The Price Breakout Schedule is a detailed pricing document for the Green River Lock and Dam #1 Interlock Wiring and Equipment Installation project. The schedule outlines two base line items: (1) installing new electrical cable and associated components between operator control shacks, and (2) providing and installing new induction/proximity limit switches with associated wiring and mounting. The project is located in Reed, Kentucky, and is a firm fixed-price contract set aside for small businesses under NAICS code 237990, with a small business size standard of $45,000,000. The contract requires the contractor to furnish all personnel, equipment, supplies, and materials necessary for lock control system electrical component installation, with work to begin within 14 calendar days of the Notice to Proceed and conclude 180 calendar days after NTP.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE BREAKOUT SCHEDULE

LINE ITEM DESCRIPTION UNIT

COST

QTY ESTIMATED

COST

BASE ITEM 01 Install new electrical cable and all associated components between the operator control shacks.

$ JOB $

BASE ITEM 02 Provide new induction/proximity type limit switches and fabricate and install mounts for switches. Install wiring between switches and operator control shacks.

$ JOB $

TOTAL FOR BASE ITEMS: $