The file is a Price Breakdown Excel template for a construction project at the Saint Cloud VA Medical Center in Minnesota. The pricing schedule breaks down costs across multiple construction divisions, including General Building Construction, Mechanical and Electrical Systems, and Site Improvements. The template allows for detailed cost allocation across 34 specific divisional categories, with additional line items for profit, overhead, and a grand total proposal price.
The related federal contract opportunity is Solicitation Number 36C26325B0007_0005 for a remodel of Building 51-1 at the Eastside of the Saint Cloud VA facility. The solicitation is issued by the Department of Veterans Affairs Veterans Health Administration, with bids due on June 26, 2025, at 9:00 AM. Interested contractors should submit their proposals to Dwayne Brauch at dwayne.brauch@va.gov, and are advised to review all attachments and updated solicitation documents carefully.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26325B0007_1 6.17.2025a.pdf | ||
| Memory cabinet measurments.docx | DOCX document | |
| Questions Request Form 6172025_ae.doc | DOC document | |
| 36C26325B0007 0005.pdf | ||
| VAAR 852.219-75 Limitations on Subcontracting Cert of Compliance.pdf | ||
| Contractor Safety and EMR.pdf | ||
| 105113 METAL LOCKERS.pdf | ||
| 105113 METAL LOCKERS.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Price Schedule Breakdown Sheet |
| Project Title: |
| Project Number: |
| Contractor: |
| Division # | Division Title | Base Project |
| 1 | General Requirements | |
| 2 | Existing Conditions | |
| 3 | Concrete | |
| 4 | Masonry | |
| 5 | Metals | |
| 6 | Wood, Plastics and Composites | |
| 7 | Thermal and Moisture Protection | |
| 8 | Openings | |
| 9 | Finishes | |
| 10 | Specialties | |
| 11 | Equipment | |
| 12 | Furnishings | |
| 14 | Conveying Equipment | |
| Subtotal General Building Construction |
| 21 | Fire Suppression |
| 22 | Plumbing |
| 23 | Heating, Ventilating and Air Conditioning |
| 25 | Integrated Automation |
| 26 | Electrical |
| 27 | Communications |
| 28 | Electronic Safety and Security |
| Subtotal Mechanical and Electrical |
| 31 | Earthwork |
| 32 | Exterior Improvements |
| 33 | Utilities |
| 34 | Transportation |
| Subtotal Site Improvements |
Miscellaneous (Contractor shall identify any costs included)
| Subtotal All Divisions & Miscellaneous (if any) | |
| Profit | |
| Overhead | |
| Proposal Grand Total |