Price_Schedule.xlsx

XLSX spreadsheet 36 KB Posted

Attached to
Lift Station Plumbing Replacement
Solicitation number
140P6421Q0052
Issued by

View the file

Other files

File Type Posted
Technical_Questionnaire.pdf PDF
Past_Performance_Questionnaire.docx DOCX document
Wage_Determination.pdf PDF
Statement_of_Work.pdf PDF
Sol_140P6421Q0052.pdf PDF
Price_Schedule.pdf PDF
Technical_Questionnaire.docx DOCX document
Past_Performance_Questionnaire.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

UNITED STATES DEPARTMENT OF THE INTERIOR
National Park Services
Indiana Dunes National Park
Dunewood Campground : RV Dumping Lift Station
Bid Schedule
DESCRIPTIONLABORMATERIALEQUIPMENTSUB-TOTALGeneral AdministrativeOverheadProfitTotal
ITEM NO.DESCRIPTIONQNTY*UNITSPRICEAMOUNTQNTYUNITSPRICEAMOUNTQNTYUNITSPRICEAMOUNT
1Removal and disposal of the existing plumbing system.1LS$ - 0$ - 01LS$ - 0$ - 01LS$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
2Drain existing lift station and placed a confined spaced system to access the pipe system in the lift station area.1LS$ - 0$ - 01LS$ - 0$ - 01LS$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
3Install a new plumbing system Include all items from Appendix A, Table 1.1LS$ - 0$ - 01LS$ - 0$ - 01LS$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
4Final Pressure Test1LS$ - 0$ - 01LS$ - 0$ - 01LS$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
$ - 0
1SUBTOTAL$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
* All the quantities have been estimated. Is responsibility of the contractor to verify all the quantities and ensure to provide a bid that will cover the completion of the entire project.
CD =CREW PER DAYTotal =$ - 0
LS =LUMP SUMBid Bond (%) =$ - 0
LF =LINEAR FEETGrand Total =$ - 0
SF =SQUARE FOOTGeneral Administrative (%)0%
Overhead (%)0%
Profit (%)0%
Bid Bond (%)0.0%