Price Breakdown 36C26127Q0026_2 B650 3rd and 2nd Flooring.xlsx
XLSX spreadsheet 12 KB Posted
- Solicitation number
- 36C26127Q0026
About this file
This is a Price Breakdown attachment for a federal construction solicitation (36C26127Q0026) issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 21. The price breakdown provides the cost structure template for the Replace B650 3rd and 2nd Flooring project (Project #612A4-27-018) at the Sacramento VA Medical Center in Mather, California. The breakdown organizes costs across multiple categories including project management and quality control oversight, mobilization, general requirements (Division 01), existing conditions demolition (Division 02), and finishes work (Division 09) such as subsurface preparation, gypsum board installation, resilient base and sheet flooring, resilient tile flooring, carpeting, and painting. Each line item is structured to capture material costs, equipment costs, and labor costs separately, with subtotals leading to a project grand total. The price breakdown also accounts for ancillary project costs including bonds, insurance, home office overhead, and profit margin.
The scope of work requires contractors to furnish all labor and materials for demolition, replacement, and installation of flooring, resilient base, stainless steel corner guards, and paint on the 3rd and 2nd floors of Building 650. All work must be performed outside normal working hours (7:30 AM to 4:00 PM, Monday through Friday) unless approved by the Contracting Officer, and contractors are responsible for waste disposal and compliance with VA infection control procedures. The attachment serves as the pricing template for bidders to submit their cost proposals for this construction project.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A - Price Breakdown 36C26127Q0026_2 - Project # 612A4-27-018, Replace B650 3rd and 2nd Flooring Attachment A - PRICE BREAKDOWN Description Material Equipment Labor Total
| Project Manager/QC |
| Superintendent/Safety |
| Mobilization |
| Division 01 - General Requirements |
| General Requirements |
| Shop Drawings, Product Data, and Samples |
| Safety Requirements |
| Reference Standards |
| Quality Control |
| Construction Waste Management |
| Sustainable Construction Requirement |
| Division 02 - Existing Conditions |
| Demolition |
| Division 09- Finishes |
| Subsurface Preparation for Floor Finishes |
| Schedule for Finishes |
| Gypsum Board |
| Resilient Base and Accessories |
| Resilient Sheet Flooring |
| Resilient Tile Flooring |
| Carpeting |
| Painting |
| Bonds |
| Insurance |
| Home Office Overhead |
| Profit |
SUB-TOTAL
PROJECT GRAND TOTAL