RFQ East Athletic Village Tennis, Track & Field Facilities
Solicitation number
DB 102440
Issued by
Maricopa County, Tucson City, Arizona

About this file

This is a Project Information and Scope of Services document issued by Arizona State University (ASU) for a Design-Build Request for Qualifications (RFQ) to construct new NCAA regulation outdoor tennis courts and track and field facilities at the ASU Tempe campus East Athletic Village. The project encompasses construction of eight NCAA intercollegiate-grade outdoor tennis courts with broadcast-level lighting and grandstands; an eight-lane 400-meter competition track with field event areas, natural turf surfaces, and approximately 2,500-seat grandstands; associated parking, utilities, restroom and concession facilities; and off-site half-street and sewer line improvements on 3rd Street. The Design-Build Team Selection is scheduled for January 2027, with programming and schematic design commencing May 2027, design development completion by August 2027, guaranteed maximum price (GMP) negotiation at 100 percent design development by October 2027, construction documents and permitting by December 2027, construction start in January 2028, and substantial completion by June 2028. The two-year warranty term extends through June 2030. Proposers must be appropriately licensed and registered in Arizona and may include pre-selected specialty consultants in telecommunications, landscape architecture, surveying, geotechnical, civil, structural engineering, and cost estimation disciplines.

The estimated construction budget is $43,350,000 with a total estimated project budget of $51,000,000. ASU has implemented a progressive fee schedule for preconstruction and construction phase fees as well as General Conditions/General Requirements, calculated using a Project Complexity Coefficient that considers delivery method, new versus renovation scope, project scope, location, and schedule. Preconstruction fees are intentionally set above typical market benchmarks to ensure adequate contractor resources and expertise for rigorous planning, scheduling, and budgeting. Construction phase fees align with prevailing market benchmarks. The project must comply with ASU Project Guidelines, applicable state and local codes, the ASU Masterplan, Novus Innovation Corridor Master Plan and Design Standards, ABOR Construction Cost Control and Professional Fee Guidelines, NCAA Championship Administration rules, NCAA Best Lighting Practices, the International Tennis Association Rule Book 2025-2026 edition, and the NCAA Track and Field and Cross Country Rules Book 2026 edition. LEED Gold certification is required no later than 12 months following substantial completion. The project requires Arizona Board of Regents (ABOR) approval and Joint Committee for Cancer Research (JCCR) approval before construction may commence.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Description

Arizona State University (ASU) extends an invitation to interested and qualified Design-Build Teams to submit their statement of qualifications to provide Design Build Services for a project that includes a new Track and Field Facility and a new Tennis Facility located on the Tempe campus.

Project Information and Scope of Services

The successful Design-Build Team in this selection will be able to provide services at ASU’s discretion for renovation/modification projects, related to this project as described below, for the duration of the warranty period of two years after substantial completion.

1. Site Description

a. The facility will be located within the ASU East Athletic Village, South of Rio Salado Parkway and East of Rural Road. The Site for the new facilities is northeast of the current ASU football practice bubble per the site map.

b. Site map.

2. Project Description

a. This project will be for the construction of new NCAA regulation outdoor tennis courts, track and field facilities and venues, including off-site utilities and right-of-way improvements, on-site grading, drainage, utility and infrastructure improvements, a parking lot and common areas to accommodate the relocation of the Sun Devil tennis and track and field programs to the East Athletic Village within the Novus Innovation Corridor.

b. The new track and field and tennis facilities will include the following:

● Construction of 8 NCAA intercollegiate grade outdoor post tension concrete, acrylic surface and regulation striped tennis courts with net posts, nets, anchors and court accessories. broadcast level lighting, chain link fencing, wind screens and gates, grandstands, and fiber optic network capability for broadcasting of events.

● Tennis venue construction shall comply with the International Tennis Association Rule Book 2025-2026 edition.

● Construction of an NCAA intercollegiate grade 8-lane 400-meter competition track and field competition venue with long and triple jump, pole vault, high jump and steeplechase facilities; a separate throws area for shot put, discus, hammer and javelin; and competition equipment and fully automatic timing infrastructure

● Running track and other competition surfaces shall have Mondo synthetic running track surface for outdoor use (or approved equal).

● Track field and throws area will be natural turf installed per NCAA regulations for grade and slope.

● Track and Field venue construction shall comply with NCAA Track and Field and Cross- Country Rules Book 2026 edition.

● Track and field grandstands shall provide bleacher seating for approximately 2,500 people with a press box, broadcast level lighting, competition scoreboard, and fiber optic network for broadcasting of events.

● Tennis, track and field venues shall have broadcast capabilities and fiberoptic network connectivity. Provide production truck compound area with power and network connection venue infrastructure. Provide pre-routed single-mode fiber optic cabling at venues for plug-and-play capability for remote production (REMI model broadcasts)

● Venues and common areas to have wireless internet connectivity for public (non-broadcast) use.

● Preparation of all base and sub-base courses for installation of various venues.

● Fencing, gates, service access and ADA routes.

● Site grading and drainage, on-site venue infrastructure and utilities and site landscaping and hardscaping.

● Provide bus drop-off area for visiting teams.

● Parking lot (paved) for 180 cars with lighting, blue-light system and associated landscaping.

● Installation of offsite half street right-of-way improvements and sewer line for 3rd

Street along the ASU property

● Restroom, concession facilities and arrival plaza.

● Design, construction documents, special inspections, commissioning, surveying, geotechnical work.

● Project options to be included in the project site plan for possible inclusion into the project: 4 additional NCAA tennis courts, shade structures at tennis and track and field venues, locker room facilities for home and visiting athletes.

● Half street and sewer line installation improvements are assumed from Dorsey Lane to the Track and Field parking area as depicted below.

● Existing on-site utilities may require an assessment for possible expansion to support the new facilities.

c. Proposed Site Improvement Areas:

d. The above description of the proposed services provides a brief overview and is not a comprehensive outline of the project’s full scope of work. Prospective proposers are strongly encouraged to submit questions to Procurement through the Questions and Answer Board within the SunRISE/Jaggaer electronic bidding portal and attend the scheduled Pre-Submittal for more detailed information.

e. ASU intends to award this contract to a single firm. ASU, at its sole discretion, reserves the right to terminate this contract in full, without any further obligation, if officials determine that it is an unsatisfactory instrument to move the project forward. ASU also reserves the right to contract with a separate entity.

f. This project will be built in accordance with:

● ASU Project Guidelines

● Applicable state and local codes

● ASU Masterplan

● Novus Innovation Corridor Master Plan & Design Standards (Exhibit A)

● ABOR Construction Cost Control and Professional Fee Guidelines

● NCAA Championship Administration

● NCAA Best Lighting Practices

● International Tennis Association Rule Book 2025-2026 edition

● NCA Track and Field and cross Country Rules Book 2026 edition

● ASU as the Authority Having Jurisdiction (AHJ)

3. Estimated Project Budget

Estimated Construction Budget $43,350,000 Estimated Project Budget $51,000,000

4. Progressive Fee Schedule

a. ASU has implemented a fee schedule to establish consistency, transparency, and alignment with market conditions across all project delivery methods.

b. Preconstruction and Construction phase fees, as well as General Conditions/ General

Requirements (GC/GRs) are calculated with a Progressive Fee Schedule.

c. ASU intends to apply fees within the ranges shown below.

d. Final project fees will be established using a Project Complexity Coefficient, considering the factors listed below.

● Delivery Method (DB, CMAR) https://cfo.asu.edu/design-professionals https://cfo.asu.edu/campus-planning http://www.azregents.edu/sites/default/files/reports/Cost-Control-Guidelines-ALL.pdf https://www.ncaa.org/sports/2021/2/8/membership-championships-administration.aspx https://www.ncaa.com/news/ncaa/article/2013-11-21/ncaa-best-lighting-practices https://www.itftennis.com/en/about-us/governance/rules-and-regulations/ https://ncaapublications.com/

● New vs Renovation

● Project Scope

● Project Location

● Project Schedule

e. Preconstruction Fees have been intentionally set higher than typical market benchmarks to ensure the contractor devotes the appropriate resources, expertise, and time necessary to rigorously plan, schedule, and budget the project. ASU views this investment as critical to achieving cost certainty at GMP and minimizing risk during construction.

f. Construction Phase Fees are aligned with prevailing market benchmarks and are applied consistently to ensure equitable treatment of all proposers.

g. GC/GRs may be reviewed and refined on a project-specific basis, subject to Owner approval. While the maximum GC/GRs percentage remains in effect, ASU may consider adjustments to the composition of GC/GRs where appropriate.

h. Certain high-cost items may be evaluated to determine whether they are more appropriately a direct cost line item within the Schedule of Values rather than embedded within GC/GRs.

i. These fees may be recalculated if there is a significant change order as required by the

Owner.

5. Estimated Project Schedule

a. Capital projects with an estimated total project cost of $10 million or more require approval from the Arizona Board of Regents (ABOR). This approval is required on projects for new construction, renovations, and major infrastructure improvements at ASU, NAU, and UA. Projects with an estimated total cost under $10 million require only university level approval.

b. Before the construction phase on this project may begin, an Individual Project Approval (IPA) from ABOR and a separate approval from JCCR will be required. The project may be delayed due to these approval processes.

Design-Build Team Selection January 2027

ABOR ACP Project Approval Sept 2027

Programming & Schematic Design Start May 2027

Design Development Aug 2027

GMP @ 100% Design Development Oct 2027

Contract Documents / Permitting Dec 2027

Construction Start Jan 2028

Commissioning Complete July 2028

Substantial Completion June 2028

Client Move-in Complete July 2028

Construction Complete July 2028

Project Closeout Oct 2028

Two-Year Warranty Term Complete June 2030

6. Scope of Services

a. Design Stages. The design portion shall follow a conceptual design, schematic design, design development, and construction document process. This design portion shall be provided for Owner review and written approval. The design shall be inclusive and will require architectural, structural, civil, MEP systems, and fire protection if necessary.

b. Design Consultants. The Design-Build Team shall provide all design and construction services necessary to complete the requirements outlined under the project. The Design-Builder may deem it necessary to bring consultants into the organization to provide all services.

c. System Design. The System Design must comply with ASU Project Guidelines.

d. For all new buildings and major renovations, if the Project satisfies the applicable LEED Minimum Program Requirements established by the U.S. Green Building Council (USGBC), the Project shall obtain LEED certification. Consistent with ASU’s Sustainability Goals, ASU will pursue a minimum certification level of LEED Gold. The contractor shall collaborate with ASU, the design team, the commissioning provider, subcontractors, and other project participants to satisfy the applicable LEED https://cfo.asu.edu/design-professionals requirements and documentation obligations. LEED certification must be obtained no later than 12 months following Substantial Completion.

e. Commissioning. The professional services contractor shall include coordination to work with the Owner’s Commissioning Agent (CxA) to provide systems commissioning. The Owner’s CxA does not relieve the professional services contractor from providing a fully functional and complete system. The Owner intends that the CxA be involved in the design review, submittal review, construction (startup and commissioning) and final checkout. The professional services contractor shall cooperate with the CxA to make changes needed to perform at those conditions and consistently throughout the year into the foreseeable future. Follow up by the contractor and CxA shall take place one year after the last checkout and adjustment, anticipated at two years after construction completion.

f. Design Services.

i. Refinement of existing programming and making recommendations for various solutions to meet Owner’s needs.

ii. Review the Owner’s existing program and validate the cost and project size assumptions.

iii. Advise the Owner of ways to gain efficiencies in project delivery.

iv. Preparation of schematic and design development drawings, including compliance requirements for all state and local building codes and Owner Project Guidelines.

v. Advise the team on choosing sustainable building systems and materials in an effort to meet ASU’s commitment to our sustainability goals with particular focus on Circular Resource System, Climate Positive, and Optimized Water.

vi. Provide alternate systems evaluation and constructability studies

vii. Provide long-lead procurement studies and initiate procurement of long-lead items

viii. Preparation of construction documents, including detailed specifications and drawings

ix. Proven detailed cost estimating and knowledge of marketplace conditions

x. Provide for construction phasing and scheduling that will minimize interruption to

ASU’s operations

xi. Provide project planning and scheduling

xii. Assist with the development of budgets and schedules

xiii. Development of guaranteed maximum prices for the project

xiv. Participate with the Owner in a process to set goals and prequalification meetings for Subcontractor participation

xv. Attendance at proposal openings, analysis of proposal documents and preparation of results

xvi. Bid, award, and manage all construction related contracts while meeting the

ASU bid requirements including Subcontractor participation goal https://cfo.asu.edu/sustainability-goals-and-vision

xvii. Protect the Owner’s expectations of quality and safety, and sensitivity to environmental factors

xviii. Obtain all required Owner, state and federal permits and utility interconnection approvals prior to starting construction

g. Pre-Construction Services. Pre-Construction services are projected to begin at the

Schematic Design Phase and will include the following, but are not limited to:

i. Milestone conceptual estimating and dynamic conceptual estimating of construction costs during the design process to prepare cost estimates that accurately forecast the guaranteed maximum price.

ii. Scheduling.

iii. Constructability reviews, systems review, and value engineering.

iv. Active participation in all meetings and other Design Build designated activities.

v. Communicating information on a timely basis to ASU, the design professional, the design professional’s consultants and any early selected subcontractors.

vi. Interacting with ASU, the design professional, the design professional’s consultants and any early selected subcontractors on a “team” or “win-win-win” basis.

vii. Pre-selection of subcontractors using a qualifications-based selection process.

viii. Preparing a proposed guaranteed maximum price and required accompanying information and negotiating a mutually satisfactory final guaranteed maximum price.

h. Construction Services.

i. Construct the project on schedule and in budget

ii. Bond and insure the construction

iii. Coordinate with various ASU departments, other agencies, utility companies, etc.

iv. Arrange for timely procurement of materials and equipment

v. Schedule and manage site operations Provide quality control

vi. Observation of the construction, as required, in conjunction with Owner’s Project Manager

vii. Work in a cooperative manner to address any changes that might arise during construction

viii. Provide all required closeout materials to Owner, including auto-CAD files of the as-built installation shall be provided to the Owner at time of project completion.

Accurate location of underground utilities will be provided to the Owner (depth, position, routing) from a fixed landmark.

ix. Provide warranty evaluations on an annual basis

x. Prepare timely meeting minutes and maintain records up-to-date

xi. Maintain a safe work site for all project participants

i. Final Documents. CAD files of the as-built installation shall be provided to the Owner at time of project completion. Accurate location of underground utilities will be provided to the Owner (depth, position, routing) from a fixed landmark.

j. No Historic Preservation issues are anticipated on this project. ASU will coordinate with

Arizona’s State Historic Preservation Office (SHPO) should any issues arise.

7. Design-Build Team Selection Process

a. The Design-Build Team will be selected based on demonstrated competence and qualifications only. The Owner is seeking the most responsible and responsive Design-Build Team to collaborate in achieving the successful realization of this project.

Such Teams should be multi-faceted, include a broad range of disciplines, and should be assembled to address the unique requirements of this project as outlined in the Project Description published elsewhere in this RFQ.

b. In addition to the Design Professional and the General Contractor, Proposers should include entities who bring to the Design-Build Team expertise in the following pertinent areas:

i. All required Design and Engineering Subconsultants including; landscape architects and cost estimators; and surveyors, geotechnical, civil, structural and telecommunications engineers.

ii. Any specialty consultants included in the Design-Build Team to address design issues raised by this project’s requirements.

c. Any Design-Build Team proposing to perform Design-Build services must be appropriately licensed/ registered in the State of Arizona at the time of submission of the Qualifications.

d. The Arizona Revised Statute 32-1151 requires that each entity proposing to perform professional design services is properly registered to perform such services in the State of Arizona, as required by the Board of Technical Registration. Arizona requires professional registration of Individuals, as well as Firms. Included among the disciplines registered by the Board in Arizona, and generally pertinent to design and construction projects, are architects, engineers, and landscape architects.

e. ASU has the responsibility of taking into account the size and complexity of the project under consideration, the resource investment of the firm in current work, and the amount or quality of previous work recently performed for ASU, in order to extend opportunities to a broad representation of qualified firms.