PROJECT MANUAL.pdf

PDF 9 MB Posted

Attached to
Ames Generator Replacement
Solicitation number
645-DOTRFB-3180-2027
Issued by
Story County, Iowa

About this file

PROJECT MANUAL SUMMARY

This Project Manual is issued by the Iowa Department of Transportation, Resources & Acquisitions Bureau for the Ames Hub Generator Replacement project located at 800 Lincoln Way, Ames, Iowa 50010 (Project Number BG-3A11(080)--80-85). The project involves removal and replacement of the existing generator for the Hub Building and installation of a new natural gas line through the parking lot. The work is structured as multiple prime contracts based on stipulated prices. Construction operations are limited to normal Department of Transportation operational hours (7:00 a.m. to 4:00 p.m.), with owner occupancy of adjacent existing buildings continuing during the entire construction period. A pre-construction meeting will be scheduled after Notice of Award, followed by a site mobilization meeting prior to contractor occupancy. The estimated project start date is July 1, 2027, with completion targeted by August 31, 2028. A preliminary construction schedule is due within 10 days of the Owner-Contractor Agreement, with a complete schedule due within 20 days thereafter.

Payment procedures follow the AIA G702 and G703 forms, with applications submitted at intervals stipulated in the agreement and requiring supporting documentation including construction progress schedules, partial releases of liens, and certificates of insurance for off-site stored products. Change orders are limited to a maximum 15% markup total between subcontractor and general contractor (including all overhead, profit, insurance, and bonds) and require a signed AIA G701 document from an authorized Iowa DOT official prior to proceeding with any work modifications. The contractor must provide all products as new unless specifically required or permitted otherwise, with preference given to products extracted, harvested, or manufactured closer to the project location and those with lower volatile organic compound content. All submittals must be made electronically in PDF, MS Word, or MS Excel format through the contractor's online document management service. Performance and payment bonds covering 100% of the contract value are required for amounts of $25,000 or more. Payment terms are Net 60, made monthly via state warrant at 97% of work performed, with the remaining 3% due upon final completion. The contractor must maintain all site records, provide comprehensive final cleaning, conduct an 11-month inspection with the Iowa DOT representative, and furnish operation and maintenance manuals in commercial-quality three-ring binders organized by specification section with full contact information and maintenance schedules.

View the file

Other files

File Type Posted
1463661-event.pdf PDF
A201-2017 Template.pdf PDF
PLANS.pdf PDF
A101-2017 - for RFB FINAL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ames Hub Generator Replacement 00 01 01 - 1 Project Title Page

SECTION 00 01 01

PROJECT TITLE PAGE

PROJECT MANUAL

AMES HUB GENERATOR REPLACEMENT

PROJECT NUMBER: BG-3A11(080)--80-85

PROJECT LOCATION ADDRESS 1

AMES , IOWA

OWNER:

STATE OF IOWA

IOWA DEPARTMENT OF TRANSPORTATION

800 LINCOLN WAY

AMES, IOWA 50010

ISSUED BY:

PURCHASING

RESOURCES & ACQUISITIONS BUREAU

IOWA DEPARTMENT OF TRANSPORTATION

800 LINCOLN WAY

AMES, IOWA 50010

ARCHITECT:

ARCHITECTURAL SERVICES

RESOURCES & ACQUISITIONS BUREAU

IOWA DEPARTMENT OF TRANSPORTATION

800 LINCOLN WAY

AMES, IOWA 50010

DATE: SEPTEMBER 2026

END OF SECTION

Replacement 00 01 10 - 1 Table of Contents

SECTION 00 01 10

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

A. 00 01 01 - Project Title Page B. 00 01 07 - Seals Page C. 00 01 10 - Table of Contents D. 00 01 15 - List of Drawing Sheets

SPECIFICATIONS

2.01 DIVISION 01 -- GENERAL REQUIREMENTS

A. 01 10 00 - Summary B. 01 20 00 - Price and Payment Procedures C. 01 25 00 - Substitution Procedures D. 01 30 00 - Administrative Requirements E. 01 32 16 - Construction Progress Schedule F. 01 40 00 - Quality Requirements G. 01 41 00 - Regulatory Requirements H. 01 42 16 - Definitions I. 01 60 00 - Product Requirements J. 01 70 00 - Execution and Closeout Requirements K. 01 78 00 - Closeout Submittals L. 01 79 00 - Demonstration and Training

2.02 DIVISION 03 -- CONCRETE

2.03 DIVISION 04 -- MASONRY

2.04 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

2.05 DIVISION 08 -- OPENINGS

2.06 DIVISION 12 -- FURNISHINGS

2.07 DIVISION 13 -- SPECIAL CONSTRUCTION

2.08 DIVISION 26 -- ELECTRICAL

A. 260500 - Common Work Results for Electrical B. 260519 - Low-Voltage Electrical Power Conductors and Cables C. 260526 - Grounding and Bonding for Electrical Systems D. 260529 - Hangers and Supports for Electrical Systems E. 260533.16 - Boxes for Electrical Systems F. 260553 - Identification for Electrical Systems G. 263213 - Engine Generators

2.09 DIVISION 31 -- EARTHWORK

2.10 DIVISION 32 -- EXTERIOR IMPROVEMENTS

Replacement 00 01 15 - 1 List of Drawing Sheets

SECTION 00 01 15

LIST OF DRAWING SHEETS

G000 COVER SHEET

E000 ELECTRICAL GENERAL INFORMATION

E100 ELECTRICAL SITE PLAN

E200 BASEMENT PLAN

E300 ELECTRICAL ONE-LINE SCHEDULES

Replacement 01 10 00 - 1 Summary

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

PROJECT

1.01 PROJECT NAME:

A. Ames Hub Generator Replacement

1.02 OWNER'S NAME:

A. State of Iowa, Iowa Department of Transportation.

1.03 THE PROJECT CONSISTS OF THE FOLLOWING:

A. Removal and replacement of generator for the Hub Building and new natural gas line through parking lot.

1.04 CONTRACT DESCRIPTION

A. Contract Type: Multiple prime contracts, each based on a Stipulated Price as described in

Document 00 50 00 - Contracting Forms and Supplements.

1.05 DESCRIPTION OF ALTERATIONS WORK

A. Scope of alterations work is indicated on drawings.

1.06 OWNER OCCUPANCY

A. Owner intends to occupy adjacent existing buildings during the entire construction period.

1.07 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to the boundaries of the property line indicated on the plans.

1. Locate and conduct construction activities in ways that will limit disturbance to site.

B. Arrange use of site and premises to allow:

1. Owner occupancy.

2. Work by Others.

3. Work by Owner.

C. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

D. Existing building spaces may not be used for construction storage.

E. Time Restrictions:

1. Limit conduct of work to the normal DOT operational hours. Estimated time is 7 a.m. to 4 p.m. unless otherwise arranged with local representative.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

Replacement 01 20 00 - 1 Price and Payment Procedures

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

D. Procedures for preparation and submittal of application for final payment.

1.02 RELATED REQUIREMENTS

A. Section 01 21 00 - Allowances: Payment procedures relating to allowances.

B. Section 01 22 00 - Unit Prices: Monetary values of unit prices; Payment and modification procedures relating to unit prices.

C. Section 01 78 00 - Closeout Submittals: Project record documents.

1.03 SCHEDULE OF VALUES

A. Use Schedule of Values Form: AIA G703, edition stipulated in the Agreement.

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Architect for approval.

C. Forms filled out by hand will not be accepted.

D. Submit Schedule of Values electronicly within 15 days after date of Owner-Contractor

Agreement.

E. Revise schedule to list approved Change Orders, with each Application For Payment.

1.04 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Use Form AIA G702 and Form AIA G703, edition stipulated in the Agreement.

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval.

D. Forms filled out by hand will not be accepted.

E. Execute certification by signature of authorized officer.

F. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of work.

G. Submit one electronic and __________ hard-copies of each Application for Payment.

H. Include the following with the application:

1. Transmittal letter as specified for submittals in Section 01 30 00.

2. Construction progress schedule, revised and current as specified in Section 01 30 00.

3. Partial release of liens from major subcontractors and vendors.

4. Affidavits attesting to off-site stored products.

5. Certificate of insurance for stored products off site with name business location, address, description of items and dollar value of stored materials.

1.05 MODIFICATION PROCEDURES

A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Architect will issue instructions directly to Contractor.

B. For other required changes, Architect will issue a document signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

Replacement 01 20 00 - 2 Price and Payment Procedures

2. Promptly execute the change.

C. For changes for which advance pricing is desired, Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 10 days.

D. Change request/order procedure.

1. Proposal request submitted by DOT project manager to general contractor.

a. Maximum 15% markup total between sub-contractor and general including all overhead, profit, insurance and bonds.

1) I.E. GC 10% and sub 5% on change order.

b. Verbal and written communications are NOT an approval to proceed with any changes to the work. An AIA document G701 Change Order signed by an authorized Iowa DOT official is required prior to proceeding with any changes to the work or deviation from the contract. Any changes to the work performed by the Contractor before a signed AIA G701 Change Order is received is assumed at the Contractor's own risk, liability and expense.

E. Contractor may propose a change by submitting a request for change to Architect, describing the proposed change and its full effect on the work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation.

Document any requested substitutions in accordance with Section 01 60 00.

F. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

1. For pre-determined unit prices and quantities, the amount will be based on the fixed unit prices.

G. Substantiation of Costs: Provide full information required for evaluation.

1. On request, provide the following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

H. Execution of Change Orders: Architect will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

I. After execution of Change Order, promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

J. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

K. Promptly enter changes in Project Record Documents.

1.06 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

PART 2 PRODUCTS - NOT USED

Replacement 01 25 00 - 1 Substitution Procedures

SECTION 01 25 00

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedural requirements for proposed substitutions.

1.02 RELATED REQUIREMENTS

A. Section 00 21 13 - Instructions to Bidders: Restrictions on timing of substitution requests.

B. Section 00 43 25 - Substitution Request Form - During Procurement: Required form for substitution requests made prior to award of contract (During procurement).

C. Section 00 63 25 - Substitution Request Form - During Construction: Required form for substitution requests made after award of contract (During construction).

D. Section 01 30 00 - Administrative Requirements: Submittal procedures, coordination.

E. Section 01 60 00 - Product Requirements: Fundamental product requirements, product options, delivery, storage, and handling.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

4. Waives claims for additional costs or time extension that may subsequently become apparent.

5. Agrees to reimburse Owner and Architect for review or redesign services associated with re-approval by authorities.

B. A Substitution Request for specified installer constitutes a representation that the submitter:

C. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

1. Note explicitly any non-compliant characteristics.

D. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.

1. Forms indicated in the Project Manual are adequate for this purpose, and must be used.

E. Limit each request to a single proposed substitution item.

1. Submit an electronic document, combining the request form with supporting data into single document.

3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT

A. Submittal Time Restrictions:

B. Submittal Form (before award of contract):

3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Substitutions will not be considered under one or more of the following circumstances:

1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.

2. Without a separate written request.

Replacement 01 25 00 - 2 Substitution Procedures

3.04 RESOLUTION

A. Architect may request additional information and documentation prior to rendering a decision.

Provide this data in an expeditious manner.

B. Architect will notify Contractor in writing of decision to accept or reject request.

3.05 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.06 CLOSEOUT ACTIVITIES

A. See Section 01 78 00 - Closeout Submittals, for closeout submittals.

Replacement 01 30 00 - 1 Administrative Requirements

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. General administrative requirements.

B. Preconstruction meeting.

C. Site mobilization meeting.

D. Progress meetings.

E. Construction progress schedule.

F. Progress photographs.

G. Coordination drawings.

H. Submittals for review, information, and project closeout.

I. Number of copies of submittals.

J. Requests for Interpretation (RFI) procedures.

K. Submittal procedures.

1.02 RELATED REQUIREMENTS

A. Section 01 32 16 - Construction Progress Schedule: Form, content, and administration of schedules.

B. Section 01 60 00 - Product Requirements: General product requirements.

C. Section 01 70 00 - Execution and Closeout Requirements: Additional coordination requirements.

D. Section 01 78 00 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.

1.03 REFERENCE STANDARDS

A. AIA G716 - Request for Information; 2004.

B. AIA G810 - Transmittal Letter; 2001.

C. CSI/CSC Form 13.2A - Request for Information; Current Edition.

1.04 GENERAL ADMINISTRATIVE REQUIREMENTS

A. Comply with requirements of Section 01 70 00 - Execution and Closeout Requirements for coordination of execution of administrative tasks with timing of construction activities.

1.05 PROJECT COORDINATION

A. Project Coordinator: Owner Project Manager (Iowa DOT Architectural Services Project Manager)

B. Cooperate with the Project Coordinator in allocation of mobilization areas of site; for field offices and sheds, for ________ access, traffic, and parking facilities.

C. During construction, coordinate use of site and facilities through the Project Coordinator.

D. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.

E. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities. Responsibility for providing temporary utilities and construction facilities is identified in Section 01 10 00 - Summary.

F. Coordinate field engineering and layout work under instructions of the Project Coordinator.

Replacement 01 30 00 - 2 Administrative Requirements

G. Make the following types of submittals to Architect through the Project Coordinator:

1. Requests for Interpretation.

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 ELECTRONIC SUBMISSION:

A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF, MS Word, or MS Excel) format, as appropriate to the document, and transmitted via contractor's online document management service.

3.02 PRECONSTRUCTION MEETING

A. Architect will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Architect/Engineer.

3. General Contractor.

4. All major Sub-Contractors.

C. Agenda:

1. Review Owner-Contractor Agreement and contract conditions.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

5. Designation of personnel representing the parties to Contract, Owner and Architect .

6. Review procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

7. Coordinate commencement of contstruction.

8. Use of premises by Owner and Contractor.

9. Temporary utilities provided by Contractor.

10. Security and housekeeping procedures.

11. Procedures for testing.

12. Procedures for maintaining record documents.

13. Requirements for start-up of equipment.

14. Inspection and acceptance of equipment put into service during construction period.

15. Scheduling.

16. Scheduling activities of a Geotechnical Engineer.

D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.03 SITE MOBILIZATION MEETING

A. Iowa Department of Transportation will schedule meeting at the Project site prior to Contractor occupancy.

Replacement 01 30 00 - 3 Administrative Requirements

B. Attendance Required:

1. Contractor.

2. Iowa Department of Transportation.

3. Architect.

4. Contractor's Superintendent.

5. Major Subcontractors.

C. Agenda:

1. Use of premises by Iowa Department of Transportation and Contractor.

2. Iowa Department of Transportation's requirements and occupancy prior to completion.

3. Construction facilities and controls provided by Iowa Department of Transportation.

4. Temporary utilities provided by Iowa Department of Transportation.

5. Survey and building layout.

6. Security and housekeeping procedures.

7. Schedules.

8. Application for payment procedures.

9. Procedures for testing.

10. Procedures for maintaining record documents.

11. Requirements for start-up of equipment.

12. Inspection and acceptance of equipment put into service during construction period.

D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.04 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the work at maximum bi-weekly intervals.

B. General Contractor will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required: Job Superintendent, major Subcontractors and suppliers, Owner Project

Manager, Architect/Engineer, as appropriate to agenda topics for each meeting.

1. Contractor.

2. Owner.

3. Architect.

4. Special consultants.

5. Contractor's superintendent.

6. Major subcontractors.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of RFIs log and status of responses.

7. Review of off-site fabrication and delivery schedules.

8. Maintenance of progress schedule.

9. Corrective measures to regain projected schedules.

10. Planned progress during succeeding work period.

11. Coordination of projected progress.

12. Status of Proposal Requests, Change Orders, Architect's Supplemental Instructions and

Requests For Information. Maintenance of quality and work standards.

13. Maintenance of quality and work standards.

14. Effect of proposed changes on progress schedule and coordination.

15. Other business relating to work.

Replacement 01 30 00 - 4 Administrative Requirements

E. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.05 CONSTRUCTION PROGRESS SCHEDULE - SEE SECTION 01 32 16

A. Within 10 days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

3.06 PROGRESS PHOTOGRAPHS

A. Submit new photographs at least once a month, within 3 days after being taken.

B. Photography Type: Digital; electronic files.

C. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to Architect.

D. In addition to periodic, recurring views, take photographs of each of the following events:

1. Completion of site clearing.

2. Excavations in progress.

3. Foundations in progress and upon completion.

4. Prior to placement of paving sub-base after compaction of sub-grade.

5. After placement and compaction of sub-base and installation of reinforcement (where called for) but before paving

6. Structural framing in progress and upon completion.

E. Views:

1. Provide non-aerial photographs from four cardinal views at each specified time, until date of Substantial Completion.

2. Consult with Architect for instructions on views required.

3. Provide factual presentation.

4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

F. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: Via email.

2. File Naming: Include project identification, date and time of view, and view identification.

3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.

3.07 REQUESTS FOR INTERPRETATION (RFI)

A. Definition: A request seeking one of the following:

1. An interpretation, amplification, or clarification of some requirement of Contract

Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.

2. A resolution to an issue which has arisen due to field conditions and affects design intent.

B. Whenever possible, request clarifications at the next appropriate project progress meeting, with response entered into meeting minutes, rendering unnecessary the issuance of a formal RFI.

Replacement 01 30 00 - 5 Administrative Requirements

C. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

2. Prepare in a format and with content acceptable to Owner.

a. Use AIA G716 - Request for Information .

b. Use CSI/CSC Form 13.2A - Request for Interpretation.

D. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.

1. Include in each request Contractor's signature attesting to good faith effort to determine from Contract Documents information requiring interpretation.

2. Unacceptable Uses for RFIs: Do not use RFIs to request the following::

a. Approval of submittals (use procedures specified elsewhere in this section).

b. Approval of substitutions (see Section - 01 60 00 - Product Requirements)

c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Conditions of the Contract).

d. Different methods of performing work than those indicated in the Contract Drawings and Specifications (comply with provisions of the Conditions of the Contract).

3. Frivolous RFIs: Requests regarding information that is clearly indicated on, or reasonably inferable from, Contract Documents, with no additional input required to clarify the question. They will be returned without a response, with an explanatory notation.

a. The Owner reserves the right to assess the Contractor for the costs (on time-and-materials basis) incurred by the Architect, and any of its consultants, due to processing of such RFIs.

E. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

F. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.

G. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.

1. Indicate current status of every RFI. Update log promptly and on a regular basis.

2. Note dates of when each request is made, and when a response is received.

3. Highlight items requiring priority or expedited response.

4. Highlight items for which a timely response has not been received to date.

H. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.

1. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith.

Identify the amended RFI with an R suffix to the original number.

2. Do not extend applicability of a response to specific item to encompass other similar conditions, unless specifically so noted in the response.

3.08 SUBMITTAL SCHEDULE

A. Submit to Architect for review a schedule for submittals in tabular format.

1. Submit at the same time as the preliminary schedule.

2. Format schedule to allow tracking of status of submittals throughout duration of construction.

3. Account for time required for preparation, review, manufacturing, fabrication and delivery when establishing submittal delivery and review deadline dates.

a. For assemblies, equipment, systems comprised of multiple components and/or requiring detailed coordination with other work, allow for additional time to make corrections or revisions to initial submittals, and time for their review.

Replacement 01 30 00 - 6 Administrative Requirements

3.09 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Architect for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.

C. Samples will be reviewed for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00 - Closeout Submittals.

3.10 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Other types indicated.

7. Manufacturer's field reports.

8. Other types indicated.

B. Submit for Architect's knowledge as contract administrator or for Iowa Department of Transportation. No action will be taken.

3.11 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 78 00 - Closeout Submittals:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

D. Submit for Owner's benefit during and after project completion.

3.12 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.13 SUBMITTAL PROCEDURES

General Requirements:

1. Use a separate transmittal for each item.

2. Transmit using approved form.

a. Use Form AIA G810.

Replacement 01 30 00 - 7 Administrative Requirements

3. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.

4. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.

5. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.

a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.

6. Schedule submittals to expedite the Project, and coordinate submission of related items.

a. For each submittal for review, allow 21 days excluding delivery time to and from the Contractor.

b. For sequential reviews involving Architect's consultants, Owner, or another affected party, allow an additional 7 days.

c. For sequential reviews involving approval from authorities having jurisdiction (AHJ), in addition to Architect's approval, allow an additional 30 days.

7. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.

8. Provide space for Contractor and Architect review stamps.

9. When revised for resubmission, identify all changes made since previous submission.

10. Distribute reviewed submittals. Instruct parties to promptly report inability to comply with requirements.

11. Incomplete submittals will not be reviewed, unless they are partial submittals for distinct portion(s) of the work, and have received prior approval for their use.

12. Submittals not requested will not be recognized or processed.

A. Product Data Procedures:

1. Submit only information required by individual specification sections.

2. Collect required information into a single submittal.

3. Do not submit (Material) Safety Data Sheets for materials or products.

B. Shop Drawing Procedures:

1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting

Contract Documents and coordinating related work.

2. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.

C. Deliver submittals to Owner in electronic format only.

1. Only physical samples to be submitted to Owner's address.

D. Samples Procedures:

1. Transmit related items together as single package.

2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.

3.14 SUBMITTAL REVIEW

A. Submittals for Review: Architect will review each submittal, and approve, or take other appropriate action.

B. Submittals for Information: Architect will acknowledge receipt and review. See below for actions to be taken.

C. Architect's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.

D. Architect's and consultants' actions on items submitted for review:

1. Authorizing purchasing, fabrication, delivery, and installation:

a. "Approved", or language with same legal meaning.

Replacement 01 30 00 - 8 Administrative Requirements

b. "Approved as Noted, Resubmission not required", or language with same legal meaning.

1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.

c. "Approved as Noted, Resubmit for Record", or language with same legal meaning.

2. Not Authorizing fabrication, delivery, and installation:

a. "Revise and Resubmit".

1) Resubmit revised item, with review notations acknowledged and incorporated.

b. "Rejected".

1) Submit item complying with requirements of Contract Documents.

E. Architect's and consultants' actions on items submitted for information:

1. Items for which no action was taken:

a. "Received" - to notify the Contractor that the submittal has been received for record only.

2. Items for which action was taken:

a. "Reviewed" - no further action is required from Contractor.

Replacement 01 32 16 - 1 Construction Progress Schedule

SECTION 01 32 16

CONSTRUCTION PROGRESS SCHEDULE

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Construction progress schedule, bar chart type.

1.02 SUBMITTALS

A. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

B. Submit updated schedule with each Application for Payment.

1.03 QUALITY ASSURANCE

A. Scheduler: Contractor's personnel or specialist Consultant specializing in CPM scheduling with one years minimum experience in scheduling construction work of a complexity comparable to this Project, and having use of computer facilities capable of delivering a detailed graphic printout within 48 hours of request.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 BAR CHARTS

A. Include a separate bar for each major portion of Work or operation.

B. Identify the first work day of each week.

3.02 NETWORK ANALYSIS

A. Prepare network analysis diagrams and supporting mathematical analyses using the Critical

Path Method.

B. Illustrate order and interdependence of activities and sequence of work; how start of a given activity depends on completion of preceding activities, and how completion of the activity may restrain start of subsequent activities.

C. Mathematical Analysis: Tabulate each activity of detailed network diagrams, using calendar dates, and identify for each activity:

1. Preceding and following event numbers.

2. Activity description.

3. Estimated duration of activity, in maximum 15 day intervals.

4. Earliest start date.

5. Earliest finish date.

6. Actual start date.

7. Actual finish date.

8. Latest start date.

9. Latest finish date.

10. Total and free float; float time shall accrue to Owner and to Owner's benefit.

11. Monetary value of activity, keyed to Schedule of Values.

12. Percentage of activity completed.

13. Responsibility.

D. Analysis Program: Capable of compiling monetary value of completed and partially completed activities, accepting revised completion dates, and recomputation of all dates and float.

E. Required Reports: List activities in sorts or groups:

1. By preceding work item or event number from lowest to highest.

2. By amount of float, then in order of early start.

3.03 REVIEW AND EVALUATION OF SCHEDULE

A. Participate in joint review and evaluation of schedule with Architect at each submittal.

Replacement 01 32 16 - 2 Construction Progress Schedule

B. Evaluate project status to determine work behind schedule and work ahead of schedule.

C. After review, revise as necessary as result of review, and resubmit within 10 days.

3.04 UPDATING SCHEDULE

A. Maintain schedules to record actual start and finish dates of completed activities.

B. Indicate progress of each activity to date of revision, with projected completion date of each activity.

C. Annotate diagrams to graphically depict current status of Work.

D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.

E. Indicate changes required to maintain Date of Substantial Completion.

F. Submit reports required to support recommended changes.

3.05 DISTRIBUTION OF SCHEDULE

A. Distribute copies of updated schedules to Contractor's project site file, to subcontractors, suppliers, Architect, Owner, and other concerned parties.

B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

Replacement 01 40 00 - 1 Quality Requirements

SECTION 01 40 00

QUALITY REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Submittals.

B. Quality assurance.

C. References and standards.

D. Inspection agencies and services.

E. Control of installation.

F. Tolerances.

G. Manufacturers' field services.

H. Defect Assessment.

1.02 RELATED REQUIREMENTS

A. Document 00 31 00 - Available Project Information: Soil investigation data.

B. Document 00 72 00 - General Conditions: Inspections and approvals required by public authorities.

C. Section 01 30 00 - Administrative Requirements: Submittal procedures.

D. Section 01 42 16 - Definitions.

E. Section 01 60 00 - Product Requirements: Requirements for material and product quality.

1.03 REFERENCE STANDARDS

A. ASTM C1021 - Standard Practice for Laboratories Engaged in Testing of Building Sealants;

2008 (Reapproved 2023).

B. ASTM C1077 - Standard Practice for Agencies Testing Concrete and Concrete Aggregates for

Use in Construction and Criteria for Testing Agency Evaluation; 2026.

C. ASTM C1093 - Standard Practice for Accreditation of Testing Agencies for Masonry; 2025.

D. ASTM D3740 - Standard Practice for Minimum Requirements for Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction; 2023.

E. ASTM E329 - Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection; 2025b.

F. ASTM E543 - Standard Specification for Agencies Performing Nondestructive Testing; 2026.

G. IAS AC89 - Accreditation Criteria for Testing Laboratories; 2025.

1.04 DEFINITIONS

A. Contractor's Professional Design Services: Design of some aspect or portion of the project by party other than the design professional of record. Provide these services as part of the Contract for Construction.

1. Design Services Types Required:

a. Construction-Related: Services Contractor needs to provide in order to carry out the Contractor’s sole responsibilities for construction means, methods, techniques, sequences, and procedures.

b. Design-Related: Design services explicitly required to be performed by another design professional due to highly-technical and/or specialized nature of a portion of the project. Services primarily involve engineering analysis, calculations, and design, and are not intended to alter the aesthetic aspects of the design.

Replacement 01 40 00 - 2 Quality Requirements

B. Design Data: Design-related, signed and sealed drawings, calculations, specifications, certifications, shop drawings and other submittals provided by Contractor, and prepared directly by, or under direct supervision of, appropriately licensed design professional.

1.05 SUBMITTALS

A. See Section 01 30 00 - Administrative Requirements, for submittal procedures.

B. Designer's Qualification Statement: Submit for Architect's knowledge as contract administrator, or for Owner's information.

1. Include information for each individual professional responsible for producing, or supervising production of, design-related professional services provided by Contractor.

a. Full name.

b. Professional licensure information.

c. Statement addressing extent and depth of experience specifically relevant to design of items assigned to Contractor.

C. Design Data: Submit for Architect's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents, or for Owner's information.

1. Include calculations that have been used to demonstrate compliance to performance and regulatory criteria provided, and to determine design solutions.

2. Include required product data and shop drawings.

3. Include signature and seal of design professional responsible for allocated design services on calculations and drawings.

D. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to Architect, in quantities specified for Product Data.

1. Indicate material or product complies with or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

E. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the Owner's information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

F. Manufacturer's Field Reports: Submit reports for Architect's benefit as contract administrator or for Owner.

1. Submit for information for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents.

G. Erection Drawings: Submit drawings for Architect's benefit as contract administrator or for

Owner.

1. Submit for information for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents.

1.06 REFERENCES AND STANDARDS

A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Comply with reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.

C. Obtain copies of standards where required by product specification sections.

D. Maintain copy at project site during submittals, planning, and progress of the specific work, until

Substantial Completion.

E. Should specified reference standards conflict with Contract Documents, request clarification from Architect before proceeding.

Replacement 01 40 00 - 3 Quality Requirements

F. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Architect shall be altered from Contract Documents by mention or inference otherwise in any reference document.

1.07 TESTING AND INSPECTION AGENCIES AND SERVICES

A. Owner shall employ and pay for services of a third party or an independent testing agency to perform specified inspection for equipment and materials provided and installed by contractor.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

PART 3 EXECUTION

2.01 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from

Architect before proceeding.

D. Comply with specified standards as minimum quality for the work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

2.02 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work.

Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from Architect before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

2.03 TESTING AND INSPECTION

A. Contractor to Notify the following agencies for required inspections of work to be outlined in the Pre-Construction Meeting and provide reports, certifications, and permits as applicable:

1. Iowa Department of Public Safety, State Fire Marshall Division, 215 E. 7th Street, Des

Moines, Iowa 50319 Phone: 515-725-6145

a. Electrical Inspection

b. Final Electrical Inspection

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract

Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

Replacement 01 40 00 - 4 Quality Requirements

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify Architect and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

6. Arrange with Owner's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-compliance with specified requirements shall be performed by the same agency on instructions by Architect.

E. Re-testing required because of non-compliance with specified requirements shall be paid for by Contractor.

2.04 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust, and balance equipment as applicable, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

2.05 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not complying with specified requirements.

B. If, in the opinion of Architect, it is not practical to remove and replace the work, Architect will direct an appropriate remedy or adjust payment.

Replacement 01 41 00 - 1 Regulatory Requirements

SECTION 01 41 00

REGULATORY REQUIREMENTS

PART 1 GENERAL

1.01 SUMMARY OF REFERENCE STANDARDS

A. Regulatory requirements applicable to this project are the following as adopted in the State of Iowa Building Code and enforced by the Iowa State Fire Marshal's Office including all amendments and modificaitons :

B. 28 CFR 35 - Nondiscrimination on the Basis of Disability in State and Local Government Services; Final Rule; Department of Justice; current edition.

C. 29 CFR 1910 - Occupational Safety and Health Standards; Current Edition.

D. 36 CFR 1191 - Americans with Disabilities Act (ADA) Accessibility Guidelines for Buildings and

Facilities; Architectural Barriers Act (ABA) Accessibility Guidelines; current edition.

E. ADA Standards - 2010 ADA Standards for Accessible Design; 2010.

F. ICC (IBC) - International Building Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

G. ICC (IECC) - International Energy Conservation Code; Most Recent Edition Adopted by

Authority Having Jurisdiction, Including All Applicable Amendments and Supplements.

H. ICC (IFC) - International Fire Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

I. ICC (IFGC) - International Fuel Gas Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

J. ICC (IMC) - International Mechanical Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

K. ICC (IPC) - International Plumbing Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

L. ICC A117.1 - Accessible and Usable Buildings and Facilities; 2017.

M. NFPA 70 - National Electrical Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

1.02 RELATED REQUIREMENTS

A. Section 01 40 00 - Quality Requirements.

PART 2 PRODUCTS - NOT USED

Replacement 01 42 16 - 1 Definitions

SECTION 01 42 16

DEFINITIONS

PART 1 GENERAL

1.01 SUMMARY

A. This section supplements the definitions contained in the General Conditions.

B. Other definitions are included in individual specification sections.

1.02 DEFINITIONS

A. Furnish: To supply, deliver, unload, and inspect for damage.

B. Install: To unpack, assemble, erect, apply, place, finish, cure, protect, clean, start up, and make ready for use.

C. Product: Material, machinery, components, equipment, fixtures, and systems forming the work result.