Project Manual (14).pdf
PDF 7 MB Posted
- Attached to
- Plantersville GLO Street Improvements
- Solicitation number
- Bleyl 13474
- Issued by
- Gillespie County, Texas
About this file
This is a Project Manual and Construction Specifications document prepared by Bleyl Engineering for the City of Plantersville, Texas, for street improvement work financed through the General Land Office (GLO) under the U.S. Department of Housing and Urban Development Community Development Block Grant - Mitigation (CDBG-MIT) program. The project (GLO Contract No. 24-065-080-E735, BE: 13474) involves earthwork, ditch regrading, rework and stabilization of existing base material, installation of new base material, placement of new asphalt pavement, and installation and repair of driveway culverts. Work items include removal of existing asphalt and culverts, installation of 24-inch HDPE culverts and 18-inch CMP culverts, asphalt driveway paving, construction material testing, clearing and grubbing, traffic control, and erosion control. The bid opening is scheduled for 2:00 p.m. on July 9, 2026, at 1722 Broadmoor Drive, Suite 210, Bryan, Texas 77802, addressed to Mayor Kimberly Allphin. Bids must remain open for acceptance for 60 days from the bid date. The contractor shall achieve substantial completion within 90 consecutive calendar days after the date of commencement of work. Bidders must conduct site inspections and become familiar with existing conditions; the City of Plantersville reserves the right to reject any or all bids or waive informalities.
A bid bond in the amount of 5 percent of the total bid is required for contracts exceeding $100,000, with alternatives including certified checks or U.S. Government Bonds at par value. The contract documents specify unit pricing for 14 bid items, with prices to be calculated by bidders using provided component prices and processes. Performance and payment bonds are required; municipalities must provide payment bonds for contracts exceeding $50,000. Prevailing wage rates determined by the Department of Labor under the Davis-Bacon and Related Acts must be paid to all laborers and mechanics, with wage determinations included in the contract documents. The project is subject to federal compliance requirements including Equal Employment Opportunity provisions, Section 3 economic opportunity requirements, debarment and suspension verification through the System for Award Management (SAM), and compliance with nondiscrimination statutes. Liquidated damages are set at $250 per calendar day for delays beyond the 90-day completion period. The contractor must maintain Worker's Compensation Insurance, Public Liability and Property Damage Insurance, and Vehicle Liability Insurance. Contract documents include bid forms, construction advertisement, instructions to bidders, general conditions, technical specifications, and drawings prepared by Bleyl Engineering. Copies of bid and contract documents are available for a $200 refundable deposit.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION SPECIFICATIONS
FOR
PLANTERSVILLE GLO STREET IMPROVEMENTS
GLO: 24-065-080-E735
BE: 13474
LOCATED IN
PLANTERSVILLE, TEXAS
PREPARED FOR
CITY OF PLANTERSVILLE
Engineer:
Bleyl Engineering Firm No. 678 1722 Broadmoor Drive, Suite 210 Bryan, Texas 77802
(979) 268-1125 Zachary M. Votaw, PE Project Manager
ZACHARY M. VOTAW
161166
06/23/2026
Bleyl Engineering Table of Contents Revised 7/9/2019 00 01 10: Page 1 of 2
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
1. Project Title Page
2. Table of Contents
3. Bid Form
4. Construction Advertisement and Invitation for Bids
5. Instructions to Bidders for Construction
6. Construction Contract
7. General Conditions – Part 1 for Construction
8. Equal Opportunity Guidelines for Construction Contractors
9. Section 3 Plan
10. Statement of Bidder’s Qualifications
11. Conflict of Interest Questionnaire
12. Non-collusion Affidavit of Prime Bidder
13. Bid Bond
14. Certification of Bidder Regarding Civil Rights Laws and Regulations
15. Contractor’s Certification of Recovered Materials
16. Contractor’s Local Opportunity Plan
17. Instructions for Proposed Contracts Breakdown and Estimated Project Workforce
Breakdown
18. Certification for Business Concerns
19. Contractor Certification of Efforts to Fully Comply with Employment and Training
Provisions of Section 3
20. Certification Regarding Lobbying
21. Disclosure of Lobbying Activities
22. Minority/Female Goals and Timetables
23. Federal Labor Standards Provisions
24. Title 29: Labor
25. Concerning Labor Standards and Prevailing Wage Requirements
26. Wage Decision
27. Payroll Packet and Labor Compliance Acknowledgement
28. GLO Signage Requirements
29. Section 504 Certification
30. Child Support Statement for Negotiated Contracts and Grants
31. Payment Bond
32. Performance Bond
33. Contractor’s Liability Insurance
34. Additional Condition of Award
35. Certificate of Interested Parties
36. Code of Federal Regulations
37. New Hires Section 3 Monthly Compliance Report
38. Section 3 Economic Opportunity
39. Assurances for Construction Programs
40. General Affirmations
41. Attorney’s Review Certification
42. Contractor’s Final Payment Affidavit
43. Change Order Form
44. Certificate of Construction Completion (CoCC)
Denotes documents to be submitted with a bid.
Bleyl Engineering Table of Contents Revised 7/9/2019 00 01 10: Page 2 of 2
CONDITIONS AND TECHNICAL SPECIFICATIONS
1. Reference Specifications TxDOT
OWNER:
Project Name:
Project No:
BIDDER:
1.0 OFFER
A.
B.
C.
D.
2.0 CONTRACT TIME
A.
BID FORM
Total Bid Price: Having examined the Project location and all matters referred to in Bid Documents for the Project, we, the undersigned, offer to enter into a Contract to perform the Work for the Total Bid Price shown on the signature page of this Document.
Period for Bid Acceptance: This offer is open to acceptance and is irrevocable for 60 days from Bid Date. The period for bid acceptance may be extended by mutual written agreement of the OWNER and BIDDER.
Addenda: All Addenda have been received. Modifications to Bid Documents have been considered and all related costs are included in the Total Bid Price.
If offer is accepted, CONTRACTOR shall achieve Date of Substantial Completion within ninety (90) consecutive calendar days after Date of Commencement of the Work, subject to adjustments of Contract Time as provided in the Contract.
Bid Supplements: The following documents are attached:
[ ] Others as listed:
City of Plantersville Plantersville GLO Street Improvements
GLO: 24-065-080-E735/BE: 13474
BIDDER acknowledges receipt of the following ADDENDA: _________________________________________________
Bleyl Engineering Revised 6/23/2026
Bid Form 00 41 43: Page 1 of 3
3.0
Item No.
Unit Quantity Total
BASE BID:
1 1 $___________
2 1 $___________
3 1 $___________
4 1.28 $___________
5 1,252 $___________
6 30 $___________
7 1 $___________
8 1 $___________
9 1 $___________
10 920 $___________
11 3,536 $___________
12 394 $___________
13 139 $___________
14 32 $___________
TOTAL BASE BID: $___________
Demo Existing Brightspeed Telephone Box and Line LS $___________
TOTAL BID PRICE HAS BEEN CALCULATED BY BIDDER, USING THE FOLLOWING COMPONENT
PRICES AND PROCESS (PRINT OR TYPE NUMERICAL AMOUNTS):
Section "A" Paving:
6" Rework & Cement Stabilization of Existing Base per TxDOT Item 275, 2" HMAC Ty DG-D, PG 64-22 w/ Tack Coat per TxDOT Item 341
SY $___________
Construction Material Testing LS
24" HDPE Culvert: 24" AASHTO M294 HDPE Culvert, smooth interior LF $___________
18" CMP Culvert: 18" AASHTO M36 Galvanized CMP Culvert, smooth interior LF
Remove Existing 24" HDPE Culvert and Concrete Cap LF $___________
SY $___________
Mobilization, bonds, and project overhead
Unit Measure
LS
Item Description Unit Price
Asphalt Driveway:
Proof Roll Existing Subgrade per TxDOT Item 247, 4" Flexible Base TY D, GR 1-2 per TxDOT Item 247, 2" HMAC TY DG-D, PG 64-22 w/ Tack Coat per TxDOT Item 341
SY $___________
Remove Existing Asphalt, all depths SY $___________
Earthwork including disposal of excess spoils LS
Traffic Control, Erosion Control, and Hydromulch Seeding LS $___________
Furnish, Install, and Maintain GLO signage board for posting required paper notices for the duration of the project LS $___________
Clearing and Grubbing AC $___________
Section "B" Paving:
Proof Roll Existing Subgrade per TxDOT Item 247, 6" Flexible Base TY D, GR 1-2 per TxDOT Item 247, 2" HMAC TY DG-D, PG 64-22 w/ Tack Coat per TxDOT Item 341
Bleyl Engineering Revised 6/23/2026
00 41 43: Page 2 of 3
4.0
BIDDER:
(Print or type full name of proprietorship, partnership, corporation, or joint venture.*)
**By:
Signature Date
Name:
(Print or type name) Title
Address:
(Mailing)
(Street Address, if different)
Telephone: Fax:
Email:
END OF SECTION
BIDDER certifies that the only person or parties interested in this offer as principals are those named above. BIDDER has not directly or indirectly entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding.
If Bid is a joint venture, add additional Bid Form signature sheets for each member of the joint venture.
SIGNATURES: By signing this Document, I agree that I have received and reviewed all Addenda and considered all costs associated with the Addenda in calculating the Total Bid Price.
Bleyl Engineering Revised 6/23/2026
00 41 43: Page 3 of 3
Construction Advertisement and Invitation for Bids
The City of Plantersville will receive bids for a street improvement project (GLO Contract No. 24-065-080-E735) until 2:00 p.m. on July 9th, 2026 at 1722 Broadmoor Drive, Suite 210, Bryan TX 77802. Bids must be addressed to: Kimberly Allphin, Mayor. The bids will be publicly opened and read aloud at the time and location described above.
Bids are invited for several items and quantities of work as follows:
1. Earthwork and regarding
2. Rework and stabilize existing base material
3. Install new base material
4. Install new asphalt pavement
5. Install culverts and repair driveways
Bid/Contract Documents, including Drawings and Technical Specifications are on file at Bleyl Engineering, 1722 Broadmoor Drive, Suite 210, Bryan, TX 77802, zvotaw@bleylengineering.com.
Copies of the Bid/Contract Documents may be obtained by depositing $200 with the engineer for each set of documents obtained. The deposit will be refunded if the documents and drawings are returned in good condition within 10 days following the bid opening.
A bid bond in the amount of 5 percent of the bid issued by an acceptable surety shall be submitted with each bid [for those contracts that exceed $100,000]. A certified check or bank draft payable to the City of Plantersville or negotiable U.S.
Government Bonds (as par value) may be submitted in lieu of the Bid Bond.
The project to be constructed will be financed with assistance from the General Land Office (GLO) under the U.S.
Department of Housing and Urban Development Community Development Block Grant - Mitigation (CDBG-MIT) program and is subject to all applicable Federal and State laws and regulations. Attention is called to the fact that not less than, the federally determined prevailing Davis-Bacon and Related Acts wage rate, as issued by the Department of Labor and contained in the contract documents, must be paid on this project. In addition, the successful bidder must ensure that employees and applicants for employment are not discriminated against because of race, color, religion, sex, sexual orientation, gender identity, or national origin. Adherence to the City of Plantersville Section 3 Policy is required for all contracts.
All contractors and subcontractors must be cleared (not suspended or debarred) prior to any formal action authorizing the award of a contract to the contractor. Minority Business Enterprises, Small Business Enterprises, Women Business Enterprises, Veteran-Owned Businesses, Section 3 Businesses, and labor surplus area firms are encouraged to submit bids.
The City of Plantersville reserves the right to reject any or all bids or to waive any informalities in the bidding. Bids may be held by City of Plantersville for a period not to exceed 60 days from the date of the bid opening for the purpose of reviewing the bids and investigating the bidder’s qualifications prior to the contract award.
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION
The project to be constructed will be financed with assistance from the General Land Office (GLO) under the U.S.
Department of Housing and Urban Development Community Development Block Grant - Mitigation (CDBG-MIT) program and is subject to all applicable Federal and State laws and regulations. The City of Plantersville is the subrecipient of the grant funding and is hereby referred to as “City/County”.
1. Use of Separate Bid Forms
These contract documents include a complete set of bid and contract forms which are for the convenience of the bidders and are not to be detached from the contract document, completed or executed. Separate bid forms are provided for your use.
2. Interpretations or Addenda
No oral interpretations will be made to any bidder. Each request for clarification shall be made in writing to the City/County or engineer no less than seven (7) days prior to the bid opening. Each interpretation made will be in the form of an Addendum to the contract documents and will be distributed to all parties holding contract documents no less than seven
(7) days prior to the bid opening. It is, however, the bidder's responsibility to make inquiry as to any addenda issued. All such addenda shall become part of the contract documents and all bidders shall be bound by such addenda, whether or not received by the bidders.
If an addendum to the bid package is necessary, it must be distributed to each potential bidder. The distribution of an addendum shall be verified either by statements of receipt or registered/certified mail receipts, which shall be included in the public works construction file. The addendum shall allow adequate time for consideration in bid preparation (usually at least one week). If adequate time is not available, the bid opening date must be extended and the City/County must republish the invitation for bids containing the place, time, and date for the new bid opening. Note that any change to the original bid opening date will require republication of the invitation for bids at least once in a locally published newspaper.
The republished notice will include the place, time and date for the new bid opening and must be published at least seven days prior to the new bid opening date.
3. Inspection of Site
Each bidder should visit the site of the proposed work and should become acquainted with the existing conditions and facilities, the difficulties and restrictions pertaining to the performance of the contract. The bidder should thoroughly examine and become familiar with the drawings, technical specifications and all other contract documents. The contractor by the execution of the contract shall in no way be relieved of any obligation under it due to failure to receive or examine any form or legal document or to visit the site or the conditions existing at the site. The City/ County will be justified in rejecting any claim based on lack of inspection of the site prior to the bid.
4. Alternate bid items
No alternate bids or bid items will be considered unless they are specifically requested by the technical specifications.
5. Bids
a. All bids must be submitted on the forms provided and are subject to all requirements of the Contract Documents, including the Drawings.
b. All bids must be regular in every respect and no interlineation, excisions or special conditions may be made or included by the bidder.
c. Bid documents, including but not limited to the bid, the bid bond(s), the contractor’s certifications, Certification of Bidder Regarding Civil Rights Laws and Regulations, Certification of Efforts to comply with Section 3, Local Opportunity Plan, Conflict of Interest Questionnaire, Non-collusion Affidavit of Prime Bidder, Certification Regarding Lobbying and Disclosure of Lobbying Activities, Proposed Contract Breakdown, Certificate of Recovered Materials, and the Statement of the Bidder’s Qualifications, shall be sealed in an envelope and clearly labeled with the words "Bid Documents”, the project’s contract number, name of bidder and the date and time of bid opening.
d. The City/County may consider as irregular any bid on which there is an alteration of or departure from the bid form and, at its option, may reject any irregular bid.
e. If a contract is awarded, it will be awarded to a responsible bidder on the basis of the lowest/best bid and the selected alternate bid items, if any. The contract will require the completion of the work in accordance with the contract documents.
6. Bid Modifications Prior to Bid Opening
a. Any bidder may modify its bid by submitting a modification or supplemental bid at any time prior to the scheduled closing time for receipt of bids, provided such modification or supplemental bid is received by the City/County prior to the closing time. The modification or supplemental bid should not reveal the original bid price but should provide only the addition, subtractions or other modifications to the original bid so that the final prices or terms will not be known by the City/County until the sealed bid is open.
7. Bid Bond
a. A bid bond in the amount of 5% of the bid issued by an acceptable surety shall be submitted with each bid [for contracts greater than $100,000]. A certified check or bank draft payable to the City/County or negotiable U.S. Government Bonds (as par value) may be submitted in lieu of the Bid Bond.
b. The bid bond or its comparable, will be returned to the bidder as soon as practical after the opening of the bids.
8. Statement of Bidders Qualifications
Each bidder shall submit on the form furnished for that purpose a statement of the bidder's qualifications. The City/County shall have the right to take such steps as it deems necessary to determine the ability of the bidder to perform its obligations under the contract, and the bidder shall furnish the City/County all such information and data for this purpose as it may request. The right is reserved to reject any bid where an investigation of the available data does not satisfy the City/County that the bidder is qualified to carry out properly the terms of the contract.
9. Unit Price
The unit price for each of the several items in the bid shall include its pro rata share of overhead so that the sum of the products obtained by multiplying the quantity shown for each item by the unit price bid represents the total bid. Any bid not conforming to this requirement may be rejected as informal. Special attention is drawn to this condition, as the unit prices will be used to determine the amount of any change orders resulting from an increase or decrease in quantities.
10. Corrections:
Erasures or other corrections in the bid must be noted over the signature of the bidder.
11. Time for Receiving Bids
Bids received prior to the advertised hour of opening shall be kept securely sealed. The officer appointed to open the bids shall decide when the specified time has arrived and no bid received thereafter will be considered; except that when a bid arrives by mail after the time fixed for opening, but before the reading of all other bids is completed, and it is shown to the satisfaction of the City/County that the late arrival of the bid was solely due to delay in the mail for which the bidder was not responsible, such bid will be received and considered.
12. Opening of Bids
The City/County shall, at the time and place fixed for the opening of bids, open each bid and publicly read it aloud, irrespective of any irregularities therein. Bidders and other interested individuals may be present.
13. Withdrawal of Bids
Bidder may withdraw the bid before the time fixed for the opening of bids, by communicating its purpose in writing to the City/County. Upon receipt of such notice, the unopened bid will be returned to the bidder. The bid guaranty of any bidder withdrawing his bid will be returned promptly.
14. Award of Contract/Rejection of Bids
a. The contract will be awarded to the responsive, responsible Bidder submitting the lowest/best bid. The bidder selected will be notified at the earliest possible date. The City/County reserves the right to reject any or all bids and to waive any informality in bids received where such rejection or waiver is in its interest.
b. The City/County reserves the right to consider as unqualified to do the work any bidder who does not habitually perform with his own forces the major portions of the work involved in construction of the improvements embraced in this contract.
15. Execution of Agreement/Performance and Payment Bonds
a. Performance Bonds - Requires all prime contractors which enter into a formal contract in excess of $100,000 with the State, a county, or a municipality; a department, board, or agency of the state, a county, or a municipality; and a school district or a subdivision thereof, to obtain a Performance Bond in the amount of the contract before commencing with work
b. Payment Bonds- Requires all prime contractors which enter into a formal contract with the State, a county, or a municipality; a department, board, or agency of the state, a county, or a municipality; and a school district or a subdivision thereof, to furnish to the governmental entity a payment bond in the amount of the contract. The payment bond must be filed within 30 days from the date of the Notice of Award:
▪ Municipalities: If the contract is in excess of $50,000, a payment bond is required.
▪ Counties: If the contract is in excess of $25,000, a payment bond is required.
c. The failure of the successful bidder to execute the agreement and supply the required bonds within thirty
(30) days from the date of the notice of award-or within such extended period as the City/County may grant, shall constitute a default and the City/County may, at its option either award the contract to the next lowest responsible bidder, or re-advertise for bids. In either case, the City/County may charge against the bidder the difference between the amount of the bid, and the amount for which a contract is subsequently executed irrespective of whether this difference exceeds the amount of the bid bond. If a more favorable bid is received through re-advertisement, the defaulting bidder shall have no claim against the City/County for a refund.
16. Wages and Salaries
Attention is particularly called to the requirement of paying not less than the prevailing Davis Bacon Related Acts (DBRA) wage rates specified in the Contract Documents. These rates are minimums to be paid during the life of the contract. It is therefore the responsibility of the Bidder to inform themselves as to local labor conditions.
17. Equal Employment Opportunity
Attention is called to the requirements for ensuring that employees and applicants for employment are not discriminated against because of race, color, religion, sex, sexual orientation, gender identity, or national origin, and other civil rights requirements.
18. Certification Regarding Lobbying
Contractors who apply or bid for an award of $100,000 or more shall provide the required certification that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer of employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 USC § 1352.
19. System for Award Management (SAM)
All contractors and subcontractors must be searched on www.sam.gov and cleared (not suspended or debarred) prior to any formal action authorizing the award of a contract to the contractor.
CONSTRUCTION CONTRACT
THIS AGREEMENT made this the _____________ day of _______________________, ___________, by and between ____________________________ (a corporation organized and existing under the laws of the State of _____________) (a partnership consisting of _______________) (an individual trading as _______________________) hereinafter called the “Contractor”, and the City of Plantersville hereinafter called the “City/County.”
WITNESSETH, that the Contractor and the City/County for the considerations stated herein mutually agree as follows:
ARTICLE 1. Statement of Work. The Contractor shall furnish all supervision, technical personnel, labor, materials, machinery, tools, equipment and services, including utility and transportation services, and perform and complete all work required for the construction of the Improvements embraced in the Project; namely, paving for the Community Development Block Grant – Mitigation (CDBG- DR) project, all in strict accordance with the contract documents including all addenda thereto, numbered __________________, dated ___________ and _________, all as prepared by Bleyl Engineering acting and in these contract documents preparation, referred to as the “Engineer”.
ARTICLE 2. The Contract Price. The City/County will pay the Contractor for the performance of the Contract in current funds, for the total quantities of work performed at the unit prices stipulated in the Bid for the several respective items of work completed subject to additions and deductions as provided in______________________________ hereof.
ARTICLE 3. The Contract. The executed contract documents shall consist of the following components:
a. This Agreement (pgs. 1-2) f. General Conditions, Part I
b. Addenda g. Special Conditions
c. Invitation for Bids h. Technical Specifications
d. Instructions to Bidders i. Drawings
e. Signed Copy of Bid j. [Add any applicable documents]
ARTICLE 4. Performance. Work, in accordance with the Contract dated __________________________, ____________, shall commence on or before _______________________________, ______________, and Contractor shall complete the
WORK within ninety (90) consecutive calendar days thereafter. The date of completion of all WORK is therefore
This Agreement, together with other documents enumerated in this ARTICLE 3, which said other documents are as fully a part of the Contract as if hereto attached or herein repeated, forms the Contract between the parties hereto. In the event that any provision in any component part of this Contract conflicts with any provision of any other component part, the provision of the component part first enumerated in this ARTICLE 3 shall govern, except as otherwise specifically stated.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed in triplicate original copies on the day and year first above written.
(The Contractor)
By _____________________________________
Title _____________________________________
City of Plantersvile
(City/County)
By _____________________________________
Title _____________________________________
Corporate Certifications
I, ______________________________, certify that I am the _________________ of the corporation named as Contractor herein; that ___________________________ who signed this Agreement on behalf of the Contractor, was then ___________________________ of said corporation; that said Agreement was duly signed for and in behalf of said corporation by authority of its governing body, and is within the scope of its corporate powers.
Corporate ________________________________
Seal (Corporate Secretary)
GENERAL CONDITIONS - PART I
FOR CONSTRUCTION
1. Contract and Contract Documents
a. The project to be constructed pursuant to this contract will be financed with assistance from the General Land Office (GLO) through the Community Development Block Grant – Mitigation (CDBG-MIT) fund and is subject to all applicable Federal and State laws and regulations.
b. The Plans, Specifications and Addenda shall form part of this contract and the provisions thereof shall be binding upon the parties as if they were herein fully set forth.
2. Definitions
Whenever used in any of the Contract Documents, the following meanings shall be given to the terms here in defined:
(a) The term "Contract" means the Contract executed between the City of Plantersville, hereinafter called the “City/County” and ____________________________________________, hereinafter called “Contractor”, of which these GENERAL CONDITIONS, form a part.
(b) The term "Project Area" means the area within the specified Contract limits of the Improvements contemplated to be constructed in whole or in part under this contract.
(c) The term "Engineer" means Bleyl Engineering, Engineer in charge, serving the City/County with architectural or engineering services, his successor, or any other person or persons, employed by the City/County for the purpose of directing or having in charge the work embraced in this Contract.
(d) The term "Contract Documents" means and shall include the following: Executed Contract, Addenda (if any), Invitation for Bids, Instructions to Bidders, Signed Copy of Bid, General Conditions, Special Conditions, Technical Specifications, and Drawings (as listed in the Schedule of Drawings).
3. Supervision By Contractor
(a) Except where the Contractor is an individual and personally supervises the work, the Contractor shall provide a competent superintendent, satisfactory to the Engineer, on the work at all times during working hours with full authority to act as Contractor’s agent. The Contractor shall also provide adequate staff for the proper coordination and expediting of his work.
(b) The Contractor shall be responsible for all work executed under the Contract. Contractor shall verify all figures and elevations before proceeding with the work and will be held responsible for any error resulting from his failure to do so.
4. Subcontracts
(a) The Contractor shall not execute an agreement with any subcontractor or permit any subcontractor to perform any work included in this contract until Contractor has verified the subcontractor has been cleared (not suspended or debarred) to participate in federally funded contracts.
(b) No proposed subcontractor shall be disapproved by the City/County except for cause.
(c) The Contractor shall be as fully responsible to the City/County for the acts and omissions of his subcontractors, and of persons either directly or indirectly employed by them.
(d) The Contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the work and required compliance by each subcontractor with the applicable provisions of the Contract.
(e) Nothing contained in the Contract shall create any contractual relation between any subcontractor and the City/County.
(f) Contractors are encouraged to subcontract with Minority Business Enterprises, Small Business Enterprises, Women Business Enterprises, and labor surplus area firms.
5. Fitting and Coordination of Work
The Contractor shall be responsible for the proper fitting of all work and for the coordination of the operations of all trades, subcontractors, or material suppliers engaged upon this Contract.
6. Payments to Contractor
(a) Partial Payments
1) The Contractor shall prepare the requisition for partial payment as of the last day of the month and submit it, with the required number of copies, to the Engineer for approval. The amount of the payment due the Contractor shall be determined by adding to the total value of work completed to date, the value of materials properly stored on the site and deducting (1) ten percent (10%) of the total amount, to be retained until final payment, and (2) the amount of all previous payments. The total value of work completed to date shall be based on the estimated quantities of work completed and on the unit prices contained in the agreement. The value of materials properly stored on the site shall be based upon the estimated quantities of such materials and the invoice prices. Copies of all invoices shall be available for inspection of the Engineer.
2) Monthly or partial payments made by the City/County to the Contractor are advanced for the purpose of assisting the contractor to expedite the work of construction. The Contractor shall be responsible for the care and protection of all materials and work upon which payments have been made until final acceptance of such work and materials by the City/County. Such payments shall not constitute a waiver of the right of the City/County to require the fulfillment of all terms of the Contract and the delivery of all improvements embraced in this Contract complete and satisfactory to the City/County in all details.
(b) Final Payment
1) After final inspection and the acceptance by the City/County of all work under the Contract, the Contractor shall prepare the requisition for final payment which shall be based upon the careful inspection of each item of work at the applicable unit prices stipulated in the Contract. The total amount of the final payment due the Contractor under this Contract shall be the amount computed as described above less all previous payments.
2) Before paying the final estimate, City/County shall require the Contractor to furnish releases or receipts from all subcontractors having performed any work and all persons having supplied materials, equipment (installed on the Project) and services to the Contractor. The City/County may make payment in part or in full to the Contractor without requiring the furnishing of such releases or receipts and any payments made shall in no way impair the obligations of any surety or sureties furnished under this Contract.
3) Any amount due the City/County under Liquidated Damages, shall be deducted from the final payment due the contractor.
(c) Payments Subject to Submission of Certificates
Each payment to the Contractor by the City/County shall be made subject to submission by the Contractor of all written certifications required of it and its subcontractors.
(d) Withholding Payments
The City/County may withhold any payment due the Contractor as deemed necessary to protect the City/County, and if so elects, may also withhold any amounts due from the Contractor to any subcontractors or material dealers, for work performed or material furnished by them. The foregoing provisions shall be construed solely for the benefit of the City/County and will not require the City/County to determine or adjust any claims or disputes between the Contractor and its subcontractors or material dealers, or to withhold any moneys for their protection unless the City/County elects to do so. The failure or refusal of the City/County to withhold any moneys from the Contractor shall in no way impair the obligations of any surety or sureties under any bond or bonds furnished under this Contract.
7. Changes in the Work
(a) The City/County may make changes in the scope of work required to be performed by the Contractor under the Contract without relieving or releasing the Contractor from any obligations under the Contract or any guarantee given pursuant to the Contract provisions, and without affecting the validity of the guaranty bonds, and without relieving or releasing the surety or sureties of said bonds. All such work shall be executed under the terms of the original Contract unless it is expressly provided otherwise. Additionally, all such change orders must be approved by CDBG-MIT prior to execution of same.
(b) Except for the purpose of affording protection against any emergency endangering health, life, limb or property, the Contractor shall make no change in the materials used or in the specified manner of constructing and/or installing the improvements or supply additional labor, services or materials beyond that actually required for the execution of the Contract, unless in pursuance of a written order from the City/County authorizing the Contractor to proceed with the change. No claim for an adjustment of the Contract Price will be valid unless so ordered.
(c) If applicable unit prices are contained in the Contract, the City/County may order the Contractor to proceed with desired unit prices specified in the Contract; provided that in case of a unit price contract the net value of all changes does not increase the original total amount of the agreement by more than twenty-five percent (25%) or decrease the original total amount by more than twenty-five percent (25%) for municipalities and eighteen percent (18%) for counties without the written consent of the contractor. [Texas Local Government Code Section 252.048(d) and Section 262.031(b)]
(d) Each change order shall include in its final form:
1) A detailed description of the change in the work.
2) The Contractor's proposal (if any) or a confirmed copy thereof.
3) A definite statement as to the resulting change in the contract price and/or time.
4) The statement that all work involved in the change shall be performed in accordance with contract requirements except as modified by the change order.
5) The procedures as outlined in this Section for a unit price contract also apply in any lump sum contract.
8. Claims for Extra Cost
(a) If the Contractor claims that any instructions by Drawings or otherwise involve extra cost or extension of time, he shall, within ten days after the receipt of such instructions, and in any event before proceeding to execute the work, submit his protest thereto in writing to the City/County, stating clearly and in detail the basis of his objections. No such claim will be considered unless so made.
(b) Claims for additional compensation for extra work, due to alleged errors in ground elevations, contour lines, or bench marks, will not be recognized unless accompanied by certified survey data, made prior to the time the original ground was disturbed, clearly showing that errors exist which resulted, or would result, in handling more material, or performing more work, than would be reasonably estimated from the Drawings and maps issued.
(c) Any discrepancies which may be discovered between actual conditions and those represented by the Drawings and maps shall be reported at once to the City/County and work shall not proceed except at the Contractor's risk, until written instructions have been received from the City/County.
(d) If, on the basis of the available evidence, the City/County determines that an adjustment of the Contract Price and/or time is justifiable, a change order shall be executed.
9. Termination, Delays, and Liquidated Damages
Right of the City/County to Terminate Contract for Convenience
City/County may at any time and for any reason terminate Contractor’s services and work at City/County's convenience upon providing written notice to the Contractor specifying the extent of termination and the effective date. Upon receipt of such notice, Contractor shall, unless the notice directs otherwise, immediately discontinue the work and placing of orders for materials, facilities and supplies in connection with the performance of this Agreement.
Upon such termination, Contractor shall be entitled to payment only as follows: (1) the actual cost of the work completed in conformity with this Agreement plus (2) such other costs actually incurred by Contractor as are permitted by the prime contract and approved by City/County. There shall be deducted from such sums as provided in this subparagraph the amount of any payments made to Contractor prior to the date of the termination of this Agreement. Contractor shall not be entitled to any claim or claim of lien against City/County for any additional compensation or damages in the event of such termination and payment.
Right of the City/County to Terminate Contract for Cause
If the Contractor fails to fulfill in a timely and proper manner its obligations under this Agreement, or if the Contractor violates any of the covenants, conditions, agreements, or stipulations of this Agreement, the City/County shall have the right to terminate this Agreement by giving written notice to the Contractor of such termination and specifying the effective date thereof, which shall be at least five days before the effective date of such termination. In the event of termination for cause, all finished or unfinished documents, data, studies, surveys, drawings, maps, models, photographs and reports prepared by the Contractor pursuant to this Agreement shall, at the option of the City/County, be turned over to the City / County and become the property of the City / County. In the event of termination for cause, the Contractor shall be entitled to receive reasonable compensation for any necessary services actually and satisfactorily performed prior to the date of termination.
Notwithstanding the above, the Contractor shall not be relieved of liability to the City/County for damages sustained by the City/County by virtue of any breach of contract by the Contractor, and the City/County may set-off the damages it incurred as a result of the Contractor’s breach of contract from any amounts it might otherwise owe the Contractor. 2 CFR
200 APPENDIX II(B)
(a) Liquidated Damages for Delays.
If the work is not completed within the time stipulated in the applicable bid for Lump Sum or Unit Price Contract provided, the Contractor shall pay to the City/County as fixed, agreed, and liquidated damages (it being impossible to determine the actual damages occasioned by the delay) the amount of $250.00 for each calendar day of delay, until the work is completed. The Contractor and Contractor’s sureties shall be liable to the City/County for the amount thereof.
(b) Excusable Delays.
1) The right of the Contractor to proceed shall not be terminated nor shall the Contractor be charged with liquidated damages for any delays in the completion of the work due to:
2) Any acts of the Government, including controls or restrictions upon or requisitioning of materials, equipment, tools, or labor by reason of war, national defense, or any other national emergency;
3) Any acts of the City/County;
4) Causes not reasonably foreseeable by the parties to this Contract at the time of execution which are beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, terrorism, war, acts of another Contractor in the performance of some other contract with the City/County, fires, floods, epidemics, quarantine, restrictions, strikes, freight embargoes, and weather of unusual severity such as hurricanes, tornadoes, cyclones and other extreme weather conditions.
5) Provided, however, that the Contractor promptly notifies the City/County within ten (10) days in writing of the cause of the delay. Upon receipt of such notification, the City/County shall ascertain the facts and the cause and extent of delay. If, upon the basis of the facts and the terms of this contract, the delay is properly excusable, the City/County shall extend the time for completing the work for a period of time commensurate with the period of excusable delay.
10. Assignment or Novation
The Contractor shall not assign nor transfer, whether by assignment or novation, any of its rights, duties, benefits, obligations, liabilities, or responsibilities under this Contract without the written consent of the City/County. No assignment or novation of this Contract shall be valid unless the assignment or novation expressly provides that the assignment of any of the Contractor's rights or benefits under the Contract is subject to a prior lien for labor performed, services rendered, and materials, tools, and equipment supplied for the performance of the work under this Contract in favor of all persons, Contractors, or corporations rendering such labor or services or supplying such materials, tools, or equipment.
11. Technical Specifications and Drawings
Anything mentioned in the Technical Specifications and not shown on the Drawings or vice versa, shall be of like effect as if shown on or mentioned in both. In case of difference between Drawings and Technical Specifications, the Technical Specifications shall govern. In case of any discrepancy in Drawings, or Technical Specifications, the matter shall be immediately submitted to the City/County for review. Contractor shall be liable for any issues or expenses in the event the discrepancy is not submitted to the City/County.
12. Shop Drawings
(a) All required shop drawings, machinery details, layout drawings, etc. shall be submitted to the Engineer in electronic copies for approval sufficiently in advance of requirements to afford ample time for checking, including time for correcting, resubmitting and rechecking if necessary. The Contractor may proceed, only at Contractor’s own risk, with manufacture or installation of any equipment or work covered by said shop drawings, etc. until they are approved and no claim, by the Contractor, for extension of the contract time shall be granted by reason of his failure in this respect.
(b) Any drawings submitted without the Contractor's stamp of approval will not be considered and will be returned to him for proper resubmission. If any drawings show variations from the requirements of the Contract because of standard shop practice or other reason, the Contractor shall make specific mention of such variation in his letter of transmittal in order that, if acceptable, suitable action may be taken for proper adjustment of contract price and/or time, otherwise the Contractor will not be relieved of the responsibility for executing the work in accordance with the Contract even though the drawings have been approved.
(c) If a shop drawing is in accordance with the contract or involves only minor adjustment in the interest of the City/County not involving a change in contract price or time, the engineer may approve the drawing. The approval shall not relieve the Contractor from responsibility to adhere to the contract or for any error in the drawing.
13. Requests for Supplementary Information
It shall be the responsibility of the Contractor to make timely requests of the City/County for any additional information which should be furnished by the City/County under the terms of this Contract, and which is required in the planning and execution of the work. Such requests may be submitted from time to time as the need approaches, but each shall be filed in ample time to permit appropriate action to be taken by all parties involved so as to avoid delay. Each request shall be in writing, and list the various items and the latest date by which each will be required by the Contractor. The first list shall be submitted within two weeks after Contract award and shall be as complete as possible at that time. The Contractor shall, if requested, furnish promptly any assistance and information the Engineer may require in responding to these requests of the Contractor. The Contractor shall be fully responsible for any delay in his work or to others arising from his failure to comply fully with the provision of this section.
14. Materials and Workmanship
(a) Unless otherwise specifically provided for in the technical specifications, all workmanship, equipment, materials and articles incorporated in the work shall be new and the best grade of the respective kinds for the purpose. Where equipment, materials, articles or workmanship are referred to in the technical specifications as "equal to" any particular standard, the Engineer shall decide the question of equality.
(b) The Contractor shall furnish to the City/County for approval the manufacturer's detailed specifications for all machinery, mechanical and other special equipment, which he contemplates installing together with full information as to type, performance characteristics, and all other pertinent information as required, and shall likewise submit for approval full information concerning all other materials or articles which he proposes to incorporate.
(c) Machinery, mechanical and other equipment, materials or articles installed or used without such prior approval shall be at the risk of subsequent rejection.
(d) Materials specified by reference to the number or symbol of a specific standard, shall comply with requirements in the latest revision thereof and any amendment or supplement thereto in effect on the date of the Invitation for Bids, except as limited to type, class or grade, or modified in the technical specifications shall have full force and effect as though printed therein.
(e) The City/County may require the Contractor to dismiss from the work such employee or employees as the City/County or the Engineer may deem unqualified.
15. Samples, Certificates and Tests
(a) The Contractor shall submit all material or equipment samples, certificates, affidavits, etc., as called for in the contract documents or required by the Engineer, promptly after award of the contract and acceptance of the Contractor's bond.
No such material or equipment shall be manufactured or delivered to the site, except at the Contractor's own risk, until the required samples or certificates have been approved in writing by the Engineer. Any delay in the work caused by late or improper submission of samples or certificates for approval shall not be considered just cause for an extension of the contract time.
(b) Each sample submitted by the Contractor shall carry a label giving the name of the Contractor, the project for which it is intended, and the name of the producer. The accompanying certificate or letter from the Contractor shall state that the sample complies with contract requirements, shall give the name and brand of the product, its place of origin, the name and address of the producer and all specifications or other detailed information which will assist the Engineer in making a prompt decision regarding the acceptability of the sample. It shall also include the statement that all materials or equipment furnished for use in the project will comply with the samples and/or certified statements.
(c) Approval of any materials shall be general only and shall not constitute a waiver of the City/County's right to demand full compliance with Contract requirements. After actual deliveries, the Engineer will have such check tests made as he deems necessary in each instance and may reject materials and equipment and accessories for cause, even though such materials and articles have been given general approval. If materials, equipment or accessories which fail to meet check tests have been incorporated in the work, the Engineer will have the right to cause their removal and replacement by proper materials or to demand and secure such reparation by the Contractor as is equitable.
(d) Except as otherwise specifically stated in the Contract, the costs of sampling and testing will be divided as follows:
1) The Contractor shall furnish without extra cost, including packing and delivery charges, all samples required for testing purposes, except those samples taken on the project by the Engineer;
2) The Contractor shall assume all costs of re-testing materials which fail to meet contract requirements;
3) The Contractor shall assume all costs of testing materials offered in substitution for those found deficient;
4) The City/County will pay all other expenses.
16. Permits and Codes
(a) The Contractor shall give all notices required by and comply with all applicable federal and state laws, ordinances, and codes of the Local Government. All construction work and/or utility installations shall comply with all applicable ordinances, and codes including all written waivers. Before installing any work, the Contractor shall examine the drawings and technical specifications for compliance with applicable ordinances and codes and shall immediately report any discrepancy to the City/County. Where the requirements of the drawings and technical specifications fail to comply with such applicable ordinances or codes, the City/County will adjust the Contract by Change Order to conform to such ordinances or codes (unless waivers in writing covering the difference have been granted by the governing body or department) and make appropriate adjustment in the Contract Price or stipulated unit prices.
(b) Should the Contractor fail to observe the foregoing provisions and proceed with the construction and/or install any utility at variance with any applicable ordinance or code, including any written waivers (notwithstanding the fact that such installation is in compliance with the drawings and technical specifications), the Contractor shall remove such work without cost to the City/County.
(c) The Contractor shall at his own expense, secure and pay for all permits for street pavement, sidewalks, shed, removal of abandoned water taps, sealing of house connection drains, pavement cuts, buildings, electrical, plumbing, water, gas and sewer permits required by the local regulatory body or any of its agencies.
(d) The Contractor shall comply with applicable local laws and ordinances governing the disposal of surplus excavation, materials, debris and rubbish on or off the Project Area and commit no trespass on any public or private property in any operation due to or connected with the…