Project_Specifications_12-01-24.pdf
PDF 2 MB Posted
- Solicitation number
- PD 24-25.108
- Issued by
- Escambia County, Florida
About this file
This document is a comprehensive project specification for the Carver Park Community Center, a project for Escambia County located in Pensacola, Florida. The project involves constructing a new 3,250 square foot modular community center with associated site work, including underground utilities, pavement, drainage, and landscaping improvements. The specifications detail a single-story facility comprised of four modular units (three 12' x 65' units and one 14' x 65' unit), designed to comply with the 2023 Florida Building Code, Energy Conservation Code, and other relevant standards. The project will involve complete site development, building construction, and installation of mechanical, electrical, and plumbing systems.
The project specifications provide extensive technical details across multiple divisions, including architectural, structural, mechanical, electrical, and site work requirements. Funding and procurement details are not explicitly stated in the document. The specifications outline precise requirements for materials, installation methods, quality control, and performance standards, with a focus on durability, energy efficiency, and compliance with local building codes. The project appears to be a public infrastructure investment aimed at providing community services, with detailed specifications ensuring high-quality construction and long-term functionality of the community center facility.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Carver Park Community Center September 2024 Escambia County, Pensacola, FL
CARVER PARK 1 OF 2 TABLE OF CONTENTS
Project Manual
Project: Carver Park Date: September 2024
TABLE OF CONTENTS
I. Technical Specifications
Division 1 - General Requirements 010100 Summary of Work 010270 Applications for Payment 010400 Project Coordination 010450 Cutting and Patching 012100 Allowances 013000 Submittals 014000 Quality Control Services 015000 Temporary Facilities 016310 Product Substitutions 016400 Owner Furnished Products 017000 Project Closeout 017400 Warranties and Bonds
Division 2 – Sitework 020700 Selective Demolition 021100 Site Clearing 022000 Earthwork 022210 Trench Excavation, Backfill and Compaction 022800 Termite Control 025100 Water Distribution 025300 Sanitary Sewers 027400 Asphalt Paving 027500 Concrete Paving 029200 Sodding
Division 3 – Concrete 033100 Cast-in-Place Concrete
Division 7 – Thermal and Moisture Protection 075416 Ketone Ethylene Ester (KEE) Roofing 079200 Joint Sealants
Division 9 – Finishes 092900 Gypsum board 095123 Acoustical tile ceilings 096513 Resilient base and accessories 096519 Resilient flooring 098000 Acoustic batt insulation 099113 Exterior painting 099123 Interior painting 099150 Color schedule 099300 Staining and transparent finishing
CARVER PARK 2 OF 2 TABLE OF CONTENTS
Division 13 – Special Construction 130010 Prefabricated Engineered Buildings and Structures 133420 Prefabricated aluminum covered walkway canopy 133430 Prefabricated modular aluminum ramp and step system 133440 Prefabricated landing & step system
Division 23 – Heating Ventilation and Air Conditioning 230000 HVAC General 230010 Codes and Standards 230020 HVAC Related Work 230513 Motors 230517 Sleeves and Sleeve Seals 230519 Meters and Gauges 230523 Valves 230526 Access Doors 230529 Hangers and Supports 230539 Testing, Cleaning, and Sterilization for HVAC Piping 230548 Vibration Isolation 230550 Excavation and Backfill 230553 HVAC Identification 230590 Startup Requirements for HVAC Systems 230593 Testing, Adjusting, and Balancing 230713 Duct Insulation 230716 HVAC Equipment Insulation 230719 HVAC Piping Insulation 230900 Instrumentation and Controls 230963 Variable Frequency Drives 232113 Hydronic Piping 232116 Hydronic Piping Specialties 232123 Hydronic Pumps 233113 Metal Ductwork 233300 Ductwork Accessories 233400 Fans 233600 Air Terminal Units 233713 Diffusers, Registers, And Grilles 233719 Wall Louvers 236423 Air-Cooled Scroll Water Chillers 237313 Air Handling Units 238126 Split-System Air Conditioning Units 238128 Ductless Split-System Air Conditioning Units 238219 Fan Coil Unit
Division 26 – General electrical
260000 General Electrical 260010 Codes and Standards 260020 Work Required for Equipment Furnished By Other Divisions 260526 Grounding and Bonding
Carver Park Community Center Summary of Work 010100 - 1
SECTION 010100 – SUMMARY OF WORK
PART 1 - GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. The Project: Placement of new community center along with associated site appurtenances for the Carver Park Community in Pensacola, Florida.
Complete Contract Documents, dated were prepared for the Project by:
Architect: Scott Dean, Dean Design Build, Inc Civil Engineer: Jason Lashley, Waggoner
B. Project Summary:
The work includes a new 3,250 square foot modular community center and associated sitework. Sitework includes underground utilities, pavement, drainage and landscaping improvements.
C. An anticipated timeframe is the following:
Bids to be submitted by: To be determined by Purchasing Begin construction by: To be determined by the Contract Construction to be substantially complete within _____ days, as stated in the Contract.
1.2 CONTRACTOR USE OF PREMISES
A. General: The Work of the Contract is subject to all applicable governing regulations, including, but not limited to, the State of Florida and Escambia County, Florida.
B. During the construction period the Contractor shall have full use of the premises for construction operations, including use of the site. The Contractor's use of the premises is limited by the Owner's right to perform work or to retain other subcontractors on portions of the Project.
END OF SECTION 010100
Carver Park Community Center Applications for Payment 010270 - 1
SECTION 010270 – APPLICATIONS FOR PAYMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary
1.2
Conditions and other Division-1 Specification Sections, apply to this Section.
SUMMARY
A. This Section specifies administrative and procedural requirements governing the Contractor's Applications for Payment.
1. Coordinate the Schedule of Values and Applications for Payment with the Contractor's Construction Schedule, List of Subcontracts, and Submittal Schedule.
B. The Contractor's Construction Schedule and Submittal Schedule are included in Section "Submittals".
1.3 SCHEDULE OF VALUES
A. Coordinate preparation of the Schedule of Values with preparation of the Contractor's Construction Schedule.
B. Correlate line items in the Schedule of Values with other required administrative schedules and forms, including:
1. Contractor's construction schedule.
2. Application for Payment form.
3. List of subcontractors.
4. Schedule of alternates.
5. List of products.
6. List of principal suppliers and fabricators.
7. Schedule of submittals.
C. Submit the Schedule of Values to the Architect at the earliest feasible date, but in no case later than 7 days before the date scheduled for submittal of the initial Application for Payment.
D. Format and Content: Use the Project Manual Table of Contents as a guide to establish the format for the Schedule of Values.
E. Identification: Include the following Project identification on the Schedule of Values:
1. Project name and location.
Carver Park Community Center Applications for Payment 010270 - 2
2. Name of the Architect.
3. Project number.
4. Contractor's name and address.
5. Date of submittal.
F. Arrange the Schedule of Values in a tabular form with separate columns to indicate the following for each item listed:
1. Generic name.
2. Related Specification Section.
3. Name of subcontractor.
4. Name of manufacturer or fabricator.
5. Name of supplier.
6. Change Orders (numbers) that have affected value.
7. Dollar value.
8. Percentage of Contract Sum to the nearest one-hundredth percent, adjusted to total 100 percent.
G. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports. Break principal subcontract amounts down into several line items.
H. Round amounts off to the nearest whole dollar; the total shall equal the Contract
Sum.
I. Schedule Updating: Update and resubmit the Schedule of Values when Change Orders or Construction Change Directives result in a change in the Contract Sum.
1.4 APPLICATION FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as certified by the Architect and paid for by the Owner.
The initial Application for Payment, the Application for Payment at time of Substantial Completion, and the final Application for Payment involve additional requirements.
B. Payment Application Times: Each progress payment date is as indicated in the
Agreement. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment Application Forms: Use AIA Document G 702 and Continuation Sheets G
703 as the form for Application for Payment.
D. Application Preparation: Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the Owner.
Incomplete applications will be returned without action.
Carver Park Community Center Applications for Payment 010270 - 3
1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions have been made.
2. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application.
E. Waivers of Mechanics Lien: With each Application for Payment submit waivers of mechanics liens from subcontracts or sub-subcontractors and suppliers for the construction period covered by the previous application.
1. Submit partial waivers on each item for the amount requested, prior to deduction for retainage, on each item.
2. When an application shows completion of an item, submit final or full waivers.
3. The Owner reserves the right to designate which entities involved in the Work must submit waivers.
F. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of the first Application for Payment include the following:
1. List of subcontractors.
2. List of principal suppliers and fabricators.
3. Schedule of Values.
4. Contractor's Construction Schedule (preliminary if not final).
5. Submittal Schedule
6. Certificates of insurance and insurance policies.
G. Application for Payment at Substantial Completion: Following issuance of the
Certificate of Substantial Completion, submit an Application for Payment; this application shall reflect any Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
H. Administrative actions and submittals that shall proceed or coincide with this application include:
1. Occupancy permits and similar approvals.
a. Warranties (guarantees) and maintenance agreements.
b. Test/adjust/balance records.
c. Maintenance instructions.
d. Meter readings.
e. Start-up performance reports.
f. Change-over information related to owner's occupancy, use operation and maintenance.
g. Final cleaning.
h. Application for reduction of retainage, and consent of surety.
i. Advice on shifting insurance coverages.
Carver Park Community Center Applications for Payment 010270 - 4
j. Final progress photographs.
k. List of incomplete work, recognized as exceptions to Architect's Certificate of
Substantial Completion.
2. Final Payment Application: Administrative actions and submittals which must precede or coincide with submittal of the final payment Application for Payment include the following:
a. Completion of Project closeout requirements
b. Completion of items specified for completion.
c. Assurance that Work not complete and accepted will be completed without undue delay. Transmittal of required Project construction records to Owner.
d. Removal of temporary facilities and services.
e. Removal of surplus materials, rubbish and similar elements.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 010270
Carver Park Community Center Project Coordination 010400 - 1
SECTION 010400 – PROJECT COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section
1.2 SUMMARY
A. This Section specifies administrative and supervisory requirements necessary for Project coordination including, but not necessarily limited to:
1. Coordination.
2. Administrative and supervisory personnel.
3. Protection of Work and Property
4. General installation provisions.
5. Cleaning and protection.
B. Progress meetings: Hold regular weekly coordination meetings at a time convenient to all parties involved. Resolve coordination problems, distribute minutes to those in attendance and those affected by decisions resulting from the meetings.
1.3 COORDINATION
A. Coordination: Coordinate construction activities included under various Sections of these Specifications to assure efficient and orderly installation of each part of the Work. Coordinate construction operations included under different Sections of the Specifications that are dependent upon each other for proper installation, connection, and operation.
1. Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.
2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where necessary, prepare memoranda for distribution to each party involved outlining special procedures required for coordination. Include such items as required notices, reports, and attendance at meetings.
Carver Park Community Center Project Coordination 010400 - 2
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project Close-out activities.
1.4 PROTECTION OF WORK AND PROPERTY
A. The services of a watchman is not a Contract requirement; however, it is the responsibility of the Contractor to protect all new and existing construction work and materials from damage or theft for the duration of the Contract. The Contractor shall provide watchman services as he deems necessary for such protection.
B. Openings in exterior walls and roof shall be enclosed to prevent unauthorized entry.
Enclosed access openings shall be provided with operating hardware and shall be locked during non-working hours.
C. The Contractor shall protect all existing construction from damage, including the existing building, adjoining building, streets, sidewalks, curbs, fire hydrants, utility poles, existing site improvements, and other property and equipment on or adjacent to the project site. The Contractor shall repair any damage to such items to the satisfaction of the Architect, without cost to the Owner.
D. The Contractor shall provide all temporary protection required to protect all persons from injury within the area of the operations of the Contract for the duration of the Contract.
E. The Contractor shall provide all temporary construction and safeguards including planking, runways, bridges, fences, guard rails, barricades, lights and warning signs, necessary for the protection of the site improvements, existing building, adjacent property, the workmen, occupants of the existing building, and the public, and as required by local authorities.
F. The Contractor shall provide protection against rain, wind, snow, frost, and heat, to protect the interior of the existing building, and all new work and materials, from damage for the duration of the Contract, and to allow the work to proceed without interruption. The Contractor shall repair any damage to such items to the satisfaction of the Architect, without cost to the Owner.
G. The Contractor shall construct and maintain all necessary temporary drainage facilities and perform all pumping necessary to keep excavations, floors, pits and trenches free of water from any source for the duration of the Contract. Water removal shall be accomplished by such methods which will not damage adjacent property, any item of permanent site improvements, or the existing building.
Carver Park Community Center Project Coordination 010400 - 3
H. Maintain the sidewalk fronting the premises free of construction debris, ice, and snow, at all times.
I. Conduct all building operations in accordance with "Good Practice Requirements for Building Construction Operations" of the National Fire Protection Association.
1.5 SUBMITTALS
A. Coordination Drawings: Prepare and submit coordination Drawings where close and careful coordination is required for installation of products and materials fabricated off-site by separate entities, and where limited space availability necessitates maximum utilization of space for efficient installation of different components.
B. Show the interrelationship of components shown on separate Shop Drawings.
C. Indicate required installation sequences.
D. Comply with requirements contained in Section "Submittals."
E. Refer to Division 23-“Heating Ventilating and Air Conditioning” for specific coordination Drawing requirements for mechanical and electrical installations not covered in the Division-13 requirements.
F. Staff Names: Within 15 days of Notice to Proceed, submit a list of the Contractor's principal staff assignments, including the Superintendent and other personnel in attendance at the site; identify individuals, their duties and responsibilities; list their addresses and telephone numbers.
G. Post copies of the list in the Project meeting room, the temporary field office, and each temporary telephone.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 GENERAL INSTSLLATION PROVISIONS
A. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which Work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
B. Manufacturer's Instructions: Comply with manufacturer's installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.
C. Inspect materials or equipment immediately upon delivery and again prior to installation. Reject damaged and defective items.
scott Comment on Text Installation
Carver Park Community Center Project Coordination 010400 - 4
D. Provide attachment and connection devices and methods necessary for securing Work.
Secure Work true to line and level. Allow for expansion and building movement.
E. Visual Effects: Provide uniform joint widths in exposed Work. Arrange joints in exposed Work to obtain the best visual effect. Refer questionable choices to the Architect for final decision.
F. Recheck measurements and dimensions, before starting each installation.
G. Install each component during weather conditions and Project status that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.
H. Coordinate temporary enclosures with required inspections and tests, to minimize the necessity of uncovering completed construction for that purpose.
I. Mounting Heights: Where mounting heights are not indicated, install individual components at standard mounting heights recognized within the industry for the particular application indicated. Refer questionable mounting height decisions to the Architect for final decision.
3.2 CLEANING AND PROTECTION
A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.
B. Clean and maintain completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.
C. Limiting Exposures: Supervise construction activities to ensure that no part of the construction completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.
END OF SECTION 010400
Carver Park Community Center Cutting and Patching 010450 - 1
SECTION 010450 – CUTTING AND PATCHING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for cutting and patching.
B. Refer to other Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work.
1. Requirements of this Section apply to mechanical and electrical installations. Refer to Division-13 and Division-23 for other requirements and limitations applicable to cutting and patching mechanical and electrical installations.
1.3 SUBMITTALS
A. Cutting and Patching Proposal: Where approval of procedures for cutting and patching is required before proceeding submit a proposal describing procedures well in advance of the time cutting and patching will be performed and request approval to proceed. Include the following information, as applicable, in the proposal:
1. Describe the extent of cutting and patching required and how it is to be performed;
indicate why it cannot be avoided.
2. Describe anticipated results in terms of changes to existing construction; include changes to structural elements and operating components as well as changes in the building's appearance and other significant visual elements.
3. List products to be used and firms or entities that will perform Work.
4. Indicate dates when cutting and patching is to be performed.
5. List utilities that will be disturbed or affected, including those that will be relocated and those that will be temporarily out-of-service. Indicate how long service will be disrupted.
6. Where cutting and patching involves addition of reinforcement to structural elements, submit details and engineering calculations to show how reinforcement is integrated with the original structure.
Carver Park Community Center Cutting and Patching 010450 - 2
7. Approval by the Architect to proceed with cutting and patching does not waive the Architect's right to later require complete removal and replacement of a part of the Work found to be unsatisfactory.
1.4 QUALITY ASSURANCE
A. Requirements for Structural Work: Do not cut and patch structural elements in a manner that would reduce their load-carrying capacity or load-deflection ratio. 1.
A. Obtain approval of the cutting and patching proposal before cutting and patching the following structural elements:
a. Foundation construction.
b. Bearing and retaining walls.
c. Structural concrete.
d. Structural steel.
e. Lintels.
f. Timber and primary wood framing.
g. Structural decking.
h. Stair systems.
i. Miscellaneous structural metals.
j. Exterior curtain wall construction.
k. Equipment supports.
l. Piping, ductwork, vessels and equipment.
B. Operational and Safety Limitations: Do not cut and patch operating elements or safety related components in a manner that would result in reducing their capacity to perform as intended, or result in increased maintenance, or decreased operational life or safety.
1. Obtain approval of the cutting and patching proposal before cutting and patching the following operating elements or safety related systems:
a. Shoring, bracing, and sheeting.
b. Primary operational systems and equipment.
c. Air or smoke barriers.
d. Water, moisture, or vapor barriers.
e. Membranes and flashings.
f. Fire protection systems.
g. Noise and vibration control elements and systems.
h. Control systems.
i. Communication systems.
j. Conveying systems.
k. Electrical wiring systems.
C. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied spaces, in a manner that would, in the Architect's opinion, reduce the building's aesthetic qualities, or result in visual evidence of cutting and patching.
Remove and replace Work cut and patched in a visually unsatisfactory manner.
Carver Park Community Center Cutting and Patching 010450 - 3
1. If possible, retain the original installer or fabricator to cut and patch the following categories of exposed Work, or if it is not possible to engage the original installer or fabricator, engage another recognized experienced and specialized firm:
a. Processed concrete finishes.
b. Ornamental metal.
c. Matched-veneer woodwork.
d. Window wall system.
e. Stucco and ornamental plaster.
f. Finished wood flooring.
g. HVAC enclosures, cabinets or covers.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Use materials that are identical to existing materials. If identical materials are not available or cannot be used where exposed surfaces are involved, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect. Use materials whose installed performance will equal or surpass that of existing materials.
PART 3 - EXECUTION
3.1 INSPECTION
A. Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed.
Take corrective action before proceeding, if unsafe or unsatisfactory conditions are encountered.
B. Before proceeding, meet at the site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.
3.2 PREPARATION
A. Temporary Support: Provide temporary support of Work to be cut.
B. Protection: Protect existing construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations.
C. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
Carver Park Community Center Cutting and Patching 010450 - 4
D. Take all precautions necessary to avoid cutting existing pipe, conduit or ductwork serving the building, but scheduled to be removed or relocated until provisions have been made to bypass them.
3.3 PERFORMANCE
A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay.
1. Cut existing construction to provide for installation of other components or performance of other construction activities and the subsequent fitting and patching required to restore surfaces to their original condition.
B. Cutting: Cut existing construction using methods least likely to damage elements to be retained or adjoining construction. Where possible review proposed procedures with the original installer; comply with the original installer's recommendations.
1. In general, where cutting is required use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots neatly to size required with minimum disturbance of adjacent surfaces.
Temporarily cover openings when not in use.
2. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.
3. Cut through concrete and masonry using a cutting machine such as a carborundum saw or diamond core drill.
4. By-pass utility services such as pipe or conduit, before cutting, where services are shown or required to be removed, relocated or abandoned. Cut-off pipe or conduit in walls or partitions to be removed. Cap, valve or plug and seal the remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after by-passing and cutting.
C. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances.
1. Where feasible, inspect and test patched areas to demonstrate integrity of the installation.
2. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
3. Where removal of walls or partitions extends one finished area into another, patch and repair floor and wall surfaces in the new space to provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary to achieve uniform color and appearance.
Carver Park Community Center Cutting and Patching 010450 - 5
4. Where patching occurs in a smooth painted surface, extend final paint coat over entire unbroken containing the patch, after the patched area has received primer and second coat.
5. Patch, repair or rehang existing ceilings as necessary to provide an even plane surface of uniform appearance.
3.4 CLEANING
A. Thoroughly clean areas and spaces where cutting and patching is performed or used as access. Remove completely paint, mortar, oils, putty and items of similar nature.
Thoroughly clean piping, conduit and similar features before painting or other finishing is applied. Restore damaged pipe covering to its original condition.
END OF SECTION 010450
Carver Park Community Center Allowances 012100 - 1
SECTION 012100 – ALLOWANCES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
B. Types of allowances include the following:
1. Lump-sum allowances.
1.2 SELECTION AND PURCHACE
1.3 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.4 LUMP SUM ALLOWANCES
A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Architect under allowance and shall include taxes, freight, and delivery to Project site.
B. Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by Owner or selected by Architect under allowance shall be included as part of the Contract Sum and not part of the allowance.
C. All allowance fund amounts not used by the Contractor shall be returned to the Owner by Change Order.
D. Owner's Contingency means the amount as indicated, that is included in the base proposal for authorizing additional work in connection with the Project. The use of the allowance requires the written approval or directive by the Owner by the Change Directive / Change Order process. All unused amount from the Owner's Contingency will be returned to the Owner by Change Order.
1.5 ADJUSTMENT OF ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of
Carver Park Community Center Allowances 012100 - 2 work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.
1. Include installation costs in purchase amount only were indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.
3. Submit substantiation of a change in scope of Work, if any, claimed in Change Orders related to unit-cost allowances.
4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.
1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.
2. No change to Contractor's indirect expense is permitted for selection of higher- or low- er priced materials or systems of the same scope and nature as originally indicated.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Re- turn damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES (NOT USED)
Carver Park Community Center Allowances 012100 - 3
END OF SECTION 012100
Carver Park Community Center Submittals 013000 - 1
SECTION 013000 – SUBMITTALS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawing and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specifications, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for submittals required for performance of the Work, including;
1. Contractor’s construction schedule.
2. Submittal schedule.
3. Daily construction reports.
4. Shop Drawings.
5. Product Data.
6. Samples.
B. Administrative Submittals: Refer to other Division-1 Sections and other Contract Documents for requirements for administrative submittals. Such submittals include, but are not limited to:
• Permits.
• Applications for payment.
• Performance and payment bonds.
• Insurance certificates.
• List of Subcontractors.
C. The Schedule of Values submittal is included in Section "Applications for Payment."
D. Inspection and test reports are included in Section "Quality Control Services."
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related elements of the Work so processing will not be delayed by the need to review submittals concurrently for coordination.
Carver Park Community Center Submittals 013000 - 2
3. The Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing: Allow sufficient review time so that installation will not be delayed as a result of the time required to process submittals, including time for resubmittals.
1. Allow three weeks for initial review. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. The Architect will promptly advise the Contractor when a submittal being processed must be delayed for coordination.
2. If an intermediate submittal is necessary, process the same as the initial submittal.
3. Allow two weeks for reprocessing each submittal.
4. No extension of Contract Time will be authorized because of failure to transmit submittals to the Architect sufficiently in advance of the Work to permit processing.
C. Submittal Preparation: Place a permanent label or title block on each submittal for identification. Indicate the name of the entity that prepared each submittal on the label or title block.
1. Include the following information on the label for processing and recording action taken:
• Project name.
• Date.
• Name and address of Architect.
• Name and address of Contractor.
• Name and address of subcontractor.
• Name and address of supplier.
• Name of manufacturer.
• Number and title of appropriate Specification Section.
• Drawing number and detail references, as appropriate.
D. Submittal Transmittal: Package each submittal appropriately for transmittal and handling. Transmit each submittal from Contractor to Architect using a transmittal form.
Submittals received from sources other than the Contractor will be returned without action.
1.4 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Bar-Chart Schedule: Prepare a fully developed, horizontal bar-chart type Contractor's construction schedule. Submit within 30 days of the date established for "Commencement of the Work".
Carver Park Community Center Submittals 013000 - 3
1. Provide a separate time bar for each significant construction activity. Provide a continuous vertical line to identify the first working day of each week. Use the same breakdown of units of the Work as indicated in the "Schedule of Values".
2. Within each time bar indicate estimated completion percentage in 10 percent increments. As Work progresses, place a contrasting mark in each bar to indicate Actual Completion.
3. Prepare the schedule on a sheet, or series of sheets, of stable transparency, or other reproducible media, of sufficient width to show data for the entire construction period.
4. Secure time commitments for performing critical elements of the Work from parties involved. Coordinate each element on the schedule with other construction activities; include minor elements involved in the sequence of the Work. Show each activity in proper sequence. Indicate graphically sequences necessary for completion of related portions of the Work. 5. Coordinate the Contractor's construction schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests and other schedules.
5. Indicate completion in advance of the date established for Substantial Completion.
Indicate Substantial Completion on the schedule to allow time for the Architect's procedures necessary for certification of Substantial Completion.
B. Phasing: Provide notations on the schedule to show how the sequence of the Work is affected by requirements for phased completion to permit Work by separate Contractors and partial occupancy by the Owner prior to Substantial Completion.
C. Work Stages: Indicate important stages of construction for each major portion of the Work, including testing and installation.
D. Area Separations: Provide a separate time bar to identify each major construction area for each major portion of the Work. Indicate where each element in an area must be sequenced or integrated with other activities.
E. Distribution: Following response to the initial submittal, print and distribute copies to the Architect, Owner, subcontractors, and other parties required to comply with scheduled dates. Post copies in the Project meeting room and temporary field office.
F. Schedule Updating: Revise the schedule after each meeting or activity, where revisions have been recognized or made. Issue the updated schedule concurrently with report of each meeting.
1.5 SUBMITTAL SCHEDULE
A. After development and acceptance of the Contractor's construction schedule, prepare a complete schedule of submittals. Submit the schedule within 10 days of the date required for establishment of the Contractor's construction schedule.
1. Prepare the schedule in chronological order; include submittals required during the first 90 days of construction. Provide the following information:
Carver Park Community Center Submittals 013000 - 4
• Scheduled date for the first submittal.
• Related Section number.
• Submittal category.
• Name of subcontractor.
• Description of the part of the Work covered.
• Scheduled date for resubmittal
• Scheduled date the Architect's final release or approval.
B. Distribution: Following response to initial submittal, print and distribute copies to the Architect, Owner, subcontractors, and other parties required to comply with submittal dates indicated. Post copies in the Project meeting room and field office. In addition, contractor shall maintain an “online” copy of approved submittals. This online copy shall be made accessible to the project team.
1. When revisions are made, distribute to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in construction activities.
C. Schedule Updating: Revise the schedule after each meeting or activity, where revisions have been recognized or made. Issue the updated schedule concurrently with report of each meeting.
1.6 DAILY CONSTRUCTION REPORTS
A. Prepare a daily construction report, recording the following information concerning events at the site; and submit duplicate copies to the Architect at weekly intervals:
• List of subcontractors at the site.
• Approximate count of personnel at the site.
• High and low temperatures, general weather conditions.
• Accidents and unusual events.
• Meetings and significant decisions.
• Stoppages, delays, shortages, losses. Meter readings and similar recordings.
• Emergency procedures.
• Orders and requests of governing authorities.
• Change Orders received, implemented.
• Services connected, disconnected.
• Equipment or system tests and start-ups.
• Partial Completions, occupancies.
• Substantial Completions authorized.
1.7 SHOP DRAWINGS
Carver Park Community Center Submittals 013000 - 5
A. Submit newly prepared information, drawn to accurate scale. Highlight, encircle, or otherwise indicate deviations from the Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings.
Standard information prepared without specific reference to the Project is not considered Shop Drawings.
B. Shop Drawings include fabrication and installation drawings, setting diagrams, schedules, patterns, templates and similar drawings. Include the following information:
• Dimensions.
• Identification of products and materials included.
• Compliance with specified standards.
• Notation of coordination requirements.
• Notation of dimensions established by field measurement.
• Sheet Size: Except for templates, patterns and similar full- size Drawings, Submit Shop Drawings on sheets at least 8-1/2" x 11" but no larger than 36" x 48".
• Submittal: Submit two blackline prints for the Architect's review. One print will be returned with any comments or markup-ups by the reviewer.
C. Coordination drawings are a special type of Shop Drawing that show the relationship and integration of different construction elements that require careful coordination during fabrication or installation to fit in the space provided or function as intended.
1. Preparation of coordination Drawings is specified in section "Project Coordination" and may include components previously shown in detail on Shop Drawings or Product Data.
2. Submit coordination Drawings for integration of different construction elements. Show sequences and relationships of separate components to avoid conflicts in use of space.
1.8 PRODUCT DATA
A. Collect Product Data into a single submittal for each element of construction or system. Product Data includes printed information such as manufacturer's installation instructions, catalog cuts, standard color charts, roughing-in diagrams and templates, standard wiring diagrams and performance curves. Where Product Data must be specially prepared because standard printed data is not suitable for use, submit as "Shop Drawings."
B. Mark each copy to show applicable choices and options. Where printed Product Data includes information on several products, some of which are not required, mark copies to indicate the applicable information include the following information:
Carver Park Community Center Submittals 013000 - 6
• Manufacturer’s printed recommendations.
• Compliance with recognized trade association standards.
• Compliance with recognized testing agency standards.
• Application of testing agency labels and seals.
• Notation of dimensions verified by field measurement.
• Notation of coordination requirements.
C. Do not submit Product Data until compliance with the requirements of the Contract Documents have been confirmed.
D. Submittals: Submit 3hard copies of each required submittal; submit 4hardcopies where required for maintenance manuals. The Architect will retain one and will return the other marked with action taken and corrections or modifications required.
In addition to hard copies, the contractor shall maintain an “online” copy of approved submittals. This online copy shall be made accessible to the project team.
E. Distribution: Furnish copies of final submittal to installers, subcontractors, suppliers, manufacturers, fabricators and others required for performance of construction activities. Show distribution on transmittal forms.
i. Do not proceed with installation until an applicable copy of Product Data applicable is in the installer's possession.
ii. Do not permit use of unmarked copies of Product Data in connection with construction.
1.9 SAMPLES
A. Submit full-size, fully fabricated Samples cured and finished as specified and physically identical with the material or product proposed. Samples include partial sections of manufactured or fabricated components, cuts or containers of materials, color range sets, and swatches showing color, texture and pattern.
B. Mount, display, or package Samples in the manner specified to facilitate review of qualities indicated. Prepare Samples to match the Architect's Sample. Include the following:
1. Generic description of the Sample.
2. Sample source.
3. Product name or name of manufacturer.
4. Compliance with recognized standards.
5. Availability and delivery time.
C. Where variation in color, pattern, texture or other characteristics are Submit Samples for review of kind, color, pattern, and texture, for a final check of these characteristics with other elements, and for a comparison of these characteristics between the final submittal and the actual component as delivered and installed.
Carver Park Community Center Submittals 013000 - 7
1. Inherent in the material or product represented, submit multiple units (not less than 3), that show approximate limits of the variations.
2. Refer to other Sections for Samples to be returned to the Contractor for incorporation in the Work. Such Samples must be undamaged at time of use.
On the transmittal, indicate special requests regarding disposition of Sample submittals.
D. Maintain sets of Samples, as returned, at the Project site, for quality comparisons throughout the course of construction.
1. Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.
2. Sample sets may be used to obtain final acceptance of the construction associated with each set.
1.10 ARCHITECT'S ACTION
A. Except for submittals for record, information or similar purposes, where action and return is required or requested, the Architect will review each submittal, mark to indicate action taken, and return promptly. Compliance with specified characteristics is the Contractor's responsibility.
B. Action Stamp: The Architect will stamp each submittal with a uniform, self-explanatory action stamp. The stamp will be appropriately marked, as follows, to indicate the action taken:
Approved: Where submittals are marked "Approved", that part of the Work covered by the submittal may proceed provided it complies with requirements of the Contract Documents; final acceptance will depend upon that compliance.
Approved as Corrected: When submittal are marked "Approved as Corrected", that part of the Work covered by the submittal may proceed provided it complies with notations or corrections on the submittal and requirements of the Contract Documents; final acceptance will depend on that compliance.
Revise and Resubmit: When submittal is marked "Revise and Resubmit", do not proceed with that part of the Work covered by the submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal in accordance with the notations; resubmit without delay. Repeat if necessary to obtain a different action mark.
Rejected: When submittal is marked "Rejected", do not proceed with that part of the Work covered by the submittal, including fabrication, delivery, or other activity.
Prepare a new submittal in accordance with the Contract Documents and submit without delay.
Carver Park Community Center Submittals 013000 - 8
Other Action: Where a submittal is primarily for information or record purposes, special processing or other activity, the submittal will be returned, marked "Action Not Required".
PART 2 - PRODUCTS (Not Applicable).
PART 3 - EXECUTION (Not Applicable).
END OF SECTION 013000
Carver Park Community Center Quality Control Services 014000 - 1
SECTION 014000 – QUALITY CONTROL SERVICES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawing and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specifications, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for quality control services.
B. Quality control services include inspections and tests and related actions including reports, performed by independent agencies, governing authorities, and the Contractor. They do not include Contract enforcement activities performed by the Architect.
C. Inspection and testing services are required to verify compliance with requirements specified or indicated. These services do not relieve the Contractor of responsibility for compliance with Contract Document requirements.
D. Requirements of this Section relate to customized fabrication and installation procedures, not production of standard products.
1. Specific quality control requirements for individual construction activities are specified in the Section that specifies those activities. Those requirements, including inspections and tests cover production of standard products as well as customized fabrication and installation procedures.
2. Inspections, tests and related actions specified are not intended to limit the Contractor's quality control procedures that facilitate compliance with Contract Documents requirements.
3. Requirements for the Contractor to provide quality control services required by the Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section.
1.3 RESPONSIBILITIES
A. Contractor's Responsibilities: The Contractor shall provide inspections, tests and similar quality control services, specified in individual Specification Sections and required by governing authorities, except where they are specifically indicated to be the Owner's responsibility, or are provided by another identified entity;…