PROJECT DESCRIPTION_MT DAR MALM 2025(1).pdf
PDF 157 KB Posted
- Solicitation number
- 69056725B000007
About this file
This document is a detailed Project Description for the MT DAR MALM 2025(1) Defense Access Roads project at Malmstrom Air Force Base in Fergus County, Montana. The project involves roadway reconditioning, aggregate surfacing, aggregate stabilization, subexcavation, and drainage improvements across five different bid schedules with varying project lengths from 12.85 to 48.90 miles. Only one schedule will be awarded, with an estimated price range of $5 million to $10 million and a tentative fixed completion date in Fall 2026.
The project specifications include comprehensive requirements across multiple divisions, such as construction survey and staking, quality control, soil erosion control, aggregate base courses, culvert installation, and temporary traffic control. Key technical elements involve crushed aggregate placement, road reconditioning, stabilized aggregate surface courses with calcium chloride treatment, riprap installation, drainage structure repairs, and turf establishment. The project will require extensive temporary traffic control measures, including flagging and traffic control support, and is being conducted by the Department of Transportation Federal Highway Administration on an unrestricted, full and open competition basis.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT DAR MALM 2025(1), Defense Access Roads FY 2025
Malmstrom Air Force Base
Fergus County, Montana
The work consists of roadway reconditioning, aggregate surfacing, aggregate stabilization, subexcavation, and drainage improvements.
Project length: Schedule A- 12.85 miles
Schedule B- 23.38 miles
Schedule C- 35.26 miles
Schedule D- 43.99 miles
Schedule E- 48.90 miles
There are five bid schedules; only one schedule will be awarded.
Tentative Fixed Completion Date: Fall 2026
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $5 million to $10 million
Location: 70 miles NW of Lewiston, MT
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-24
O n e S ch ed u le
S ch
N am e
A
A d d it io n al
N am e
B
A d d it io n al
N am e
_C d d it io n al
N am e
D
A d d it io n al
N am e
_E
DIVISION 150 – Project Requirements
152 Construction Survey & Staking (yes/no) Yes Yes Yes Yes Yes
153 Contractor Quality Control and Assurance (yes/no) Yes Yes Yes Yes Yes
154 Contractor Sampling & Testing (yes/no) Yes Yes Yes Yes Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes Yes Yes Yes
157 Soil Erosion & Sediment Control (erosion control devices)
Fiber Rolls
460 LNFT
Fiber Rolls
900 LNFT
Fiber Rolls
1400 LNFT
Fiber Rolls
1580 LNFT
Fiber Rolls
1760 LNFT
158 Watering for Dust Control Yes Yes Yes Yes Yes
O n e S ch ed u le
N am e
A d d it io n al
N am e
B
A d d it io n al
N am e
_C d d it io n al
N am e
D
A d d it io n al
N am e
_E
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Riprap
Class 2
9 CUYD
Class 2
9 CUYD
Class 2
9 CUYD
Class 2
63 CUYD
Class 3
20 CUYD
Class 2
63 CUYD
Class 3
20 CUYD
DIVISION 300 – Aggregate and Base Courses
302 Crushed Aggregate (Roadway Aggregate, Method 2) 890 TON 1635 TON 1925 TON 1925 TON 2310 TON
303 Road Reconditioning 12.85 MILE 23.38 MILE 35.26 MILE 43.99 MILE 48.90 MILE
311 Stabilized Aggregate Surface Course Aggregate
35515 TON
Calcium Chloride
679 TON
Aggregate
58117 TON
Calcium Chloride
1211 TON
Aggregate
79650 TON
Calcium Chloride
1753 TON
Aggregate
92226 TON
Calcium Chloride
2201 TON
Aggregate
107669 TON
Calcium Chloride
2459 TON
DIVISION 600 – Incidental Construction
602 Culverts & Drains (indicate one or both)
24-inch Culvert
50 LNFT
24-inch Culvert
50 LNFT
36-inch Culvert
80 LNFT
24-inch Culvert
50 LNFT
36-inch Culvert
80 LNFT
24-inch Culvert
50 LNFT
36-inch Culvert
80 LNFT
607 Cleaning, Relaying, & Repairing Existing Drainage Structures
Repairing 1
EACH
Repairing 5
EACH
Repairing 6
EACH
Cleaning 1
EACH
Repairing 6
EACH
Cleaning 2
EACH
Repairing 6
EACH
622 Rental Equipment (yes/no) Yes Yes Yes Yes Yes
623 General Labor (yes/no) Yes Yes Yes Yes Yes
624 Topsoil (landscaping & related items) 4-inch depth
45 SQYD
4-inch depth
315 SQYD
4-inch depth
450 SQYD
4-inch depth
450 SQYD
4-inch depth
450 SQYD
625 Turf Establishment (indicate seeding or mulching separately) 45 SQYD 315 SQYD 450 SQYD 450 SQYD 450 SQYD
635 Temporary Traffic Control Yes Yes Yes Yes Yes
635 Temporary Traffic Control – Flagger 1040 HOUR 1940 HOUR 2820 HOUR 3420 HOUR 3840 HOUR
635 Temporary Traffic Control – TCS 52 DAY 97 DAY 141 DAY 171 DAY 192 DAY