PROJECT DESCRIPTION_ID FLAP ADA 2019(1).pdf
PDF 269 KB Posted
- Solicitation number
- 69056726R000010
About this file
This is a presolicitation notice for a federal transportation construction project in Ada County, Idaho. The project, identified as ID FLAP ADA 2019(1) for the Western Heritage Byway - Swan Falls Road, consists of shoulder widening, paving, signage, parking lot improvement, and culvert replacement located 7 miles south of Kuna, Idaho. The solicitation is tentatively scheduled for Summer 2026 with a fixed completion date in Summer/Fall 2027, and the estimated price range is $5 million to $10 million.
The contract offers four mutually exclusive bid schedules with varying project scopes: Schedule A covers 3.25 miles, Schedule B covers 3.82 miles, Schedule C covers 4.94 miles, and Schedule D covers 8.50 miles, with only one schedule to be awarded. Work requirements are detailed across multiple divisions including project requirements (survey, staking, quality control, erosion control), earthwork (clearing, grubbing, excavation, removal of existing features), base courses and aggregate, asphalt and concrete pavements, culvert installation and maintenance, and incidental construction including signage, pavement markings, temporary traffic control, and site fixtures. Key quantities vary by schedule, with Schedule D representing the largest scope including chip seal surface treatment (147,500 square yards) not included in smaller schedules. All schedules require construction survey and staking, contractor quality control and testing, and construction scheduling.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PRELIM_ida-ada2019-1_plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID FLAP ADA 2019(1), Western Heritage Byway - Swan Falls Road
Ada County, Idaho
This work consists of shoulder widening, paving, signage, parking lot improvement, and culvert replacement.
Project length:
Schedule A – 3.25 miles
Schedule B – 3.82 miles
Schedule C – 4.94 miles
Schedule D – 8.50 miles
There are 4 bid schedules; only 1 bid schedule will be awarded.
Tentative Fixed Completion Date: Summer/Fall 2027
(Once solicitation is issued, see SF1442 Continuation, Block 11 for exact date.)
Tentative Solicitation Date: Summer 2026
Estimated Price Range: $5 million to $10 million
Location: 7 miles south of Kuna, Idaho
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-24
S ch ed u le A ed u
B ed u
C ed u
D
DIVISION 150 – Project Requirements
152 Construction Survey & Staking (yes/no) Yes Yes Yes Yes
153 Contractor Quality Control (yes/no) Yes Yes Yes Yes
154 Contractor Sampling & Testing (yes/no) Yes Yes Yes Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes Yes Yes
157 Soil Erosion & Sediment Control, Fiber Roll 10,500 LNFT 10,700 LNFT 17,500 LNFT 17,500 LNFT
158 Watering for Dust Control LPSM LPSM LPSM LPSM
DIVISION 200 – Earthwork
201 Clearing & Grubbing 9 ACRE 9.5 ACRE 13 ACRE 13 ACRE
203 Removal of Cattle Guard 1 EACH 1 EACH 1 EACH 1 EACH ed u ed u ed u ed u
203 Removal of Gate 1 EACH 1 EACH 1 EACH 1 EACH
203 Removal of Restroom Facility 2 EACH 2 EACH 2 EACH 2 EACH
203 Removal of Sign 4 EACH 4 EACH 4 EACH 4 EACH
203 Removal of Vault (Concrete Tanks) 4 EACH 4 EACH 4 EACH 4 EACH
203 Removal of Fence 55 LNFT 55 LNFT 55 LNFT 55 LNFT
203 Sawcutting Pavement 33,880 LNFT 39,900 LNFT 49,000 LNFT 49,000 LNFT
204 Roadway Excavation 13,000 CUYD 14,600 CUYD 18,400 CUYD 18,400 CUYD
204 Rock Excavation 420 CUYD 420 CUYD 420 CUYD 420 CUYD
204 Ditch, Excavation (Regrading) 90 LNFT 90 LNFT 90 LNFT 90 LNFT
204 Remove and Reset Boulder 30 EACH 30 EACH 30 EACH 30 EACH
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Placed Riprap, Class 2 5 CUYD 5 CUYD 5 CUYD 5 CUYD
DIVISION 300 – Aggregate and Base Courses
302 Roadway Aggregate, Method 2 17,000 TON 20,000 TON 24,000 TON 24,000 TON
302 Roadway Aggregate, Method 2, Surface Course, 6-Inch Depth 2,000 SQYD 2,000 SQYD 2,000 SQYD 2,000 SQYD
DIVISION 400 – Asphalt Pavements & Surface Treatments
403 Asphalt Concrete Pavement 3,600 TON 4,200 TON 6,500 TON 6,500 TON
406 Fog Seal - - - 100 TON
407 Chip Seal, Type 1C - - - 147,500 SQYD
407 Emulsified Asphalt - - - 280 TON
412 Tack Coat 1.5 TON 1.5 TON 5 TON 5 TON
413 Asphalt Pavement Milling, 4-Inch Depth 1,200 SQYD 1,200 SQYD 6,800 SQYD 6,800 SQYD
414 Cracks, Cleaning and Sealing 3.5 MILE 4 MILE 5 MILE 9 MILE
414 Cracks, Cleaning and Filling 3.5 MILE 4 MILE 5 MILE 9 MILE
DIVISION 500 – Rigid Pavement
501 Minor Concrete Pavement, Plain, 6-Inch Depth 70 SQYD 70 SQYD 70 SQYD 70 SQYD
DIVISION 600 – Incidental Construction
602 12-Inch Pipe Culvert - 50 LNFT 50 LNFT 50 LNFT ed u ed u ed u ed u
602 18-Inch Pipe Culvert 210 LNFT 210 LNFT 210 LNFT 210 LNFT
602 24-Inch Pipe Culvert 270 LNFT 270 LNFT 370 LNFT 370 LNFT
602 End Section for 24-Inch Pipe Culvert 3 EACH 3 EACH 3 EACH 3 EACH
607 Cleaning Culvert In Place 2 EACH 2 EACH 2 EACH 2 EACH
609 Wheelstop, Concrete 2 EACH 2 EACH 2 EACH 2 EACH
610 Sidewalk, Concrete (6-Inch Depth) 300 SQYD 300 SQYD 300 SQYD 300 SQYD
614 Flowable Backfill 13 CUYD 13 CUYD 13 CUYD 13 CUYD
619 Cattle Guard, 32 Feet 1 EACH 1 EACH 1 EACH 1 EACH
619 Remove and Reset Fence 30 LNFT 30 LNFT 30 LNFT 30 LNFT
622 Rental Equipment (yes/no) Yes Yes Yes Yes
623 General Labor (yes/no) Yes Yes Yes Yes
624 Providing and Placing Topsoil, 4-Inch Depth 7 ACRE 8 ACRE 9 ACRE
625 Turf Establishment 7 ACRE 8 ACRE 9 ACRE
633 Sign System 235 SQFT 235 SQFT 235 SQFT 235 SQFT
633 Object Marker 4 EACH 4 EACH 4 EACH 4 EACH
633 Rumble Strip 32,950 LNFT 38,780 LNFT 50,600 LNFT 50,600 LNFT
634 Pavement Markings, Type B, Solid (White) 69,000 LNFT 81,100 LNFT 105,100 LNFT 180,300 LNFT
634 Pavement Markings, Type B, Solid (Yellow) 51,210 LNFT 58,100 LNFT 74,340 LNFT 126,660 LNFT
634 Pavement Markings, Type B, Broken (Yellow) 15,700 LNFT 19,900 LNFT 26,000 LNFT 39,200 LNFT
634 Pavement Markings, Type B, Accessibility Symbol 4 EACH 4 EACH 4 EACH 4 EACH
635 Temporary Traffic Control, Barricade Type 1 5 EACH 5 EACH 5 EACH 5 EACH
635 Temporary Traffic Control, Barricade Type 3 2 EACH 2 EACH 2 EACH 2 EACH
635 Temporary Traffic Control, Drum 230 EACH 260 EACH 320 EACH 320 EACH
635 Temporary Traffic Control, Portable Changeable Message Sign 2 EACH 2 EACH 2 EACH 2 EACH
635 Temporary Traffic Control, Pavement Markings 430 LNFT 430 LNFT 3,130 LNFT 3,130 LNFT
635 Temporary Traffic Control, Construction Sign 150 SQFT 150 SQFT 150 SQFT 150 SQFT
635 Temporary Traffic Control, Flagger 3,000 HOUR 3,100 HOUR 3,500 HOUR 3,500 HOUR
635 Temporary Traffic Control, Pilot Car 600 HOUR 650 HOUR 900 HOUR 1,070 HOUR
635 Temporary Traffic Control, Traffic Control Supervisor 105 DAY 110 DAY 120 DAY 120 DAY
646 Fixture, Picnic Table 2 EACH 2 EACH 2 EACH 2 EACH
646 Fixture, Vault Toilet 1 EACH 1 EACH 1 EACH 1 EACH
646 Fixture, Shelter (Shade Structure) 1 EACH 1 EACH 1 EACH 1 EACH