Preliminary Results~82.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
GNA Heritage Surveys for the Wallowa Valley Fuel Break
Solicitation number
S-62900-00010899
Issued by
Union County, Oregon

About this file

This file is a preliminary bid results spreadsheet (S-73000-00010900) dated September 12, 2024, comparing pricing submissions from two bidders—HP Civil Inc. and Aaken Corporation—for a construction project involving traffic management, pavement work, and erosion control. The project encompasses 42 line items including mobilization, temporary traffic control devices, temporary protection systems, pavement removal and replacement, asphalt paving, concrete barrier work, and intelligent transportation system (ITS) electrical installation. Estimated quantities range from unit items such as sequential arrow signs (2 each) to larger volume items including 14,000 linear feet of temporary striping, 440 tons of asphalt concrete pavement, and 8,900 linear feet of pavement marking tape. The bid contains no specified response deadline, site visit requirements, or bidder conference information in this preliminary results document.

HP Civil Inc. submitted a total bid of $847,121.00, while Aaken Corporation submitted a total bid of $1,072,099.11, representing a difference of approximately $224,978.11. Significant pricing variances between bidders appear on items including 18-inch subgrade stabilization (HP Civil at $1,500 versus Aaken at $28,500), aggregate base (HP Civil at $18,850 versus Aaken at $39,150), and ITS electrical system installation (HP Civil at $75,000 versus Aaken at $122,000). The document header indicates these are preliminary results and are not an indicator of award, suggesting that the final award determination remains pending. No incumbent vendor information, set-asides, or funding source details are provided in this preliminary bid results document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-00010900September 12, 2024 3:30 PM
Preliminary Results*HP Civil Inc.Aaken Corporation
ItemDescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1MOBILIZATION1.0LS$115,000.00$115,000.00$100,000.00$100,000.00
2TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC1.0LS$110,000.00$110,000.00$148,998.00$148,998.00
3TEMPORARY SIGNS1100.0SQFT$32.50$35,750.00$36.73$40,403.00
4SEQUENTIAL ARROW SIGNS2.0EACH$800.00$1,600.00$3,500.00$7,000.00
5PORTABLE CHANGEABLE MESSAGE SIGNS2.0EACH$3,000.00$6,000.00$4,800.00$9,600.00
6RADAR SPEED TRAILER2.0EACH$2,500.00$5,000.00$7,500.00$15,000.00
7TEMPORARY BARRICADES, TYPE III8.0EACH$150.00$1,200.00$197.75$1,582.00
8TEMPORARY PLASTIC DRUMS240.0EACH$45.00$10,800.00$62.00$14,880.00
9TEMPORARY DELINEATORS52.0EACH$55.00$2,860.00$84.75$4,407.00
10TEMPORARY REFLECTIVE PAVEMENT MARKERS670.0EACH$7.50$5,025.00$8.48$5,681.60
11TEMPORARY STRIPING14000.0FOOT$0.35$4,900.00$0.40$5,600.00
12STRIPE REMOVAL8000.0FOOT$0.85$6,800.00$0.96$7,680.00
13TEMPORARY BARRIER2300.0FOOT$17.00$39,100.00$18.70$43,010.00
14TEMPORARY IMPACT ATTENUATOR, NARROW SITE SYSTEM1.0EACH$3,500.00$3,500.00$3,390.00$3,390.00
15TEMPORARY IMPACT ATTENUATOR, TRUCK MOUNTED1.0EACH$6,500.00$6,500.00$12,500.00$12,500.00
16REFLECTIVE BARRIER PANELS600.0EACH$33.00$19,800.00$40.00$24,000.00
17REPAIR TEMPORARY IMPACT ATTENUATOR, NARROW SITE SYSTEM1.0EACH$6,500.00$6,500.00$5,650.00$5,650.00
18REPAIR TEMPORARY IMPACT ATTENUATOR, TRUCK MOUNTED1.0EACH$1,500.00$1,500.00$1.00$1.00
19CONSTRUCT AND REMOVE TEMPORARY ROADBED AND SURFACING1.0LS$55,000.00$55,000.00$67,671.20$67,671.20
20EROSION CONTROL1.0LS$500.00$500.00$3,500.00$3,500.00
21SEDIMENT BARRIER, TYPE 31100.0FOOT$4.00$4,400.00$8.31$9,141.00
22POLLUTION CONTROL PLAN1.0LS$500.00$500.00$1,500.00$1,500.00
23LEAD COMPLIANCE PLAN1.0LS$500.00$500.00$1,500.00$1,500.00
24CONSTRUCTION SURVEY WORK1.0LS$15,000.00$15,000.00$11,270.00$11,270.00
25ASPHALT PAVEMENT SAW CUTTING2300.0FOOT$6.00$13,800.00$3.50$8,050.00
26GENERAL EXCAVATION220.0CUYD$95.00$20,900.00$175.00$38,500.00
2718 INCH SUBGRADE STABILIZATION300.0SQYD$5.00$1,500.00$95.00$28,500.00
28SUBGRADE GEOTEXTILE300.0SQYD$3.00$900.00$6.00$1,800.00
29ADJUSTING INLETS3.0EACH$2,000.00$6,000.00$4,500.00$13,500.00
30CAPPING EXISTING CONCRETE STRUCTURES3.0EACH$3,000.00$9,000.00$5,635.00$16,905.00
31COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP800.0SQYD$7.00$5,600.00$6.22$4,976.00
32COLD PLANE PAVEMENT REMOVAL, 4 INCHES DEEP640.0SQYD$17.00$10,880.00$15.26$9,766.40
33AGGREGATE BASE290.0TON$65.00$18,850.00$135.00$39,150.00
34LEVEL 4, 1/2 INCH ACP440.0TON$245.00$107,800.00$253.00$111,320.00
35PG 70-22ER ASPHALT IN LEVEL 4, 1/2 INCH ACP21.0TON$1.00$21.00$0.01$0.21
36REMOVE AND REINSTALL EXISTING CONCRETE BARRIER, TALL970.0FOOT$30.00$29,100.00$32.77$31,786.90
37DELINEATORS, TYPE 530.0EACH$50.00$1,500.00$55.00$1,650.00
38MONO-DIRECTIONAL WHITE TYPE IAR MARKERS, RECESSED130.0EACH$60.00$7,800.00$62.15$8,079.50
39GAP PATTERN RUMBLE STRIPS0.2MILE$35,000.00$7,000.00$39,550.00$7,910.00
40PAVEMENT MARKING TAPE, GROOVED, PATTERNED, WET WEATHER8900.0FOOT$8.15$72,535.00$9.21$81,969.00
41ITS ELECTRICAL SYSTEM INSTALLATION1.0LS$75,000.00$75,000.00$122,000.00$122,000.00
42PERMANENT SEEDING0.3ACRE$4,000.00$1,200.00$7,571.00$2,271.30
TOTAL$847,121.00$1,072,099.11
*Preliminary Results are not an indicator of Award