needed permits and approvals from NDEP. No work shall commence prior to receiving permits and approvals. A copy of the permits and approvals shall be forwarded to the NPS for review.

B. Logistics: NPS Employee access should be maintained to all facilities during construction. The

Contractor shall be responsible for the security of all materials staged/stored on LAKE NRA property.

C. Environmental Compliance Requirements:

1. The Contractor and all employees working on the Project will be required to take �Desert

Tortoise Awareness Training� which will be provided by the Government at no cost to the

Contractor. This training will take approximately 30 minutes or less.

2. The Contractor�s employees shall never handle a desert tortoise.

3. The Contractor and employees shall immediately report the presence of any desert tortoise to the COR.

4. Herbicides shall not be used in or around the Project site.

5. The environmental compliance contact for this project is Kelly Wallace. For questions or additional information, contact the following people via email.

LAKE � PMIS #248827 01 11 00 - 7

a. Kelly Wallace, Biologist: kelly_wallace@nps.gov

D. Equipment Washing:

1. Equipment washing is required to preclude the introduction and spread of non-native species into the Park. Therefore, all equipment shall be cleaned outside of the Park before entering the Park. Equipment leaving the park for any reason must be rewashed before returning to the job site. Equipment that is moved from the job site, but remains within the original developed area, need not be re-washed prior to returning to the job site. It is also known that there are areas inside the Park that have non-native plants and weed species infestation. Therefore, before equipment can be moved from one developed area to another, it must be washed at the location identified on the Site Plan (see attached site plan and mileage table) to ensure weeds are not spread from one developed area to another.

2. The Contractor shall clean all equipment prior to the equipment entering Lake Mead National

Recreation Area. It is recommended that cleaning be accomplished by hot water, pressure washing, using water only. All equipment surfaces shall be cleaned, with special emphasis given to the undercarriage. This includes, but is not limited to: wheel wells, bumpers, radiator grills, springs, shock absorbers, wire harnesses, skid plates, oil pans, axles, frame ledges, buckets, tracks, belly pans, etc. Cleaning shall also include all dirt and debris inside the cab, or operator area. A Shop-Vac or commercial car wash vacuum system may be used for operator compartments, provided the method used effectively removes all visible debris.

Equipment cleaning is for the purpose of removing any seed and soil accumulations to prevent the potential spread of non-native plant and weed species from outside the park to locations inside the park. Cleaning shall be performed in a manner that will reasonably remove all visible soil, plant and other foreign material. All equipment that requires washing shall be inspected by government personnel, or contractors/partners assigned to this duty, to ensure compliance.

3. Equipment that requires washing is generally defined as track or rubber-tired machinery intended for use primarily off-road. Examples include backhoes, loaders, earthmovers, graders, rollers, bulldozers, water trucks, etc; or four wheel drive or passenger vehicles that are driven in off road areas. Equipment may also be stationary, such as a material screening plant, conex storage containers, or a mobile office (mobile offices may be cleaned in the same manner as operator compartments as outlined in paragraph 2). The equipment is generally under the direct control of the contractor or sub-contractors, is likely to remain on the construction site for an extended period of time, and may contain adhered soil and seed from other project sites.

4. Equipment/Vehicles that do not require washing are defined as those normally used for highway driving only, and travel primarily on paved surfaces and well-maintained service roads and parking areas (this includes approved staging areas). Examples include semi-tractor trailers, dump trucks, concrete trucks, pickup trucks, fuel trucks, service trucks, etc. These

LAKE � PMIS #248827 01 11 00 - 8

delivery and passenger vehicles are generally not under the direct control of the contractor, have no earth-moving function, and do not remain on the project site. These vehicles have a low probability of carrying adhered soil and seed from other projects. However, every vehicle and piece of equipment is subject to rejection from entering the park if there are obvious signs (covered in mud, plant material adhered to it, etc.) that it could be transporting non-native species into the park.

E. Post Washing Equipment Inspections:

1. All equipment subject to inspection will be inspected by government, or other authorized personnel prior to leaving the paved surface or designated washing area identified on the Site

Plan. Equipment determined to be free of soil or mud based on visual examination by government personnel will be cleared to enter the project area or proceed to other areas of the park as appropriate. The Contractor shall arrange for needed inspections by contacting the

NPS inspection office no less than 5 working days prior to the inspection. Such contact shall provide sufficient time to accommodate scheduling and travel to the site. Equipment not passing initial inspection must be rewashed outside the park at no additional expense to the government.

2. A list of government Inspectors for this project will be provided by the list below. Please contact via email all members and coordinate designated representative for inspection:

a. Kelly Wallace, Biologist: kelly_wallace@nps.gov

1.6 REFERENCE DOCUMENTS / REPORTS

A. General: The following reference documents / reports are available upon request to supplement the information specified in the contract documents:

i. Not Applicable

1.7 DESIGNATED OFFICIALS

A. The NPS Project Manager (PM) and Contracting Officer's Representative (COR) will be:

Carl Bush PE, Lake Mead NRA

Telephone: 702-859-0194

E-mail: carl_bush@nps.gov

B. The Contracting Officer (CO) will be:

TBD

END OF SECTION 01 11 00

LAKE � PMIS 248827 01 11 40 - 1

WORK RESTRICTIONS

SECTION 01 11 40

WORK RESTRICTIONS

PART 1 � GENERAL

1.1 PARK REGULATIONS

A. General: The Contractor must comply with the following rules and conditions:

1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.

2. Ensure equipment is conspicuously marked for identification.

3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.

4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction / repair.

5. Control and provide security of Contractor-owned equipment and materials at the work site.

Report immediately missing / lost / stolen property to the park dispatch / law enforcement rangers at 702-293-8998 NON-EMERGENCY.

6. Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.

a. Contractor will provide the Contracting Officer with a listing of its subcontractors and their associated vehicles and employees entering the park on a daily basis.

b. Contractor will provide the Contracting Officer with a listing of anticipated deliveries for each week.

7. Vehicles / Heavy Equipment:

a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.

LAKE � PMIS 248827 01 11 40 - 2

b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.

c. Vehicle Exhaust: All vehicles will be properly maintained to insure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the

Contracting Officer of spills.

e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.

f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.

g. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.

h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road).

Oversized vehicles must not exceed the clearances along the Park road corridor.

Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.

i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).

j. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a park law enforcement ranger.

k. Road & Weight Restrictions: All vehicle load, weight and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11).

LAKE � PMIS 248827 01 11 40 - 3

No loads heavier than the current load rating for the historic Park bridge will be permitted.

8. Emergency Medical and Accident Reporting:

a. The Contractor or subcontractor shall contact Park Dispatch for any medical emergency or traffic accident occurring within the Park.

Emergency number: Dial 911 as needed.

Park Dispatch: 702-293-8932 EMERGENCY

Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles (e.g. ambulance) need to enter the Park and so that any available

Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.

b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a

Law Enforcement Ranger at the first available opportunity before leaving the park:

Park Dispatch: 702-293-8998 NON-EMERGENCY

1.2 RESOURCE PROTECTION

A. General: The park is committed protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:

1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to packing / loading. The park requires, and will perform, inspections to ensure non-transport of non-native species PRIOR to arriving at the park entrance. Contact the resource staff directly at 702-371-9673 or 702-293-8849 at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.

2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact park dispatch at 702-293-8998 immediately if animal is hit or injured or will not move off of the road. All contractor personnel working in Lake Mead

National Recreation Area must have up-to-date Lake Mead desert tortoise awareness training. Prior to starting work, contact the resource staff directly at 702-371-9673 or

702-293-8849 at least three (3) business days in advance to schedule the desert tortoise awareness training.

LAKE � PMIS 248827 01 11 40 - 4

3. Archaeological Resources: Archaeological resources are physical evidences of past human activity, including evidences of the effects of that activity on the environment.

Archaeological resources are found above and below ground and underwater. The contractor shall appoint an archaeological monitor during all ground-disturbing activities in archaeological sensitive areas. If the monitor discovers resources, the contractor shall stop work or relocate work to a non-sensitive area and contact the contracting officer immediately. Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.

4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.

END OF SECTION 01 11 40

LAKE � PMIS #248827 01 27 00 - 1

DEFINITION OF CONTRACT PRICE ITEMS

SECTION 01 27 00

DEFINITION OF CONTRACT PRICE ITEMS

PART 1 � GENERAL

1.1 DESCRIPTION

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one bid item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related bid item.

1.2 LIST OF CONTRACT LINE ITEMS

A. Contract Price Item No.1 � Dewatering and Disposal of Sediment, Plant Debris, and Liner

Material

1. This price item consists of:

All necessary materials, equipment, and labor to properly dispose of all sediment, debris, existing liner material and liquids needed to prepare site for liner demolition.

This work includes, but is not limited to: Excavation, compaction, dewatering, testing, and trucking effort.

2. No separate measurement will be made.

3. Payment will be made at the contract unit price.

B. Contract Price Item No.2 � Install Pond Liner System

1. This price item consists of:

All necessary materials, labor, and equipment to demo the existing liner system. Unit price also includes installation of a new liner and all associated items including anchor trench and pipe boots. The work includes, but is not limited to: Site visit, disposal of items, surveying, liner installation, excavation, backfill, and compaction.

2. No separate measurement will be made.

3. Payment will be made at the contract unit price.

C. Contract Price Item No.3 � Install Overflow drain and PVC Outlet Pipe

1. This price item consists of:

All necessary materials, labor, and equipment to demo 6-inch PVC overflow drain and piping. Unit price also includes installation of a new overflow drain located in the pond and installing new PVC outlet pipe into the wash. The work includes, but is not limited to: excavation, compaction, delivery of product and installation of product.

2. No separate measurement will be made.

3. Payment will be made at the contract unit price.

D. Contract Price Item No.4 � Install Duckbill Valves and PVC Inlet Pipe

LAKE � PMIS #248827 01 27 00 - 2

DEFINITION OF CONTRACT PRICE ITEMS

1. This price item consists of:

All necessary materials, labor, and equipment to demo two existing 6-inch PVC inlet pipes coming into lagoon from water plant, including two flapper valves. Unit price also includes installation of two new inlet PVC pipe at least 10 feet long each and two new duckbill water valves. The work includes, but is not limited to: excavation, compaction, delivery of product and installation of product.

2. No separate measurement will be made.

3. Payment will be made at the contract unit price.

1.3 LIST OF SCHEDULE OF VALUES

All listed quantities shown are estimated values and shall be validated by contractor.

Item

No.

Descriptions Govt

Estimated

Quantities

Govt

Unit

Contractor

Quantities

Contractor

Unit

1 Dewatering and Disposal of Sediment, Plant

Debris, and Liner Material

50 TON

2 Install Pond Liner System 2024 SF

3 Install Overflow drain and PVC Outlet Pipe 35 LF

4 Install Duckbill Valves and Two PVC Inlet

Pipes

20 LF

END OF SECTION 01 27 00

LAKE � PMIS #248827 01 31 00 - 1

PROJECT MANAGEMENT & COORDINATION

SECTION 01 31 00

PROJECT MANAGEMENT & COORDINATION

PART 1 � GENERAL

1.1 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Site health and Safety Plan.

7. Waste Plan.

8. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

9. Satisfactory evidence of liability insurance coverage and workman�s compensation for the Contactor and all subcontractors.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction

Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to

Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.2 PROJECT MEETINGS

A. Preconstruction Conference: Once the contract is awarded, an initial orientation meeting will be scheduled for a time and date that is agreeable to the Government and Contractor and will be conducted in the Lake Mead Maintenance Building. Lake Mead personnel will be present to go over park specific requirements of the project with the Contractor and the Contractor�s supervisory and administrative team. Conference meeting may also be a teleconference or

TEAMS presentation if lead by the NPS. ZOOM meeting will have to be facilitated by the contractor. Discussion of the method of the conference will be made between the CO and the contractor. The Notice to Proceed date will also be established at the Preconstruction

Conference.

1. Agenda: Items to be discussed will include but not be limited to:

1. Park Rules and Regulations.

LAKE � PMIS #248827 01 31 00 - 2

2. General correspondence procedures.

3. Labor standards provisions.

4. Payroll reports.

5. Payments to the Contractor.

6. Acceptance/rejection of work.

7. Progress Meetings.

8. Subcontractors.

9. Documents required under contract.

10. Local emergency phone number.

11. Specifications and drawings.

2. Once the Notice to Proceed date has been established, the Contractor shall submit the proposed work schedule to the government for approval.

1.3 REQUESTS FOR INFORMATION (RFIs)

A. General: On discovery of the need for additional information or interpretation of the Contract

Documents, the Contractor shall prepare and submit an RFI utilizing the form designated by the Contracting officer.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by

Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

7. Contractor�s signature.

8. Requested date for response.

9. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, and details of affected materials, assemblies, and attachments on attached sketches.

LAKE � PMIS #248827 01 31 00 - 3

C. Contracting Officer�s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in the need for a change to the Contract

Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

END OF SECTION 01 31 00

LAKE � PMIS #248827 01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16

CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The

Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 SUBMITTALS

A. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

B. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit a baseline schedule, large enough to show entire schedule for entire construction period.

C. Construction Schedule Updates: Prior to the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.

1.3 COORDINATION

A. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, payment requests, and other required schedules and reports.

B. Coordinate the construction operations identified in the various Sections of this Specification to ensure the efficient installation of all materials and equipment.

1. Schedule construction operations in the proper sequence required to obtain the best results where installation of one part of the Work depends on installation of other components before or after its own installation.

2. Coordinate installation of difference components with subcontractors and Government personnel to ensure maximum accessibility for required maintenance, service, and repair.

LAKE � PMIS #248827 01 32 16 - 2

CONSTRUCTION SCHEDULE

3. Make adequate provisions to accommodate items scheduled for later installation.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments. Each progress payment request shall include the overall percentage completion to that date.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting

Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using computerized scheduling software.

1. Construction Baseline Schedule shall show submittal review, construction start date, work activities / staff resources, activity durations, major milestones, inspection dates, closeout activities, and project end date.

2. Establish procedures for updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

3. Contracting Officer may request an updated Construction Schedule at any time to confirm progress of the work.

END OF SECTION 01 32 16

LAKE � PMIS #248827 01 33 00 - 1

SUBMITTAL PROCEDURES

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 � GENERAL

1.1 GENERAL SUBMITTAL PROCEDURES

A. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. CM-16 Transmittal Form: All submittals shall be transmitted using National Park Service form CM-16 form, attached to the end of this specification section. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form.

Complete the general information at the top of the form.

a. Provide all required information based on the submittal type

b. Attach all related documents.

c. Sign the CM-16 form in the contractor section at the bottom of the form.

2. Physical samples: Complete the CM-16 form as outlined above, and deliver the physical sample to the CO (or designee) on site for processing. All comments and actions will be documented on the CM-16 form.

END OF SECTION 01 33 00

LAKE � PMIS 248827 01 35 23 - 1

SAFETY REQUIREMENTS

SECTION 01 35 23

SAFETY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. General: This section includes establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

1.2 SUBMITTALS

A. Accident Prevention Plan: After contract award and before the Pre-Construction conference, submit for review an Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within ten (10) days. No progress payments will be made until the Plan is accepted.

1.3 QUALITY ASSURANCE

A. Comply with contract clauses entitled "Accident Prevention" and "Permits and Responsibilities". In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees:

1. All employees must be physically qualified and able to perform their assigned duties in a safe manner.

2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

3. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

LAKE � PMIS 248827 01 35 23 - 2

1.4 ACCIDENT REPORTING

A. Reportable Accidents: A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of one hundred dollars ($100). Notify Contracting Officer immediately in the event of a reportable accident. Within seven (7) days of a reportable accident, fill out and forward to Contracting Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.

PART 2 - PRODUCTS

2.1 ACCIDENT PREVENTION PLAN

A. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name of responsible supervisor to carry out the program.

2. Weekly and monthly safety meetings.

3. First aid procedures.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase.

5. Training, both initial and continuing.

6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

2.2 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.

2.3 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of applicable ANSI standards.

PART 3 - EXECUTION

3.1 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

LAKE � PMIS 248827 01 35 23 - 3

3.2 FIRE AND LIFE SAFETY

A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).

B. Contractor will obtain a hot permit from NPS for operating a hot plant and torch.

C. Store hazardous materials in accordance with manufacturer�s and OSHA recommendations.

Maintain readily available, on site, MSDS for each chemical.

1. Immediately report all spills of hazardous materials to the park.

2. Maintain a spill emergency response kit.

3.3 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.4 SAFETY MEETINGS

A. As a minimum, conduct weekly fifteen (15) minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one (1) day after the meeting.

B. Conduct monthly safety meetings for all levels of supervision. Meetings shall be attended by all contractors and subcontractors performing work on the site. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the Accident Prevention Plan. The Contracting Officers Representative will attend the meeting and enter the results of the meetings into the daily log.

3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A. A hard hat area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment at all times. As a minimum, provide six (6) six hard hats for use by visitors.

LAKE � PMIS 248827 01 35 23 - 4

3.6 TRAINING

A. First Aid: Provide adequate training to an adequate number of personnel to ensure prompt and efficient first aid.

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

END OF SECTION 01 35 23

LAKE � PMIS 248827 01 40 00-1

QUALITY REQUIREMENTS

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the

Contract Document requirements.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.

2. Requirements for Contractor to provide quality-assurance and -control services required by

Government or authorities having jurisdiction are not limited by provisions of this Section.

1.2 DEFINITIONS

A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Contracting Officer.

C. Mockups: Full-size, physical assemblies that are constructed on-site. Mockups are used to verify selections made under sample submittals, to demonstrate aesthetic effects and, where indicated, qualities of materials and execution, and to review construction, coordination, testing, or operation;

they are not Samples. Approved mockups establish the standard by which the Work will be judged.

D. Laboratory Mockups: Full-size, physical assemblies that are constructed at testing facility to verify performance characteristics.

E. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated…

This is the start of the file's text. The full file is on GovTribe.