This document contains a federal contract opportunity notice and supporting project information form. The Naval Facilities Engineering Systems Command, Mid-Atlantic is seeking small businesses capable of performing a renovation project at Building 79 of the Portsmouth Naval Shipyard in Kittery, Maine. The project scope involves replacing mechanical systems on the second and third floors, including a new steam to hot water plant, HVAC system, and controls. Interested small businesses are requested to submit a capabilities package using the attached project information form to document two to five relevant past construction projects of similar size, scope and complexity, specifically those over $10 million involving renovation of a historic government building and replacement of HVAC, electrical and plumbing systems. Responses must be submitted electronically by February 2, 2023. Upon review, the government will determine if a small business set-aside is appropriate for this acquisition.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Project Matrix 23R2602.xlsx | XLSX spreadsheet | |
| Contractor Information Form 23R2602.docx | DOCX document | |
| 23R2602 Sources Sought Notice.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOURCES SOUGHT – PROJECT INFORMATION FORM
Use this form (one per project) to provide supporting information that demonstrates project experience relevant to the subject announcement. Submit up to five (5) projects. Please limit response to two pages per project.
| 1. |
| Contractor Name: |
| 2. | ||||
| Project No. (check one): | ||||
| |_| 1 | |_| 2 | |_| 3 | |_| 4 | |_| 5 |
| 3. |
| Contract Number: |
| Delivery/Task Order No.: |
| Project Number: |
| Title: |
| Location: |
| 4. |
| Award Date (mm/dd/yy): |
| 5. |
| Final Contract Price: |
| $ |
| Completion Date (mm/dd/yy): |
| (includes all options and mods) |
| Project is % complete (as of submission due date) |
| This is the |_| total project |_| subcontract price. |
| 6. | ||
| Type of work: | ||
| |_| New Construction | |_| Repair | |_| Renovation |
| 7. |
| Customer/Owner Name: |
| Point of Contact Name/Title: (person with project knowledge) |
| POC Phone Number: |
| POC Email Address: |
| 8. | |
| Were you the Prime contractor for this project? | |
| |_| Yes | |_| No |
| Were you a subcontractor for this project? | |
| |_| Yes | |_| No |
| If subcontractor, who was the Prime contractor? |
| 9. |
| Type of Contract (check all that apply): |
|_| Design-Build |_| Design-Bid-Build (fully designed project)
| |_| Other (explain): |
| If Design-Build, provide the following information: |
| |_| Design accomplished in-house |
| Lead design firm name: |
| Years working together: |
| Address: |
10. Provide a detailed description of the project:
11. Percentage of work you self-performed on this project: %.
Provide a detailed description of the work your firm self-performed on this project:
Form may be expanded. Please DO NOT change content of the form