Project_Design_Specs_Jackson_Trail_Plan_08182025_Compress_(DISREGARD_PGS_28-40).pdf
PDF 14 MB Posted
- Attached to
- Sharp Park MTB Trail Project
- Solicitation number
- 2026-PARKS & RECREATION-032
- Issued by
- Kalamazoo County, Huntington Woods City, Michigan
About this file
This is a Project Design Specifications document prepared for the City of Jackson Parks & Recreation Department for the Sharp Park Mountain Bike Trail Project in Michigan. The document outlines planning-level cost estimates for multiple trail development components across several project areas, including Sharp Park, areas adjacent to the MLK Equality Trail, the Armory Arts Walk, and Summit Township Trails. The Sharp Park project specifically encompasses approximately 12.5 miles of informally developed natural surface singletrack trails requiring design and construction services. The document provides detailed quantity breakdowns for various trail types and difficulty levels, ranging from easy trails to most difficult trails, along with supporting infrastructure such as kiosks, signage, mapping, and amenity facilities.
The total planning-level cost estimates for the Sharp Park project components are as follows: Trail Design and Construction costs total $434,579, while Sharp Park Other Amenities total $570,000, and trails adjacent to MLK Equality Trail total $353,648, Armory Arts Walk total $394,118, and Summit Township Trails total $282,892. Pricing is based on current market trends with unit prices ranging from $2.40 to $300,000 depending on the line item, and includes a 10 percent contingency across most project areas. The document notes that all pricing and quantities are subject to change upon completion of final design, and economies of scale may be realized through bundling design packages. Design estimates are dated between July 30, 2025, and August 11, 2025. Special amenity considerations include the use of repurposed shipping containers for trailhead and tool storage facilities as a cost-effective solution, with potential additional costs for licensed architect or engineer design services not included in current estimates.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TYPE UNITS QTY UNIT PRICE AMT
Trail Design - Sharp Park LS 1 35,000.00$ 35,000$
SUB-TOTAL 35,000$
TYPE UNITS QTY UNIT PRICE AMT
Easy Trail (New and Reroute) LF 14,000 12.60$ 176,400$
More Difficult Trail (New and Reroute) LF 4,340 11.64$ 50,518$
Most Difficult Trail (New) LF 400 20.40$ 8,160$
Beginner Trail (Rehabilitate Existing) LF 1,425 10.80$ 15,390$
More Difficult Trail (Rehabilitate Existing) LF 1,950 9.00$ 17,550$
Decommission Trail LF 2,500 2.64$ 6,600$
Trail Features Contingency LS 1 50,000.00$ 50,000$
Kiosks, Signage, Mapping LS 1 25,000.00$ 25,000$
Contingecy PCT 1 10% 29,962$
SUB-TOTAL 379,579$
TYPE UNITS QTY UNIT PRICE AMT
Mobilization | Other Expenses LS 1 20,000$ 20,000$
SUB-TOTAL 20,000$
Total: Design (Planning Level)
Total: Construction (Planning Level) - Trails
Total: Other Expenses
Total: Trail Design and Construction Costs
Date: 7/30/2025
Construction Estimate (Planning Level) - Trails
Other Expenses
Total Trail Design and Construction (Planning Level) 35,000$
Notes:
1) Pricing is based on current market trends, quantities and pricing subject to change at completion of final design.
2) Economies of scale may be realized by bundling design packages.
379,579$
20,000$
434,579$
Sharp Park Design Estimate (Planning Level)
Sharp Park
TYPE UNITS QTY UNIT PRICE AMT
Skills Area Design - Sharp Park LS 1 20,000.00$ 20,000$
SUB-TOTAL 20,000$
TYPE UNITS QTY UNIT PRICE AMT
Skills Area EA 1 300,000.00$ 300,000$
Trailhead Facility* EA 1 150,000.00$ 150,000$
Tool Storage Facility* EA 1 50,000.00$ 50,000$
Contingecy PCT 1 10% 50,000$
SUB-TOTAL 550,000$
Total: Design (Planning Level)
Total: Construction (Planning Level) Other Amenities
Total: Trail Design and Construction Costs
Date: 8/11/2025
Sharp Park
Design Estimate (Planning Level) Sharp Park
550,000$
Notes:
*Trailhead and Tool Storage Facility development is anticipated to use repurposed shipping containers as the preferred approach, offering a cost-effective and community-branded solution. Depending on the final scope of amenities, design services from a licensed architect or engineer may still be required. These professional design costs are not included in the current cost estimates.
Construction Estimate (Planning Level) - Other Amenities
Total Other Amenities 20,000$
550,000$
Trail Design - Adjacnet to MLK Equality Trail |
Neighborhood Access
LS 1 30,000.00$ 30,000$
SUB-TOTAL 30,000$
TYPE UNITS QTY UNIT PRICE AMT
Easy Trail (New) LF 15,840 12.60$ 199,584$
More Difficult Trail (New) LF 5,280 11.64$ 61,459$
Kiosks, Signage, Mapping LS 1 15,000.00$ 15,000$
Contingecy PCT 1 10% 27,604$
SUB-TOTAL 303,648$
TYPE UNITS QTY UNIT PRICE AMT
Mobilization | Other Expenses LS 1 20,000$ 20,000$
SUB-TOTAL 20,000$
Total: Concept and Design (Planning Level)
Total: Construction (Planning Level) - Trails
Total: Other Expenses
Total: Trail Design and Construction Costs
Date: 7/30/2025
Other Expenses
Trails Adjacnet to MLK Equality Trail | Neighborhood Access Concept and Design Estimate (Planning Level)
Trails Adjacnet to MLK Equality Trail Construction Estimate (Planning Level) - Trails
1) Pricing is based on current market trends, quantities and pricing subject to change at completion of final design.
2) Economies of scale may be realized by bundling design packages.
Total Trail Design and Construction (Planning Level) 30,000$
303,648$
20,000$
353,648$
Notes:
TYPE UNITS QTY UNIT PRICE AMT
Trail Design - Adjacnet to Armory Arts Walk LS 1 25,000.00$ 25,000$
SUB-TOTAL 25,000$
TYPE UNITS QTY UNIT PRICE AMT
Easy Trail (New) LF 3,500 12.60$ 44,100$
More Difficult Trail (New) LF 2,000 11.64$ 23,280$
Base Prep for All Weather Surfacing Option SF 22,000 2.40$ 52,800$
All Weather Surfacing Option SF 22,000 9.60$ 211,200$
Kiosks, Signage, Mapping LS 1 10,000.00$ 10,000$
Contingecy PCT 1 10% 7,738$
SUB-TOTAL 349,118$
TYPE UNITS QTY UNIT PRICE AMT
Mobilization | Other Expenses LS 1 20,000$ 20,000$
SUB-TOTAL 20,000$
Total: Concept and Design (Planning Level)
Total: Construction (Planning Level) - Trails
Total: Other Expenses
Total: Trail Design and Construction Costs
Date: 7/30/2025
Other Expenses
Armory Arts Walk Concept and Design Estimate (Planning Level)
Armory Arts Walk Construction Estimate (Planning Level) - Trails
1) Pricing is based on current market trends, quantities and pricing subject to change at completion of final design.
2) Economies of scale may be realized by bundling design packages.
Total Trail Design and Construction (Planning Level) 25,000$
349,118$
20,000$
394,118$
Notes:
Trail Design - Summit Township Trails LS 1 30,000.00$ 30,000$
SUB-TOTAL 30,000$
TYPE UNITS QTY UNIT PRICE AMT
Easy Trail (New) LF 4,000 12.60$ 50,400$
More Difficult Trail (New) LF 13,000 11.64$ 151,320$
Kiosks, Signage, Mapping LS 1 10,000.00$ 10,000$
Contingecy PCT 1 10% 21,172$
SUB-TOTAL 232,892$
TYPE UNITS QTY UNIT PRICE AMT
Mobilization | Other Expenses LS 1 20,000$ 20,000$
SUB-TOTAL 20,000$
Total: Concept and Design (Planning Level)
Total: Construction (Planning Level)
Total: Other Expenses
Total: Trail Design and Construction Costs
Date: 8/11/2025
Other Expenses
Summit Township Trails Concept and Design Estimate (Planning Level)
Summit Township Trails Construction Estimate (Planning Level)
1) Pricing is based on current market trends, quantities and pricing subject to change at completion of final design.
2) Economies of scale may be realized by bundling design packages.
Total Trail Design and Construction (Planning Level) 30,000$
232,892$
20,000$
282,892$
Notes: