MMSL_BY
| ELIN / PRICING Schedule |
| CONTRACT POP: 01 January 2021 - 31 December 2021 |
| Base Year (FY21) | ||||||
| CLIN | ELIN No | DESCRIPTION | QTY | U/I | UNIT | TOTAL |
| PRICE | AMOUNT | |||||
| EURO | EURO |
| 0001 | A001 | Measuring of Landfill Gas Emission at the Landfill Surface Are via Flame Ionization Detector (FID) IAW the PWS, Paragraph 5.2.1 - 5.2.1.3 | ||
| A001AA | Preparation of the landill surface are for measurement | 1 | EA | |
| A001AB | Measurement (FID) of the landfill gas | 1 | EA | |
| A001AC | Documentation | 1 | EA |
| 0002 | A002 | Flushing/Cleaning and Camera-Inspection of Underground Leachate Water Lines, Control Shafts and Collection Basins, Performance of Pressure- and Tightness Tests IAW the PWS, Paragraph 5.2.2 - 5.2.2.13 | ||
| A002AA | TV-Inspection of leachate water lines outside the sealed landfill area (total length - 880.7 meter) | 1 | SV | |
| A002AB | Semi-annual flushing and cleaning of leachate water lines (880.7 meters) outside the sealed landfill area | 2 | SV | |
| A002AC | Semi-annual flushing and cleaning of leachate water control shafts (30ea) outside the sealed landfill area | 2 | SV | |
| A002AD | Preparation of shaft documentation papers and sewer sections report | 28 | EA | |
| A002AE | TV-inspection of 8 each control drainage lines inside the sealed landfill area (total length-743 meter) | 1 | SV | |
| A002AF | Preparation of inspection reports for the control drainage lines inside the sealed landfill area | 8 | EA | |
| A002AG | TV-inspection of leachate water drainages inside the landfill area (total length - 991.1 meter) | 1 | SV | |
| A002AH | Semi-annual flushing and cleaning of the leachate water drainage lines (991,1 meters) inside the sealed landfill area | 2 | SV | |
| A002AI | Preparation of inspection reports of the Video inspected leachate water lines within the landfill area | 12 | EA | |
| A002AJ | Tightness inspection of leachate water carrying lines outside the sealed landfill area (total length-880.7 meter) | 1 | SV | |
| A002AK | Preparation of Tightness Test Protocols for each shaft | 28 | EA | |
| A002AL | Inspection of the leachate water control shafts for constructual and operational function/condition | 28 | EA | |
| A002AM | Reconsideration of tighness test if tests are negative | 3 | EA | |
| A002AN | Semi-annual cleaning services at the leachate water basin at Building 716 | 2 | SV | |
| A002AO | Flushing of storm sewer lines at the landfill entrance area (total length-749.13 meter) | 1 | SV | |
| A002AP | Cleaning of 18 ea shafts within the landfill entrance area | 1 | SV | |
| A002AQ | Flushing of storm sewer lines at the shredder plant facility Bldg. 710 and Bldg. 720 (557,12 meters) and the condensing water shaft (1) in front of Bldg.717 | 1 | SV | |
| A002AR | Pumping and cleaning of the reserve leachate water basin near Building 716 | 1 | SV | |
| A002AS | Semi-annual flushing of lines in filling field 18 (total length-31 meter) | 2 | SV | |
| A002AT | Semi-annual flushing, cleaning and inspection of leachate water control shafts (28 each) and the gas line collection shaft (1 each) at Bldg. 717 | 2 | SV | |
| A002AV | Flushing of the leachate water pressure lines (total length-1,329 meter) and cleaning of 15 each shafts | 1 | SV | |
| A002AW | Annual Measurement of the Inside Temperature of all leachate Water Lines | 1 | SV | |
| A002AX | Flushing and cleaning of the vehicle scale | 1 | SV | |
| A002AY | Recording and preparation video DVD's for all TV-Inspections | 1 | SV |
| 0003 | A003 | Maintenance and Inspection of the Lambda Container Degassing Unit CHC 10 inclusive Gas Torch IAW the PWS,Paragraph 5.2.3 - 5.2.3.2.5 | ||
| A003AA | Bi-weekly function control of the Gas Torch | 24 | SV | |
| A003AB | Quarterly Maintenece and Safety Inspection | 2 | SV | |
| A003AC | Semi-Annual control for damages of the gas control station and gas collectors | 1 | SV | |
| A003AD | Annual Maintenance anad performance of the landfill gas analysis | 1 | SV | |
| A003AE | Gas Torch Emmission Measurement (Basic Year only) | 1 | SV |
| 0004 | A004 | Maintenance and Monitoring of the Landfill Gas Wells and Horizontal Pipes IAW PWS, Paragraph 5.2.4 - 5.2.4.5 | ||
| A004AA | Bi-Weekly servicing of 26 each Gas Wells | 24 | EA | |
| A004AB | Bi-Weekly servicing of 5 each Horizontal Gas Pipes | 24 | EA | |
| A004AC | Bi-weekly control and adjust Flap Position | 24 | EA | |
| A004AD | Bi-weekly control of 5 each Condensate Collection Vats | 12 | SV | |
| A004AD | Bi-weekly gas analysis | 24 | EA |
| 0005 | Time & Material - Labor Hours | ||
| Performance of repair work IAW the PWS Paragraph 5.3 | |||
| Contractor/ Subcontractor assessed hourly rate if additional repair work outside the routine maintenance work is required | 50 | HR |
| 0006 | Time & Material -Spare Parts | ||
| Government assessed amount during contract award for the procurement and delivery of Parts and Material for repair work IAW the PWS, Paragraph 5.2.3 | 1 | LS | |
| NOTE: THE AMOUNT FOR THIS CLIN WILL BE INSERTED AT TIME OF AWARD. |
(GOVERNMENT SET AMOUNT DO NOT INSERT PRICE FOR THIS CLIN)
| 0007 | Performance of On-Call Services / Troubleshooting | ||
| Perfromance of On-Call Sevices and Troubleshooting IAW the PWS, Paragraph 5.4 | 5 | SV |
| 0008 | Documentation | ||
| Create and maintain all required bi-weekly-, monthy, quarterly, semi-annual and annual statistics as well as the creation of an annual summary of all test results for the submission to the controlling authorities IAW the PWS | 1 | SV |
| Consolidation: | |
| CLIN 0001 (A001AA - A001AC) | € 0.00 |
| CLIN 0002 (A002AA - A002AY) | € 0.00 |
| CLIN 0003 (A003AA - A003AE) | € 0.00 |
| CLIN 0004 (A004AA - A004AD) | € 0.00 |
| CLIN 0005 T&M - Labor Hours | € 0.00 |
| CLIN 0006 T&M - Spare Parts (DO NOT INSERT PRICE FOR THIS CLIN) | € 0.00 |
| CLIN 0007 ON-Call-Services | € 0.00 |
| CLIN 0008 Documentation | € 0.00 |
| Total CLIN 0001 - CLIN 0008 | € 0.00 |
MMSL_1st OY
| ELIN / PRICING Schedule |
| CONTRACT POP: 01 January 2022 - 31 December 2022 |
| 1st Option Year (FY22) | ||||||
| CLIN | ELIN No | DESCRIPTION | QTY | U/I | UNIT | TOTAL |
| PRICE | AMOUNT | |||||
| EURO | EURO |
| 1001 | A001 | Measuring of Landfill Gas Emission at the Landfill Surface Are via Flame Ionization Detector (FID) IAW the PWS, Paragraph 5.2.1 - 5.2.1.3 | ||
| A001AA | Preparation of the landill surface are for measurement | 1 | EA | |
| A001AB | Measurement (FID) of the landfill gas | 1 | EA | |
| A001AC | Documentation | 1 | EA |
| 1002 | A002 | Flushing/Cleaning and Camera-Inspection of Underground Leachate Water Lines, Control Shafts and Collection Basins, Performance of Pressure- and Tightness Tests IAW the PWS, Paragraph 5.2.2 - 5.2.2.13 | ||
| A002AA | TV-Inspection of leachate water lines outside the sealed landfill area (total length - 880.7 meter) | 1 | SV | |
| A002AB | Semi-annual flushing and cleaning of leachate water lines (880.7 meters) outside the sealed landfill area | 2 | SV | |
| A002AC | Semi-annual flushing and cleaning of leachate water control shafts (30ea) outside the sealed landfill area | 2 | SV | |
| A002AD | Preparation of shaft documentation papers and sewer sections report | 28 | EA | |
| A002AE | TV-inspection of 8 each control drainage lines inside the sealed landfill area (total length-743 meter) | 1 | SV | |
| A002AF | Preparation of inspection reports for the control drainage lines inside the sealed landfill area | 8 | EA | |
| A002AG | TV-inspection of leachate water drainages inside the landfill area (total length - 991.1 meter) | 1 | SV | |
| A002AH | Semi-annual flushing and cleaning of the leachate water drainage lines (991,1 meters) inside the sealed landfill area | 2 | SV | |
| A002AI | Preparation of inspection reports of the Video inspected leachate water lines within the landfill area | 12 | EA | |
| A002AJ | Tightness inspection of leachate water carrying lines outside the sealed landfill area (total length-880.7 meter) | 1 | SV | |
| A002AK | Preparation of Tightness Test Protocols for each shaft | 28 | EA | |
| A002AL | Inspection of the leachate water control shafts for constructual and operational function/condition | 28 | EA | |
| A002AM | Reconsideration of tighness test if tests are negative | 3 | EA | |
| A002AN | Semi-annual cleaning services at the leachate water basin at Building 716 | 2 | SV | |
| A002AO | Flushing of storm sewer lines at the landfill entrance area (total length-749.13 meter) | 1 | SV | |
| A002AP | Cleaning of 18 ea shafts within the landfill entrance area | 1 | SV | |
| A002AQ | Flushing of storm sewer lines at the shredder plant facility Bldg. 710 and Bldg. 720 (557,12 meters) and the condensing water shaft (1) in front of Bldg.717 | 1 | SV | |
| A002AR | Pumping and cleaning of the reserve leachate water basin near Building 716 | 1 | SV | |
| A002AS | Semi-annual flushing of lines in filling field 18 (total length-31 meter) | 2 | SV | |
| A002AT | Semi-annual flushing, cleaning and inspection of leachate water control shafts (28 each) and the gas line collection shaft (1 each) at Bldg. 717 | 2 | SV | |
| A002AV | Flushing of the leachate water pressure lines (total length-1,329 meter) and cleaning of 15 each shafts | 1 | SV | |
| A002AW | Annual Measurement of the Inside Temperature of all leachate Water Lines | 1 | SV | |
| A002AX | Flushing and cleaning of the vehicle scale | 1 | SV | |
| A002AY | Recording and preparation video DVD's for all TV-Inspections | 1 | SV |
| 1003 | A003 | Maintenance and Inspection of the Lambda Container Degassing Unit CHC 10 inclusive Gas Torch IAW the PWS,Paragraph 5.2.3 - 5.2.3.2.5 | ||
| A003AA | Bi-weekly function control of the Gas Torch | 24 | SV | |
| A003AB | Quarterly Maintenece and Safety Inspection | 2 | SV | |
| A003AC | Semi-Annual control for damages of the gas control station and gas collectors | 1 | SV | |
| A003AD | Annual Maintenance and performance of the landfill gas analysis | 1 | SV |
| 1004 | A004 | Maintenance and Monitoring of the Landfill Gas Wells and Horizontal Pipes IAW PWS, Paragraph 5.2.4 - 5.2.4.5 | ||
| A004AA | Bi-Weekly servicing of 26 each Gas Wells | 24 | EA | |
| A004AB | Bi-Weekly servicing of 5 each Horizontal Gas Pipes | 24 | EA | |
| A004AC | Bi-weekly control and adjust Flap Position | 24 | EA | |
| A004AD | Bi-weekly control of 5 each Condensate Collection Vats | 12 | SV | |
| A004AD | Bi-weekly gas analysis | 24 | EA |
| 1005 | Time & Material - Labor Hours | ||
| Performance of repair work IAW the PWS Paragraph 5.3 | |||
| Contractor/ Subcontractor assessed hourly rate if additional repair work outside the routine maintenance work is required | 50 | HR |
| 1006 | Time & Material -Spare Parts | 1 | LS |
| Government assessed amount during contract award for the procurement and delivery of Parts and Material for repair work IAW the PWS, Paragraph 5.2.3 | |||
| NOTE: THE AMOUNT FOR THIS CLIN WILL BE INSERTED AT TIME OF AWARD. |
(GOVERNMENT SET AMOUNT DO NOT INSERT PRICE FOR THIS CLIN)
| 1007 | Performance of On-Call Services / Troubleshooting | 5 | SV |
| Perfromance of On-Call Sevices and Troubleshooting IAW the PWS, Paragraph 5.4 |
| 1008 | Documentation | ||
| Create and maintain all required bi-weekly-, monthy, quarterly, semi-annual and annual statistics as well as the creation of an annual summary of all test results for the submission to the controlling authorities IAW the PWS | 1 | SV |
| Consolidation: | |
| CLIN 0001 (A001AA - A001AC) | € 0.00 |
| CLIN 0002 (A002AA - A002AY) | € 0.00 |
| CLIN 0003 (A003AA - A003AE) | € 0.00 |
| CLIN 0004 (A004AA - A004AD) | € 0.00 |
| CLIN 0005 T&M - Labor Hours | € 0.00 |
| CLIN 0006 T&M - Spare Parts (DO NOT INSERT PRICE FOR THIS CLIN) | € 0.00 |
| CLIN 0007 ON-Call-Services | € 0.00 |
| CLIN 0008 Documentation | € 0.00 |
| Total CLIN 0001 - CLIN 0008 | € 0.00 |
MMSL_2nd OY
| ELIN / PRICING Schedule |
| CONTRACT POP: 01 January 2023 - 31 December 2023 |
| 2nd Option Year (FY23) | ||||||
| CLIN | ELIN No | DESCRIPTION | QTY | U/I | UNIT | TOTAL |
| PRICE | AMOUNT | |||||
| EURO | EURO |
| 2001 | A001 | Measuring of Landfill Gas Emission at the Landfill Surface Are via Flame Ionization Detector (FID) IAW the PWS, Paragraph 5.2.1 - 5.2.1.3 | ||
| A001AA | Preparation of the landill surface are for measurement | 1 | EA | |
| A001AB | Measurement (FID) of the landfill gas | 1 | EA | |
| A001AC | Documentation | 1 | EA |
| 2002 | A002 | Flushing/Cleaning and Camera-Inspection of Underground Leachate Water Lines, Control Shafts and Collection Basins, Performance of Pressure- and Tightness Tests IAW the PWS, Paragraph 5.2.2 - 5.2.2.13 | ||
| A002AA | TV-Inspection of leachate water lines outside the sealed landfill area (total length - 880.7 meter) | 1 | SV | |
| A002AB | Semi-annual flushing and cleaning of leachate water lines (880.7 meters) outside the sealed landfill area | 2 | SV | |
| A002AC | Semi-annual flushing and cleaning of leachate water control shafts (30ea) outside the sealed landfill area | 2 | SV | |
| A002AD | Preparation of shaft documentation papers and sewer sections report | 28 | EA | |
| A002AE | TV-inspection of 8 each control drainage lines inside the sealed landfill area (total length-743 meter) | 1 | SV | |
| A002AF | Preparation of inspection reports for the control drainage lines inside the sealed landfill area | 8 | EA | |
| A002AG | TV-inspection of leachate water drainages inside the landfill area (total length - 991.1 meter) | 1 | SV | |
| A002AH | Semi-annual flushing and cleaning of the leachate water drainage lines (991,1 meters) inside the sealed landfill area | 2 | SV | |
| A002AI | Preparation of inspection reports of the Video inspected leachate water lines within the landfill area | 12 | EA | |
| A002AJ | Tightness inspection of leachate water carrying lines outside the sealed landfill area (total length-880.7 meter) | 1 | SV | |
| A002AK | Preparation of Tightness Test Protocols for each shaft | 28 | EA | |
| A002AL | Inspection of the leachate water control shafts for constructual and operational function/condition | 28 | EA | |
| A002AM | Reconsideration of tighness test if tests are negative | 3 | EA | |
| A002AN | Semi-annual cleaning services at the leachate water basin at Building 716 | 2 | SV | |
| A002AO | Flushing of storm sewer lines at the landfill entrance area (total length-749.13 meter) | 1 | SV | |
| A002AP | Cleaning of 18 ea shafts within the landfill entrance area | 1 | SV | |
| A002AQ | Flushing of storm sewer lines at the shredder plant facility Bldg. 710 and Bldg. 720 (557,12 meters) and the condensing water shaft (1) in front of Bldg.717 | 1 | SV | |
| A002AR | Pumping and cleaning of the reserve leachate water basin near Building 716 | 1 | SV | |
| A002AS | Semi-annual flushing of lines in filling field 18 (total length-31 meter) | 2 | SV | |
| A002AT | Semi-annual flushing, cleaning and inspection of leachate water control shafts (28 each) and the gas line collection shaft (1 each) at Bldg. 717 | 2 | SV | |
| A002AV | Flushing of the leachate water pressure lines (total length-1,329 meter) and cleaning of 15 each shafts | 1 | SV | |
| A002AW | Annual Measurement of the Inside Temperature of all leachate Water Lines | 1 | SV | |
| A002AX | Flushing and cleaning of the vehicle scale | 1 | SV | |
| A002AY | Recording and preparation video DVD's for all TV-Inspections | 1 | SV |
| 2003 | A003 | Maintenance and Inspection of the Lambda Container Degassing Unit CHC 10 inclusive Gas Torch IAW the PWS,Paragraph 5.2.3 - 5.2.3.2.5 | ||
| A003AA | Bi-weekly function control of the Gas Torch | 24 | SV | |
| A003AB | Quarterly Maintenece and Safety Inspection | 2 | SV | |
| A003AC | Semi-Annual control for damages of the gas control station and gas collectors | 1 | SV | |
| A003AD | Annual Maintenance and performance of the landfill gas analysis | 1 | SV |
| 2004 | A004 | Maintenance and Monitoring of the Landfill Gas Wells and Horizontal Pipes IAW PWS, Paragraph 5.2.4 - 5.2.4.5 | ||
| A004AA | Bi-Weekly servicing of 26 each Gas Wells | 24 | EA | |
| A004AB | Bi-Weekly servicing of 5 each Horizontal Gas Pipes | 24 | EA | |
| A004AC | Bi-weekly control and adjust Flap Position | 24 | EA | |
| A004AD | Bi-weekly control of 5 each Condensate Collection Vats | 12 | SV | |
| A004AD | Bi-weekly gas analysis | 24 | EA |
| 2005 | Time & Material - Labor Hours | ||
| Performance of repair work IAW the PWS Paragraph 5.3 | |||
| Contractor/ Subcontractor assessed hourly rate if additional repair work outside the routine maintenance work is required | 50 | HR |
| 2006 | Time & Material -Spare Parts | 1 | LS |
| Government assessed amount during contract award for the procurement and delivery of Parts and Material for repair work IAW the PWS, Paragraph 5.2.3 NOTE: THE AMOUNT FOR THIS CLIN WILL BE INSERTED AT TIME OF AWARD. |
(GOVERNMENT SET AMOUNT DO NOT INSERT PRICE FOR THIS CLIN)
| 2007 | Performance of On-Call Services / Troubleshooting | 5 | SV |
| Perfromance of On-Call Sevices and Troubleshooting IAW the PWS, Paragraph 5.4 |
| 2008 | Documentation | ||
| Create and maintain all required bi-weekly-, monthy, quarterly, semi-annual and annual statistics as well as the creation of an annual summary of all test results for the submission to the controlling authorities IAW the PWS | 1 | SV |
| Consolidation: | |
| CLIN 0001 (A001AA - A001AC) | € 0.00 |
| CLIN 0002 (A002AA - A002AY) | € 0.00 |
| CLIN 0003 (A003AA - A003AE) | € 0.00 |
| CLIN 0004 (A004AA - A004AD) | € 0.00 |
| CLIN 0005 T&M - Labor Hours | € 0.00 |
| CLIN 0006 T&M - Spare Parts (DO NOT INSERT PRICE FOR THIS CLIN) | € 0.00 |
| CLIN 0007 ON-Call-Services | € 0.00 |
| CLIN 0008 Documentation | € 0.00 |
| Total CLIN 0001 - CLIN 0008 | € 0.00 |
Sheet1
| CHANGE REQUEST |
| for Contract # W912PB-08-0014, 2nd Option |
| Following Line Item must be changed: | |||||
| ITEM | DESCRIPTION | QUANTITY | U/I | UNIT | TOTAL |
| Following Line Item must be changed: | |||
| 2003 | Operation of the Recycling Yard in | 2 | MO |
| accordance with Performance Work | |||
| Statement, para 2.5. | |||
| Operation days: Monday thru Saturday | |||
| Fixed Service |
Following Line Item must be added:
| 2010 | Operation of the Recycling Yard in | 10 | MO |
| accordance with Performance Work | |||
| Statement, para 2.5. | |||
| Operation days: Tuesday/Thursday/Saturday | |||
| Fixed Service |
File details come from the government source that posted it. Updated .