Preliminary_Site_Layout.pdf

PDF 925 KB Posted

Attached to
Architectural Design Services for Escambia County Area Transit (ECAT) Facility- CDBG-DR HS004
Solicitation number
PD 25-26.042
Issued by
Escambia County, Florida

About this file

This is a preliminary site layout document for the Escambia County Area Transit (ECAT) facility design update prepared by the Escambia County Board of County Commissioners in response to Hurricane Sally damage. The document outlines the comprehensive program requirements for a new single-story, approximately 55,000 square-foot ECAT complex located at 100 Clarinda Lane, Pensacola, Florida, consisting of four main components: an Administration Building, Bus Wash facility, Fuel Depot, and Maintenance Building. The facility design accommodates a fleet of 135 buses with capacity metrics including 27 buses per hour fueling operations across 4 stations, bus washing of the entire fleet daily, and 4 bus bays with 14 van bays for maintenance activities. Program components include fleet parking, private vehicle parking, administration and support areas with open and private offices, dispatch operations, driver facilities with lockers and training areas, maintenance bays for large fleet vehicles and vans, parts storage, electrical and mechanical support, and county vehicle maintenance areas. The preliminary layout incorporates route management considerations, frequency analysis, schedule integration, and site access points for both pedestrians and vehicles. Maintenance activities encompass scheduled periodic work, daily operations, warranty service, bodywork, brake repair, diagnosis and repair, tire service, lubrication, component overhaul, and painting. A pre-solicitation meeting was scheduled for January 29, 2026, with questions due by February 12, 2026, and proposals due by February 20, 2026.

The facility is designed to Enhanced Hurricane Protection Area (EHPA) specifications enabling it to function as an emergency operations distribution center and emergency shelter during catastrophic events while incorporating regional stormwater management to mitigate area flooding. Professional Architectural and Engineering Firms must provide design and limited construction administration services with at least one registered Florida architect and one civil engineer knowledgeable in local, state, and federal regulations. Proposals will be evaluated on experience with public mass transit facilities (40 points), personnel qualifications (20 points), personnel availability (30 points), and performance in avoiding change orders (10 points). The project is funded through Community Development Block Grant-Disaster Recovery (CDBG-DR) HS004 funds from the U.S. Department of Housing and Urban Development (HUD) representing recovery efforts from Hurricane Sally in September 2020. The procurement is subject to Section 3 of the Housing and Urban Development Act of 1968, requiring that 25 percent of total project hours be worked by Section 3 workers and 5 percent by Targeted Section 3 workers. The selected firm must obtain comprehensive insurance coverage including worker's compensation at statutory limits, general liability of $1,000,000 per occurrence/$2,000,000 aggregate, business auto liability of $1,000,000, and professional errors and omissions coverage of $1,000,000/$2,000,000, with contract award on an "all-or-none total" basis.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Escambia County Area Transit (ECAT)

Design Update Discussion 02.09.2026

New ECAT Facility

Program Verification

• Detailed Fleet Information

• APTA LOS Guidelines

• FTA Guidance

• Throughput of Fueling, Wash and Daily Service Functions (cleaning, cash)

• Program Components

• Fleet Parking

• Private Vehicle Parking

• Administration and

Support Areas

• Expansion or Phasing

Capability

• Site Access Points for Pedestrians and Vehicles

• Route Management

• Frequency

• Capacity of Buses

• Ridership

• Direction of Travel

• Connections

• Schedule

• Cross Streets

• Signalization

Factors in Right-Sizing the Facility

Program Verification

Fleet Maintenance Activities

MAINTENANCE ACTIVITIES

UNSCHEDULEDPERIODICDAILY

Warranty Service

Bodywork and Collision

Brake Repair

Other Diagnosis and Repair

Recommended Interval Inspection

Tire Service

Lubrication Service

Wiper Replacement

Bulb Replacement

Component Overhaul

Painting

ECAT

CAPACITY

METRICACTIVITY

27/ hour

= 5 hours

4 stations @ 24 per hour avg. (10 min.)

Buses per Hour

Fueling and Fare

Collection

--(30?)Buses per Hour

Bus Washing

Entire Fleet135 Buses Per Day

Interior Cleaning

Facility Design

Administration

Open Office

Private Office

Dispatch

Training

Driver/Operator

Facilities

Lockers

Changing

Showers

Lounge

Training

Building Support

Electrical

Mechanical

IT

Maintenance Bays

Large Fleet

Vehicles

Vans

Parts, Brakes, Tires, Storage

TRANSIT HUB

FLEET MAINT.

(4 BUS BAYS, 14 VAN BAYS)

ADMINISTRATION

FUEL WASH

COUNTY

VEHICLE

MAINT.

Facility Design