PROJECT DESCRIPTION_ID DOT 21(1) SH-21.pdf
PDF 174 KB Posted
- Solicitation number
- 69056721B000009
About this file
This document provides a project description and related federal contract opportunity for a wildlife overpass construction project. The project description outlines the scope of work to include construction of a precast concrete arch structure, MSE walls, fencing with gates, asphalt paving, turf establishment, and installation of solar powered video cameras. The location is 20 miles east of Boise, Idaho with an estimated price range of $3-5 million and tentative completion date of Fall 2022. The related federal contract opportunity on SAM.gov is a pre-solicitation for the ID DOT 21(1) SH-21 Wildlife Overpass with the Department of Transportation Federal Highway Administration as the contracting agency. The opportunity is set aside for small businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PROJECT DESCRIPTION_ID DOT 21(1) SH-21 updated.pdf | ||
| ID DOT 21(1) PRELIM PLANS.pdf | ||
| ID DOT 21(1) Prelim Letter.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID DOT 21(1) SH-21 Wildlife Overpass at Cervidae Peak, MP 19.3
This project includes, a precast concrete arch structure, MSE walls connecting to the concrete arch structure, 8-foot tall steel post fence with wire mesh, and gates intermittently positioned along the fence alignment. This project also includes grading related to fence installation and concrete arch installation, asphalt Paving, turf establishment, solar powered video camera installation, and all necessary staging, erosion control and traffic control to complete the work.
Tentative Fixed Completion Date: Fall 2022 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $3 million to $5 million
Location: 20 Miles East of Boise Idaho.
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
On e S ch ed ul e
Sc h
Na m e
DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance
(yes/no) Yes 154 Contractor Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Select 157 Soil Erosion & Sediment Control - Silt Fence
13,000 LN
FT
157 Soil Erosion & Sediment Control - Stabilized Construction Exit 2 158 Watering for Dust Control LPSM
DIVISION 200 – Earthwork 201 Clearing & Grubbing 1 acre 204 Excavation & Embankment 1000 CY 203 Pavement Removal 1400 SQ YD 204 Unclassified Borrow 17,000 CY DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap 500 CY
On e S ch ed ul e
Sc h
Na m e
255 Mechanically Stabilized Earth Walls (retaining walls) 4500 SQFT DIVISION 300 – Aggregate and Base Courses 301 Aggregate Courses (crushed aggregate) 230 CY DIVISION 400 – Asphalt Pavements & Surface Treatments 401 Asphalt Concrete Pavement By Gyratory Mix Design Method 1100 TON 413 Asphalt Pavement Milling 1300 SQYD
DIVISION 550 – Bridge Construction 552 Structural Concrete (concrete – major structures) 1250 CY DIVISION 600 – Incidental Construction 617 Guardrail 570 LNFT 618 Concrete Barriers & Precast Guardwalls 300 LNFT 619 Fence 13,100
LNFT
619 Gate (3 feet) 10 EA 619 Gate (10 feet) 10 EA 624 Topsoil (landscaping & related items) 2500 CY 625 Turf Establishment (indicate seeding or mulching separately) 2 acres 635 Temporary Traffic Control - Signs 35 SQ FT 635 Temporary Traffic Control – Pavement Markings 5820 LN FT 635 Temporary Traffic Control – Portable Changeable Message Signs 2 EA 635 Temporary Traffic Control – Traffic Signal System 2 EA 635 Temporary Traffic Control – Flagger 112 HR 646 Roadside Development – Camera Fixture 4 EA 646 Roadside Development – Cameras 10 EA 646 Roadside Development – Jumpouts 11 EA
| DIVISION 200 – Earthwork |
| DIVISION 250 – Slope Reinforcement and Retaining Walls |
| DIVISION 300 – Aggregate and Base Courses |
| DIVISION 400 – Asphalt Pavements & Surface Treatments |