Price_List_Closure_of_Groundwater_Monitoring_Wells.pdf

PDF 130 KB Posted

Attached to
Monitoring Well Closure, BIA, Tuba City Operating
Solicitation number
140A0925Q0059
Issued by

About this file

This document is a Price Schedule for a project involving the decommissioning of monitoring wells, likely for the Navajo Nation. The project is divided into three main tasks: Task 1 involves pre-work submittal, including a Health and Safety Plan and Work Plan/Work Schedule, with a payment to Navajo Nation Water Resources. Task 2 focuses on decommissioning monitoring wells, which includes locating nine specific monitoring wells (MW-15, 28, 32, 216, 301, 302, 303, 304, and 311), preparing the wells by removing protective covers, sealing the wells through casing removal and backfilling, and performing surface restoration. Task 5 involves drafting and finalizing a report with Professional Engineer (PE) Certification. The price schedule includes separate line items for AZGRT and NNGRT, suggesting potential involvement of these entities, with a Grand Total to be calculated based on the individual task costs.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TASK 1 Pre-work Submittal (includes draft and final)

1 Health and Safety Plan $

2 Work Plan/Work Schedule $

3 Navajo Nation Watr Resources Payment $

Task 2 Decommision Monitoring Wells

1 Mobilization/Equipment $

2 Locate nine (9) monitoring wells: MW-15, 28, 32, 216, 301, 302, 303, 304, and 311. $

3 Prep the wells. Remove any protective covers, caps, or other obstructions. $

4 Seal the wells. Casing Removal and Backfilling and Sealing. $

5 Surface Restoration. Fill area and restore to its orginal condition. $

Task 5 Reports

1 Draft and Finalize Report $

2 PE Certification $

SubTotal

AZGRT $

NNGRT $

Price Schedule

Grand Total