Preliminary Bid Results~26.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- R1 Synthetic Ivy Pilot - I5 MP 304. 76-304. 93
- Solicitation number
- S-73000-00012353
- Issued by
- Multnomah County, Oregon
About this file
This preliminary bid results document from Oregon shows bid tabulations for the R1 Synthetic Ivy Pilot project along I-5 mile posts 304.76-304.93, with bids opened on January 14, 2025. The project involves the installation of synthetic ivy on existing sound walls, including traffic control and maintenance services. The scope includes installation of 7,000 square feet of Simplico Ivy and six months of monthly maintenance service, along with mobilization and temporary work zone traffic control requirements.
Two companies submitted bids for this project: DallumBuildCo LLC and Coast Industries Northwest Inc. DallumBuildCo LLC submitted the lower bid at $74,135.00, while Coast Industries Northwest Inc. bid $183,400.00. The significant price difference between the two bids was largely due to the unit price variation for the Simplico Ivy installation, with DallumBuildCo LLC bidding $6.18 per square foot compared to Coast Industries Northwest's $25.83 per square foot.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00012353 RFCQ Attachments.docx | DOCX document | |
| 00012353 RFCQ (1).docx | DOCX document | |
| Exhibit B - Sample Boilerplate Terms Personal Service Agreement.docx | DOCX document | |
| Exhibit 1 - Technical Specifications and Special Provisions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 1/14/25 | |||
| ITB No. | S-73000-00012353 | BIDDER | ||
| NAME: | DallumBuildCo LLC | Coast Industries Northwest Inc. | ||
| Bid Closing: | January 14, 2025 | CITY/STATE: | ||
| Description: | R1 Synthetic Ivy Pilot - I5 MP 304.76-304.93 | CCB#: | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $ 8,125.00 | $ 8,125.00 | $ - 0 | $ - 0 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $ 8,125.00 | $ 8,125.00 | $ - 0 | $ - 0 |
| 3 | Simplico Ivy, Complete | 7,000 | SQFT | $ 6.18 | $ 43,260.00 | $ 25.83 | $ 180,775.00 |
| 4 | Monthly Maintenance Service | 6 | Month | $ 2,437.50 | $ 14,625.00 | $ 437.50 | $ 2,625.00 |
| TOTAL | $ 74,135.00 | $ 183,400.00 |
File details come from the government source that posted it. Updated .