This is a Presolicitation notice for a repair and construction project at the Nez Perce-Clearwater National Forest located 15 miles southeast of Grangeville, Idaho, spanning Clearwater and Idaho Counties. The project consists of culvert replacement, wall construction, and slope repairs across five locations within the forest, with a total project length of 0.2 miles and an estimated price range of $2,000,000 to $5,000,000. The tentative solicitation date is Winter 2026/2027, with a tentative fixed completion date of Fall 2027.

Work scope includes earthwork (clearing and grubbing, roadway excavation, select borrow, geotextile and geogrid installation totaling 2,200 square yards and 5,100 cubic yards respectively), slope reinforcement and retaining walls (mechanically stabilized earth walls of 4,200 square feet, placed riprap, and special rock embankment of 1,000 cubic yards), aggregate and base courses (700 cubic yards aggregate surface course and 670 cubic yards roadway aggregate), and incidental construction including 24-inch and 72-inch pipe culverts (125 and 50 linear feet respectively), turf establishment (2,550 square yards), temporary stream diversion, temporary traffic control measures, and equipment rental for dump trucks, hydraulic excavators, and chain saws. Contractor quality control and assurance, contractor sampling and testing, construction scheduling, and soil erosion and sediment control measures of 200 linear feet are required components of the base schedule.

View the file

Other files

File Type Posted
Prelim Letter_ID ERFO FS 2022-1(1).pdf PDF
id-ef2022-1-1-PLAN_preliminary.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID ERFO FS 2022-1(1), Nez Perce-Clearwater Repairs 2022-1

Nez Perce-Clearwater National Forest

Clearwater and Idaho Counties, Idaho

The work consists of culvert replacement, wall construction, and slope repairs. The project consists of five locations within the Nez Perce-Clearwater National Forest.

Project length: 0.2 miles

Tentative Fixed Completion Date: Fall 2027

(Once solicitation is issued, see SF1442 Continuation, Block 11 for exact date.)

Tentative Solicitation Date: Winter 2026/2027

Estimated Price Range: $2,000,000 and $5,000,000

Location: 15 miles SE of Grangeville, ID

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-24

Base Schedule

DIVISION 150 – Project Requirements

151 Mobilization Yes

152 Construction Survey & Staking (yes/no) Yes

153 Contractor Quality Control and Assurance (yes/no)

Yes

154 Contractor Sampling & Testing (yes/no) Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes

157 Soil Erosion & Sediment Control (erosion control devices) 200 LNFT

DIVISION 200 – Earthwork

201 Clearing & Grubbing 2200 SQYD

204 Roadway Excavation 5100 CUYD

204 Subexcavation 400 CUYD

204 Select Borrow 380 CUYD

207 Separation Geotextile, Woven 710 SQYD

207 Geogrid, Standard 950 SQYD

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Placed Riprap, Class 3 72 CUYD

252 Special Rock Embankment, Mechanically placed 1000 CUYD

255 Mechanically Stabilized Earth Walls 4200 SQFT

Base Schedule

DIVISION 300 – Aggregate and Base Courses

301 Aggregate Surface Course 700 CUYD

302 Roadway Aggregate, Method 2 670 CUYD

314 Stockpiled Aggregates – Bentonite 2 TON

DIVISION 600 – Incidental Construction

602 24-inch pipe Culverts 125 LNFT

602 72-inch pipe Culverts 50 LNFT

622 Dump Truck 40 HOUR

622 Hydraulic Excavator 40 HOUR

622 Chain Saw 40 HOUR

622 General Labor 40 HOUR

625 Turf Establishment 2550 SQYD

628 Temporary Stream Diversion LPSM

635 Temporary Traffic Control, Traffic Control Supervisor LPSM

635 Temporary Traffic Control, Barricade Type 3 10 EACH

635 Temporary Traffic Control, Construction Sign 500 SQFT

635 Temporary Traffic Control, Flagger 100 HOUR

635 Temporary Traffic Control, Pilot Car 10 DAY