Project Manual - FO501995 Torrey Life Sciences Greenhouse Improvements - Phase 1.pdf
PDF 2 MB Posted
- Solicitation number
- FO501995a
- Issued by
- Connecticut
About this file
Summary
This Project Manual contains the comprehensive contract documents for the Torrey Life Sciences Greenhouse Improvements - Phase 1 (Project #FO501995) at the University of Connecticut's Storrs campus, prepared by the University of Connecticut Office of University Planning, Design and Construction. The project involves the removal, cleaning, and reinstallation of existing single-glazing systems in three greenhouse structures (GH-1, GH-2, and GH-3) constructed in the late 1950s, including abatement of asbestos-containing materials (ACM) and materials assumed to contain polychlorinated biphenyls (PCBs) at concentrations of 50 parts per million or greater. The scope encompasses removal of approximately 9,900 linear feet of glazing compounds from 3,450 glass panes mounted on metal and glass substrates, cleaning of glass and framing systems, and reinstallation of glazing using approved silicone sealants such as DOWSIL 795 or equivalent. The Owner will furnish replacement glass and aluminum compression muntins; the Contractor must coordinate all installation work. The Contractor is required to obtain a Certificate of Substantial Completion within 90 calendar days from the Notice to Proceed, with work restrictions limiting on-site hours to 7:00 a.m. to 4:30 p.m., Monday through Friday, and prohibiting work during University exam periods and other specified academic calendar dates.
Only contractors appearing on the State of Connecticut Department of Public Health approved list of asbestos abatement contractors holding valid Connecticut licenses are eligible to submit proposals. Bidders must submit experience records showing completion of at least three similar projects within the past year, along with qualifications of the project supervisor and on-site personnel. The contract requires submission of a Critical Path Method construction schedule, hourly rates for self-performed labor, owned equipment lists, health and safety plans, background screening control plans, and multiple other pre-construction submittals within specified timeframes. All work must comply with EPA (40 CFR 761), OSHA (29 CFR 1926.1101), and Connecticut Department of Public Health standards for hazardous material abatement. The Contractor bears full responsibility for containment, selective demolition, removal, transportation, and off-site disposal of all ACM and PCB-containing waste materials, with disposal facilities and transporters subject to Owner approval. Change orders require detailed Proposed Change Order submissions within seven working days, with strict documentation requirements for labor, materials, and equipment costs. The contract includes provisions for liquidated damages, extended warranty requirements, and mandatory insurance coverage maintenance for three years after final completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
Project # FO501995
Torrey Life Sciences Greenhouse Improvements Phase 1 GH-3 75 North Eagleville Road, Storrs, CT 06269
Construction Documents Volume 1 of 1
State of Connecticut
University Planning, Design and
Construction
Project Administration
Dr. Radenka Maric President
Prepared By:
Project Administration 3 Discovery Drive, Storrs CT
March 24, 2026
UNIVERSITY OF CONNECTICUT 100 % COMPLETE DOCUMENTS
Torrey Life Sciences Greenhouse Improvements Phase 1
FO501995 DATE 03/24/2026
DIVISION 01 GENERAL REQUIREMENTS
TAB SECTION DESCRIPTION
01 01-1000 SUMMARY
05 01-2500 SUBSTITUTION PROCEDURES
06 01-2600 CONTRACT MODIFICATION PROCEDURES
07 01-3100 PROJECT MANAGEMENT AND COORDINATION
08 01-3200 CONSTRUCTION PROGRESS DOCUMENTATION
09 01-3233 PHOTOGRAPHIC DOCUMENTATION
10 01-3300 SUBMITTAL PROCEDURES
11 01-4000 QUALITY REQUIREMENTS
12 01-5000 TEMPORARY FACILITIES AND CONTROLS
13 01-5600 TEMPORARY PROTECTIONOF EXISTING CONSTRUCTION
14 01-5640 TREE PROTECTION AND PRESERVATION
16 01-5719 TEMPORARY ENVIRONMENTAL CONTROLS
17 01-6000 PRODUCT REQUIREMENTS
18 01-7300 EXECUTION
19 01-7700 CLOSEOUT PROCEDURES
20 01-7823 OPERATION AND MAINTENANCE DATA
01-7839 02-8213 02-8400
PROJECT RECORD DOCUMENTS
ASBESTOS ABATEMENT
MANAGEMENT OF BUILDING MATERIALS ASSUMED TO
CONTAIN PCBS ≥ 50 PPM
END OF SECTION 01-0000
TABLE OF CONTENTS
Draft Date
01-0000 - 1 03 / 2026 https://uconn.edu/
University of Connecticut Project Name Torrey Life Science Improvements
SUMMARY 01-1000-1
SUMMARY 08/2025 01-1000 - 1
SECTION 01-1000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Related Documents
2. Summary
3. Project information.
4. Work covered by Contract Documents.
5. Work under separate contracts.
6. Definitions
7. Time of Completion.
8. Documents required before execution of the Contract.
9. Access to site and use of the Site.
10. Coordination with occupants.
11. Work restrictions.
12. Prohibited Items
13. Work Sequence.
14. Miscellaneous provisions.
B. Related Requirements:
1. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
2. Division 01 Section “Temporary Tree and Planting Protection” for general protection and pruning of existing trees and plants that are affected by the execution of the Work.
3. Division 01 Section “Submittal Procedures” for submittal requirements prior to start of work.
1.3 PROJECT INFORMATION
A. Project Identification: FO501995 Torrey Life Sciences Greenhouse Improvements GH-3 Only
1. Project Location: 75 N Eagleville Rd, Storrs, CT 06269
B. Owner: University of Connecticut
1. Owner's Representative: Jason LePino Jason.lepino@uconn.edu 860-486-0554
2. Owner’s Architect: N/A mailto:Jason.lepino@uconn.edu
SUMMARY 01-1000-2
SUMMARY 08/2025 01-1000 - 2
3. Architect's Consultants: The Architect has retained the following design professionals who have prepared designated portions of the Contract Documents:
a.
4. Other Owner Consultants: The Owner has retained the following design professionals who have prepared designated portions of the Contract Documents:
a. Asbestos / Environmental Design Service Consultant: Fuss & Oneil 203-374- 3748 has provided the additional documents labeled Section 02 82 13 – Asbestos Abatement, Section 02 84 00 – Management of Building Materials Assumed to Contain PCBS ≥ 50 PPM and Abatement Plan HM-101 Commissioning Agent:
University of Connecticut
b. Structural Engineering Consultant: Gale Associates Inc. 860-430-5660 has provided a Structural analysis report included in the specifications.
Commissioning Agent: University of Connecticut
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. This project involves hazardous material abatement associated with the removal, cleaning and reinstallation of the existing single glazing associated with the TLS Greenhouses (GH-1, GH-2, GH-3) at the University of Connecticut. The structures were originally constructed in the late 1950s and are classified as Group U Occupancy (Utility and Miscellaneous) per code definitions and are assumed to be of Type V-B construction—non-rated, unprotected wood or metal framing.
2. The scope includes the removal of all single pane glazing and associated compression brackets, followed by cleaning of both the glass and framing systems including compression brackets. Glazing shall be reinstalled using an approved silicone sealant primer—such as DOWSIL™ 1200 OS, GE SS4044P, or Tremco Primer #996—in conjunction with a structural silicone sealant, such as DOWSIL™ 795, GE SilGlaze® II SCS2000, or Tremco Proglaze® SSG, applied at glass-to-framing and glass-to-compression muntin brackets. Perform adhesion tests of installed sealant per ASTM C1521, Standard Practice for Evaluating Adhesion of Installed Weatherproofing Sealant Joints. Additionally, the scope includes the complete removal and off-site disposal of glazing compounds that have been confirmed to contain asbestos, as well as those presumed to contain polychlorinated biphenyls (PCBs) at concentrations ≥50 ppm. These hazardous materials are present in approximately 9,900 linear feet of glazing compounds, associated with 3,450 glass panes mounted on metal/glass substrates across the three greenhouse structures. Contractor shall select the appropriate primer/sealant combination for the actual frame finish, subject to review and approval.
Major building assemblies include:
Roof and wall systems: Comprised of metal framework and glass glazing panels
SUMMARY 01-1000-3
SUMMARY 08/2025 01-1000 - 3
Glazing compounds: Serving as sealants for windowpanes, identified as both ACM and assumed PCB-containing
Substrate materials: Primarily glass and metal frames requiring decontamination and salvage
All work must be performed under strict regulatory compliance with EPA (40 CFR 761), OSHA (29 CFR 1926), and Connecticut Department of Public Health standards. The contractor will be responsible for containment, selective demolition, removal, and appropriate environmental controls throughout the abatement process.
3. Removal of all debris caused by this Contract.
4. Protection of the public, building, grounds from damage during this contract is always the responsibility of the Contractor for this project.
5. Repair or replace landscaping including trees, shrubs or other planting disturbed during the Work of the contract with new to match existing, unless otherwise noted. Regrade and reseed any grass area damaged as a result of the Work. Repair any walkways or paved areas damaged as a result of the Work.
B. Owner-Furnished Materials:
1. Owner will furnish replacement glass and aluminum compression muntin’s as required for the Work. Installation of Owner-furnished materials shall be considered equivalent to the removal, cleaning, and reinstallation of existing components. Contractor shall include all costs for coordination, receiving, handling, storage, protection, and installation of Owner-furnished glass and muntin’s in the Base Bid.
2. Replacement of broken, missing, or non-reusable glass or compression muntin’s with Owner-furnished materials shall not be considered additional work, and no additional compensation will be provided.
1.5 WORK UNDER SEPARATE CONTRACTS
General: Cooperate fully with contractors that may have been issued separate contract(s) to perform certain construction operations at the site prior to construction activity under this contract so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under separate contracts.
1.6 DEFINITIONS UNDER THE CONTRACT DOCUMENTS
A. Architect: The term used to designate the Professional Consultant who provides Architectural, Engineering, Geotechnical, and Interior Design services for the Project. The term includes any associates or sub-consultants employed or contracted by the Architect/Engineer to assist in providing the phased services of the contract documents. Architect or Engineer of Record shall apply to the primary where the construction contract type is not design-build.
B. Architect/Engineer Sub-Consultants: The term used to designate professional consultants who provide design and engineering services as a team under the Architect or Engineer of Record responsibilities. The term is not limited to a single tier of sub-consultants. Architect/Engineer and their sub-consultants cannot be sub-consultants to the Contractor.
SUMMARY 01-1000-4
SUMMARY 08/2025 01-1000 - 4
C. Bridging Documents: Where there is a design-build construction form of contract, the term used for the design documents developed and issued for bid by the Bridging-Architect. The Bridging documents have brought the intent of the design to the design documents through the designated percentage completeness identified on the bridging documents.
D. Commissioning: this term is used in conjunction with the Contractor carrying out the proper installation of provided product/systems and all necessary tests and procedures required by the industry to demonstrate the system and each component is fully functioning as intended within the design documents and Owner’s operational requirements. There does not need to be an independent technical advisor to the Owner for the Contractor to maintain responsibility for proper and affective commissioning of their installations.
E. Commissioning Agent: an independent technical advisor who is contracted directly with the Owner who works closely with the lead contractors to ensure that a building or construction project meets the operation requirements of the Owner. Oversees the design, installation, testing and maintenance of all components materials and systems.
F. Contract Arborist: The term used to designate a Professional Consultant who is licensed in the practice of arboriculture and who is contracted by the Contractor. The Contract Arborist cannot also be the same individual or entity as the Project Arborist contracted by the Architect/Engineer and/or Owner.
G. Contract Documents: The Contract between Owner and Contractor signed by the Owner and the Contractor and any documents expressly incorporated therein for the Project. Such incorporated documents customarily include the Contract and General Conditions, any Supplemental General Conditions, any Special Conditions, the plans and the specifications, and all modifications, including addenda and subsequent Change Orders.
H. Contractor: The person or entity with whom the Owner has directly entered into a contractual agreement to do the Work. Applies to Construction Manager, General Contractor, Prime Contractor or Design-Build Contractor.
Companies that are owned or operated by the same individual or entity, close relations, parent company or subsidiary, who operate under the same address and/or building, has either directly or indirectly any degree of ownership, management or control of another corporation, company or partnership; has directly or indirectly close relations or family members, share the same or adjacent space addresses or share resources to perform work as a joint venture formally or informally; is viewed as a signatory employer and not as separate trade supplier or installers who subcontracts and/or supply to each other. Such entities are viewed as a single pooled resource and therefore not separate unto each other.
I. Day: Means a calendar day, 24-hour period. All response times and schedules shall be based on a calendar day, unless specifically noted otherwise.
J. Daily Construction Report: A written daily log recording the day’s construction site activities conditions and progress.
SUMMARY 01-1000-5
SUMMARY 08/2025 01-1000 - 5
K. Daily Additional Work Tickets: Recording the day’s trade labor work performed for a change in the work issued by a CCD.
L. Drawing: A page or sheet of the Plan which presents a graphic representation, usually drawn to scale, showing the technical information, design, location, and dimensions of various elements of the Work. The graphic representations include, but are not limited to, plan views, elevations, transverse and longitudinal sections, large- and small-scale sections and details, isometrics, diagrams, schedules, tables and/or pictures.
M. Hourly Rate: An hourly rate for self-performed work. Self-performed work shall not be limited to trade labor, technical or professional service. Hourly rate shall be calculated utilizing the Hourly Rate Worksheet template identified within the contract documents.
N. Labor: a term used for trade and professional work effort performed in the project. Labor is not limited to trade or on-site work effort.
O. Like New Condition: The appearance of looking new having no marks, chips, or cracks.
P. Notice to Proceed: A written notice given by the Owner to the Contractor (with a copy to A/E) fixing the date on which the Contract time will commence for the Contractor to begin the prosecution of the Work in accordance with the requirements of the Contract Documents. The Notice to Proceed will customarily identify a Contract Completion Date.
Q. Owner: University of Connecticut Office of University Planning, Design and Construction.
The terms “Owner” and “Awarding Authority” as used in the Project Manual have the same meaning and are interchangeable in Contract Documents. Both terms refer to the same entity.
R. Provide: The term is used when the Contractor is required to provide a product or service and shall mean to obtain a product or service, delivery of the product and/or service, installation and maintenance the product during warrantee period, including any fuel or utility required to run the product or service. And if not temporary services or controls, warrantee/guarantee the product or service to the Owner.
S. Project: The term used instead of the specific or proper assigned title of the entire undertaking which includes, but is not limited to, the “Work” described by the Contract Documents.
T. Project Manager: The Project Manager as used herein shall be the Owner’s designated representative on the Project. The Project Manager shall be the person through whom the Owner generally conveys decisions. The Owner may change the Project Manager from time to time or may appoint an interim Project Manager.
U. Site: Shall mean the location at which the Work is performed or is to be performed. Also referred to as Work Zone, Site Logistics Plan, and Construction Area.
V. Small Tools: Shall mean any work-related equipment, tools or instruments normally supplied with the labor and utilized in the normal course of performing the work. Equipment, tools or instruments not limited to items such as; hand held tools, shovels, picks, rakes, ladders, power tools, computers and computer software or instruments normally supplied with the labor or that are normally expected to be provided (owned or rented) in the performance of the typical work
SUMMARY 01-1000-6
SUMMARY 08/2025 01-1000 - 6
for the category, are not compensable. These costs shall not be approved as part of the Direct Cost of a Change Order as they are included within the Contractor’s overhead mark-up percentage.
W. Specifications: That part of the Contract Documents containing the written administrative requirements and the technical descriptions of materials, equipment, construction systems, standards, and workmanship which describe the proposed Work in sufficient detail and provide sufficient information for the Contractor to perform the Work.
X. Subcontractor: A person or entity having a direct or indirect contract with the Contractor for the performance of the Work. Subcontractor includes any person or entity who provides on-site labor but does not include any person or entity who only furnishes product or material supplies for the Project and does not provide labor of any kind. A person or entity that provides and installs product received from a source such as a manufacturer, wholesaler, distributor or dealer are recognized as Subcontractors and shall follow the same requirements under the contract documents as the Contractor.
A person or entity that has either directly or indirectly any degree of ownership, management or control of another corporation, company or partnership; directly or indirectly with family members, share the same or adjacent space addresses or share resources to perform work as a joint venture formally or informally; is viewed as a signatory employer. Such circumstances shall be viewed as a single entity and not as sub-tiers or separate supplier and installer. Where the contract documents refer to the “Contractor”, the requirements under the contract shall also apply to the Subcontractor and sub-tiers and given all costs associated are inclusive in their bid.
Y. Submittals: All shop, fabrication, setting and installation drawings, diagrams, illustrations, schedules, samples, and other data required by the Contract Documents which are specifically prepared by or for the Contractor to illustrate some portion of the Work and all illustrations, brochures, standard schedules, performance charts, instructions, diagrams and other information prepared by a Supplier and submitted by the Contractor to illustrate material or equipment conformance of some portion of the Work with the requirements of the Contract Documents.
Z. Substantial Completion: Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy and utilize the Work for the use for which it is intended, without impact or interruptions to its use.
AA. Supplier: A manufacturer or manufacturer’s direct authorized wholesaler/distributor, who provides material or equipment that can only be obtained directly through such manufacturer’s authorized wholesaler/distributor (proprietary, prime supplier). Such cost represented by the manufacturer or authorized wholesaler/distributor is the direct cost inclusive of engineering, transportation, storage, delivery, oversight, overhead and profit. Material and equipment supplied by another is considered a sub-tier supplier.
A supplier does not provide on-site labor of any kind. A subcontractor or sub-tier subcontractor cannot also be a material supplier to themselves, with the exception of proprietary product that can only be obtain from the material supplier who is also the manufacturer. See definition of a Subcontractor.
Project # FO501995
SUMMARY 01-1000-7
SUMMARY 08/2025 01-1000 - 7
BB. Surveyor: A licensed professional land surveyor in the State of Connecticut with a minimum of 5 years expert surveyor credentials. Operates and manages land-information computer systems and storing data. Owns survey equipment and robotics. The Surveyor hired by the Contractor cannot be the same person or entity hired by the Bridging-Architect/Engineer and/or Owner.
CC. Traffic Control: A person who is appropriately trained and certified to provide traffic control flagging services. On any State roads running through any University campus, traffic control shall be performed by University Police.
DD. Time for Completion: Is either the number of consecutive calendar days following the issuance of the Notice to Proceed which the Contractor has to substantially complete all Work required by the Contract or when the Notice to Proceed is issued, it identifies Contract Completion Date, which has been set by the Owner based on the Time for Completion.
EE. Work: The services performed under this Contract including, but not limited to, furnishing labor, and furnishing and incorporating materials and equipment into the construction. The Work also includes the entire completed construction, or the various separately identifiable parts thereof, required to be furnished under the Contract Documents.
1.7 TIME OF COMPLETION
The established Substantial Completion Date or number of consecutive calendar days (if specifically outlined) following the issuance of the Notice to Proceed which the Contractor has to substantially complete all Work required by the Contract. Work required by the project shall commence immediately upon receipt of a Notice to Proceed.
1.8
A. The Contractor shall obtain the Certificate of Substantial Completion as defined in the Contract Documents by August 21, 2026 from the Notice to Proceed.
B. Due to the nature of this institution, it is required that the academic schedules must be maintained. Contractor shall cooperate and coordinate with the Owner to assure that the schedules will be maintained.
DOCUMENTS REQUIRED BEFORE EXECUTION OF A CONTRACT
Contractor shall provide the following documents for the scope review meeting or if there is no scope review meeting provide the list of required documents within the time period outlined within the Letter of Intent to award:
A. Project Specific Critical Path Method Construction Schedule in sufficient detail as required under Section 3200 Construction Progress Documentation.
B. Hourly rates for trade or professional labor work self-performed by the Contractor shall be submitted utilizing the most current hourly rate form template provided by the Owner. Hourly Rates shall be reviewed and accepted by the Owner and are established for the life of the project. See Section on Contract Modifications and Project Management for more information
SUMMARY 01-1000-8
SUMMARY 08/2025 01-1000 - 8
on hourly rate requirements. The hourly rate template can be found at the following weblink:
https://updc.uconn.edu/contractors-working-at-uconn/
1.9 ACCESS TO THE SITE AND USE OF THE SITE
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Field Offices and Sheds: A field office space is not to be provided by the Contractor. Offices and storage sheds/containers shall be located within the site limits unless otherwise formally authorized by the Owner prior to submitting the Contractors logistics plans. Contractor shall not assume such authorization will be granted. Refer to Section 01 3100 Project Management and Coordination for requirements.
C. Access to the Site: Contractor shall always maintain control and access to the project site through final completion.
1. Access to the Campus:
As it relates to the Storrs Campus, all Contractors shall restrict use of construction related trucks on local, secondary roads, such as Hillyndale, Eastwood and Westwood Road, Hunting Lodge, Separatist and North Eagleville Road (from Hunting Lodge to SR 32) by using SR 195, SR 275 and North Hillside Road (from SR44 to North Eagleville Road on campus) as primary travel routes to the campus. Contractors shall not authorize the use of these secondary roads by construction related trucks or subcontractor vehicles in support of the project without explicit pre-authorization from the Owner on a per project basis.
Road Restrictions Map can be found at the following web link:
https://updc.uconn.edu/contractors-working-at-uconn/
2. Access to the Project Construction Site:
All Contractors shall access the construction site from Route 275. No other access shall be assumed.
D. Use of Site: Limit use of Project site to areas indicated; allow for Owner occupancy and use by the public. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to areas within the Project limits indicated in the contract documents. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.
a. Changes to the location of the identified perimeter contract limits, including access to the project site shall not be assumed by the Contractor. Contractor must submit a detailed narrative to the Architect and Owner on impacts to constructability as to why the contracted Project limits cannot be maintained.
b. Restore all lawn, sidewalk, paved areas damaged by vehicles and or construction activities to their original or better condition. See Section on Temporary Facilities and Controls for more details.
https://updc.uconn.edu/contractors-working-at-uconn/
SUMMARY 01-1000-9
SUMMARY 08/2025 01-1000 - 9
c. All grounds including construction site within contract limit shall be kept neat and orderly at all times.
2. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, other contractors and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Burial of Waste Materials: Do not dispose of organic and hazardous material on site, either by burial or by burning.
4. Construction Entrances:
Contractor shall prevent sediment from being transported onto paved areas and roads by construction vehicles exiting the project site. Contractor shall be responsible for immediate clean-up of soils or sediments tracked onto paved off site areas including but not limited to sweeping with motorized sweepers and power washing paved areas at frequencies as required within the contract documents but shall not be less than twice daily.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
5. Document Site Conditions and Progress of the Work:
Photograph and document daily the site conditions and progress of the work. Web Cameras are not required for this project. When required, the system shall provide for time lapse videography reflecting date and time with web view access at a minimum.
Aerial Photographs are not required for this project. If required, submit digital images in JPG2 format as outlined for digital cameras. If it is intended to use drones, Contractor must notify the Owner prior to use. If approved, Contractor must follow all governmental requirements and Owner Policy.
Refer to Section 01 3100 Project Management and Coordination Refer to Section 01 3200 Construction Progress Documentation Refer to Section 01 3233 Photographic Documentation Refer to Section 01 5640 Temporary Protection and Preservation Refer to Section 01 5719 Temporary Environmental Controls
6. Condition of Existing Building:
Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations.
Take all precautions necessary to protect the building and its occupants during the construction period.
7. Condition of existing perimeter Buildings and Landscape:
Protect surrounding buildings from noise, dust/dirt and pollution caused by the construction of the project. Clean exterior of the building(s) immendiately adjacent to the construction site. Replace and restore landscape/hardscape immediately surrounding the construction site which has been impacted by the project. Take all precautions necessary to protect the surrounding space and maintain controls.
SUMMARY 01-1000-10
SUMMARY 08/2025 01-1000 - 10
Refer to Sections for additional requirements not limited to 01-5000 Temporary Facilities and Controls and 01-5719 Temporary Environmental Controls for additional requirements
8. Parking: A modest/limited quantity of on campus parking spaces shall be made available within the contract limits to the Contractor, but not the subcontractors. All remaining demands for parking will follow the University Policy on Contractor Parking. Costs associated with parking on any University property is at the Contractor’s expense. Such policy can be located utilizing the following link;
http://policy.uconn.edu/2016/02/04/contractor-parking-policy.
1.10 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and building(s) during entire construction period.
Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
2. Notify Owner not less than 72 hours in advance of activities that will affect Owner's operations.
B. Partial Owner Occupancy: The Owner reserves the right to occupy and to place and install equipment in completed areas of the building, prior to Substantial Completion provided that such occupancy does not interfere with completion of the Work. Such placing of equipment and partial occupancy shall not constitute acceptance of the total Work or infer that the Contractor has met Substantial Completion.
1. A Certificate of Substantial Completion will be executed for each specific portion of the Work to be occupied prior to Owner occupancy.
2. Certifications. The Contractor at completion of construction shall provide to the University a “Certificate of Substantial Compliance with the State Building and Fire Safety Codes” bearing original signatures of an officer of the company stating: “This is to CERTIFY that in my professional opinion the complete structure/renovations described above is in substantial compliance with the approved construction documents on file with the University of Connecticut. Minor deviations and special stipulations are noted below (if any)”.
3. Prior to partial Owner occupancy, mechanical and electrical systems shall be fully operational. Required inspections and tests shall have been successfully completed. Upon recognition of mechanical and electrical systems being fully functioning and successfully inspected and tested for completeness, the Owner will provide operation and maintenance of mechanical and electrical systems in occupied portions of the building.
http://policy.uconn.edu/2016/02/04/contractor-parking-policy
SUMMARY 01-1000-11
SUMMARY 08/2025 01-1000 - 11
1.11 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations, the use of public streets and with other requirements of authorities having jurisdiction.
1. Work off Campus or on the edge of any campus where town residence property back up to or in close proximity to the Work, shall adhere to the Owner’s noise limits.
a. On-Site Work Hours: Limit work in the existing building to normal business working hours of 7:00 a.m. to 4:30 p.m., Monday through Friday, unless otherwise indicated.
Permission must be requested and approved in writing prior to performance of the work outside normal working hours or on a State Holiday.
b. Early Morning Hours for Dormitory Work: No noisy activities where the noise exceeds 55 dBA can take place prior to 8:00 am when working on or in the vicinity of a student dormitory.
c. Refer to Section 5719 Temporary Environmental Controls for other acceptable noise levels during working hours.
2. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
a. Obtain Owner Representative written permission before proceeding with utility interruptions.
3. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
a. Notify Owner Representative not less than two days in advance of proposed disruptive operations.
b. Obtain Owner’s written permission before proceeding with disruptive operations
c. Noise which exceeds 55 db at the site perimeter will not be permitted between the hours of
8:00 PM and 8:00 AM.
d. No Work may be conducted during University exam periods, commencement/graduation day, student move in/convocation days (includes Fridays), move out days (including Fridays) and Open House Fall and Spring without the written permission from the Owner.
Exam periods which may affect this project are scheduled per attached link:
http://www.registrar.uconn.edu/calendar.htm
4. Deviations: Contractor shall not assume deviations to the noise restrictions.
a. Deviation is dependent upon availability of University supervisory personnel and shall be at the Contractor’s expense.
b. Certain aspects of the project may require work to be performed off hours outside of the requirements the Contractor or Owner determines that work on this project must be performed during a time other than normal working hours of the University, costs for any premium time must be included in the Base Bid.
5. Prohibited Items: Refer to the latest version of the University’s Contractor Environmental Health and Safety Manual for products and substances which are prohibited on University property.
http://www.registrar.uconn.edu/calendar.htm
SUMMARY 01-1000-12
SUMMARY 08/2025 01-1000 - 12
1.12 WORK SEQUENCE
The responsibility of coordinating and phasing the Work falls entirely on the Contractor.
1.13 MISCELLANEOUS PROVISIONS
A. Certifications
1. The Contractor, at completion of construction, shall provide to the University a “Certificate of Substantial Compliance” bearing original signatures of an officer of the company stating:
“this is to CERTIFY that, in my professional opinion, the complete structure/renovations described above is in substantial compliance with the approved construction documents on file with the University of Connecticut. Minor deviations and special stipulations are noted below (if any)”
B. Background Screenings: Project specific background screenings on all workers anticipated to be performing work on the project is not required for this project. All Contractors and Subcontractors will follow the University’s Capital Project’s Background Screening Standards policy. All costs associated with implementation and management of the background screening standards shall be at the Contractor’s expense and those of their subcontractors.
Refer to Section 01-3300 Submittal Procedures for requirements
Refer to Section 01 3100 Project Management and Coordination for requirements
C. Owner and Bridging-Architect Supplied Documents/Data
1. The majority of the Owner’s buildings were constructed prior to 1978 and are likely to have painted surfaces contacting lead-based paint. Any information the Owner provides on known location of lead base paint or other hazardous materials. Any information the Owner provides on known locations of lead-based paint or other hazardous materials is offered, in good faith for information only, solely for the purpose of placing the Contractor in receipt of all information known to the University at this time. Unless otherwise provided, this and other data is not to be considered a part of the contract documents. The University does not warrant or represent that the information contained in these documents or reports is complete or accurate but only that it constitutes a disclosure of the information known to the Owner at this time regarding these conditions.
2. Original construction drawings, as-builts, modeling, calculations or other data are provided for information and reference only and do not represent exact conditions existing in the buildings. The Contractor is responsible for all work described in the scope of work regardless of information provided in the reference drawings. This information is offered in good faith for information only, solely for the purpose of placing the Contractor in receipt of all information known to the University at this time. Unless otherwise provided, this data is not to be considered a part of the contract documents. The University does not warrant or represent that the information contained in these reports is complete or accurate but only that it constitutes a disclosure of the information known to the Owner at this time regarding these conditions.
SUMMARY 01-1000-13
SUMMARY 08/2025 01-1000 - 13
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01-1000
Project Name Torrey Life Science Improvements Phase 1 Project# FO501995
SUBSTITUTION PROCEDURES 01-2500-1
100% Contract Documents
01-2500 - 1 03 / 2026
SECTION 01-2500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Division 01 Section "Allowances" for products selected under an allowance.
2. Division 01 Section "Alternates" for products selected under an alternate.
3. Division 01 Section "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
4. Divisions 02 through 33 Sections for specific requirements and limitations for substitutions.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents.
1. Specifications where there are multiple named manufactures of a particular product and does not note “or approved equal” such product submittals are limited to those manufactures listed with no substitutions being permitted.
2. Specifications that provide a performance-based specification for a particular product with a single manufacturer’s name as the basis of design and “or approved equal” is included, such submittal is not considered a substitution, if the product submitted for consideration has been determined by the Architect and Owner to meet or exceed all aspects of the performance, compatibility and other requirements outlined by the performance-based product specifications.
3. Request for substitution shall not be based on failure to adequately plan the review of a product submittal, confirming extended warranty requirements, obtain approval of the product submittal timely, and properly schedule to install without impact to other trade work and construction schedule. The Contractor is responsible for any additional costs
SUBSTITUTION PROCEDURES 01-2500-2
01-2500 - 2 03 / 2026 associated in expediting delivery or surcharges or upcharges associated with maintaining compliance with the contract documents and construction schedule.
B. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product and regulatory changes.
a. Discontinuation or lead time issues of product which has been determined by the
Architect or Owner to be caused by Contractor’s failure to submit timely for approval and/or immendiately secure previously approved product shall not be grounds for substitution, nor does it relieve the Contractor of their obligations to supply the product specified at no additional cost to the Owner.
1) If such product is not available on the secondary market, Contractor shall submit on any other listed manufacturer product within the specific specification, at no additional cost to the Owner.
2) If there was no other product manufacturers listed with the discontinued product, Architect will identify as close a comparable product for Contractor to submit on. Such submission shall be at no additional cost to the Owner.
2. Substitutions for Convenience: Changes proposed by Contractor that are not required in order to meet other Project requirements but may offer advantages to both the Contractor and Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable. Provide documentation that supports such submission.
b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.
Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
SUBSTITUTION PROCEDURES 01-2500-3
01-2500 - 3 03 / 2026
g. List of similar installations for completed projects with project name and contact names, current phone numbers and addresses of architects and owners who were directly involved with accepting the product substitution.
h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
i. Safety Data Sheet demonstrates that the product does not contain any hazardous material as defined in Section 01-7839 Project Record Documents.
j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Savings to the Owner, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
m. By submitting such documentation, the Contractor waives their rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to properly perform or produce indicated results. Any additional costs associated with other work classifications may be required to perform to assist in the accepted substitution to achieve the performance and results claimed, shall be at a cost to the Contractor.
2. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven (7) days of receipt of a request for substitution. Architect will notify the Owner of their recommendation to accept or reject the submission. Upon Owner decision, Architect will notify Contractor of acceptance or rejection of proposed substitution within seven (7) days of receipt of request, or seven (7) days of receipt of additional information or documentation, whichever is later.
a. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. If applicable, engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
SUBSTITUTION PROCEDURES 01-2500-4
01-2500 - 4 03 / 2026
B. Architect/Engineer shall review the request for substitution in accordance with the conditions and requirements stated within. Once a determination has been made by the Architect/Engineer, the Architect/Engineer will summarize the request and provide their findings and recommendations in writing to the Owner. The Owner will review and make the final determination of acceptance of the substitution. Such acceptance must be obtained in writing from the Owner. Provide the summary findings and Owner acceptance of the substitution with the change management document.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Submit requests for substitution within 14 days from Owner-Contractor contract execution.
Consideration of requests for substitution are solely at the discretion of the Owner, with assistance from the Architect.
1. Multiple resubmissions caused by incomplete information being submitted are limited to one resubmission or additional information submission. Any costs the Owner incurs for submission reviews of substitutions shall be at the Contractor’s expense regardless if the product substitution is accepted.
B. Conditions: Architect and Owner may consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will deny the request and return to record noncompliance with any of these requirements:
1. Is consistent with the Contract Documents and will produce indicated results. Must meet all product details and exceed all product performance as those explicit to the basis of design.
2. Provides sustainable design characteristics that the specified product provided.
3. Is fully documented and properly submitted.
4. Does not contain any hazardous material.
5. Will not adversely affect Contractor's CPM construction schedule.
6. Has received necessary approvals of authorities having jurisdiction.
7. Is fully compatible with other portions of the Work.
8. Has been coordinated with other portions of the Work.
9. Provides equal or better warranty than specified. If the manufacturer’s standard warranty does not meet the specified warranty, a notarized certified letter from manufacturer (not their Representative) shall be required at the time of consideration.
10. Does not require additional design changes to be performed by the architect/engineer in order to incorporate the substitution into the work.
11. Is compatible within the allocated space intended for the product originally specified.
12. Is a gross credit from all involved contractors, including overhead and profit to the
Owner.
SUBSTITUTION PROCEDURES 01-2500-5
01-2500 - 5 03 / 2026
13. If requested substitution involves more than one contractor, requested substitution must represent full coordination with other portions of the Work, is uniform and consistent, is fully compatible with other products, and is acceptable to all contractors involved.
14. If the product substitution is accepted; all performance, compatibility, coordination and liability of the product is the sole responsibility of the Contractor.
PART 3 - EXECUTION
3.1 NON-COMPLIANCE
A. The Contractor shall replace the product substituted with the initially specified product including any associated work and reimburse all associated costs incurred by the Owner and/or Architect should it be determined that such product substitute is not compatible with associated portions of the work, does not perform to the level of the initially specified product and/or the manufacturer will not provide the warranty/guaranty as was initially specified.
END OF SECTION 01-2500
Project# FO501995
CONTRACT MODIFICATION 01-2600-1
PROCEDURES
01-2600 - 1 03/2026
SECTION 01-2600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Division 01 Section "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions” (ASI). The Contractor shall proceed with minor changes in the work shown on ASI’s.
1.4 AE PROPOSAL REQUESTS OR BULLETINS
A. Initiated Proposal Requests: Architect or Owner will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
B. Proposal Requests (PR) or Bulletins issued by the Architect or Engineer are not instructions either to stop work in progress or to execute the proposed change. The Contractor shall only proceed with the change work when a CCD or CO is executed by the Owner.
Project# FO501995
CONTRACT MODIFICATION 01-2600-2
01-2600 - 2 03/2026
1.5 ADMINISTRATION OF CHANGES IN THE WORK
A. Changes to the work shall be submitted in accordance with all contract document requirements.
1. Section 4b-24 of the Connecticut General Statutes, the public auditors of the State of Connecticut and the auditors or accountants of the Owner shall have the right to audit and make copies of the books of the Contractor employed by the Owner.
2. All changes in the Work shall be subject to the written approval of the Owner.
a. A change in the Contract Sum or the Contract Time shall be accomplished only by formal written change order signed by both parties.