PROJECT SCHEDULE (1).pdf

PDF 372 KB Posted

Attached to
High School Weight Room Addition
Solicitation number
RFP GRPS 270000000030 1
Issued by
Kent County, Michigan

About this file

This is a Project Schedule (Gantt chart) for a High School Weight Room Addition project in Michigan. The project is scheduled to commence in Q2 2027, with the last day of school on June 4, 2027, and substantial completion targeted for March 6, 2028. The construction sequence includes selective demolition (June 5-26, 2027), sitework and foundation activities (June 22-July 31, 2027), concrete work (August 2-11, 2027), masonry (August 17-September 17, 2027), metals installation (September 20-30, 2027), roofing systems (October 4-14, 2027), aluminum storefronts and glazing (November 1-27, 2027), fire protection (November 22-December 10, 2027), painting (December 13, 2027-January 6, 2028), flooring (January 31-February 25, 2028), mechanical systems (June 21, 2027-February 29, 2028), and electrical work (February 14, 2028).

The schedule reflects a comprehensive renovation project requiring coordination across multiple construction trades. The project timeline demonstrates careful sequencing to accommodate the school calendar, with work beginning after the academic year ends and substantial completion occurring before the following school year. All major construction phases are scheduled during the period between June 2027 and March 2028, indicating a compressed construction timeline of approximately nine months for the complete renovation and addition.

View the file

Other files

File Type Posted
H.S. Weight Room Addition - Updated Front Ends.pdf PDF
BID INVITE TEMPLATE (1).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gantt

Q2 2027 tones

Last Day of School

28-277 days

Jun 4, '27 Last Day of School

Substantial Completion Mar 6, '28

Q3 2027 Q4 2027 Q12028

Selective Dem Jun 5, 27-Jun 26, '27 Selective Demolition

ECTRICAL Feb 14, '28

MECHANICAL Jun 21, '27- Feb 29, '28

SITEWORK Jun 22, '27-Jul 10, '27

Footings/Foundation Dig Jul 27, 27- Jul 31, '27

SITEWORK

Footings/ Foundation Dig

CONCRETE Aug 2, '27-Aug 11, '27 CONCRETE

MASONRY Aug 17, '27- Sep 17, '27

METALS Sep 20, '27- Sep 30, '27

ROOFING SYSTEMS Oct 4, '27-Oct 14, '27

ALUMINUM STOREFRONTS Nov 1, '27- Nov 11, '27

Nov 8, '27- Nov 27, '27

FIRE PROTECTION Nov 22, '27- Dec 10, '27

PAINTING Dec 13, 27- Jan 6, 28

FLOORING Jan 31, '28-Feb 25, '28

Substantial Co

ELECTRICAL

MECHANICAL

MASONRY

METALS

ROOFING SYSTEMS

|ALUMINUM STOREFRONTS/GLAZING

LPDA

FIRE PROTECTION

PAINTING

FLOORING