Preliminary Bid Results~15.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
US35 Mount Hood Asphalt Surface Maintenance
Solicitation number
S-73000-00011139
Issued by
Hood River County, Oregon

About this file

This document is a bid tabulation detailing the preliminary bid results for the ITB No. S-73000-00011139 for the US35 Mount Hood Asphalt Surface Maintenance project issued by the Oregon Department of Transportation (ODOT). The purpose of this Invitation to Bid (ITB) is to establish a contract for grinding and inlay paving, cold plane ACP removal, temporary and permanent pavement markings, and other related work. The bid closing date was August 22, 2024. The bid tabulation shows the unit pricing and total bid amounts submitted by three bidders: Jim Turin & Sons Enterprises, Knife River Corporation - Northwest, and Granite Construction Company.

The bid items included in the ITB are Mobilization, Traffic Control, Asphalt Grinding, and Level 3, 1/2" Dense, HMAC paving. The estimated quantities for each bid item are provided. This bid tabulation is not an indicator of award, but rather a summary of the bids submitted for consideration.

View the file

Other files

File Type Posted
RFP NBA Building HVAC Evaluation 24.07.29.pdf PDF
00011139_Invitation to Bid.docx DOCX document
Attachment B - Bid Pricing Form~25.xlsx XLSX spreadsheet
Attachment A - Special Provisions~34.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:8/22/24
ITB No.S-73000-00011139BIDDER
NAME:Jim Turin & Sons EnterprisesKnife River Corporation - NorthwestGranite Construction Company
Bid Closing:August 22, 2024CITY/STATE:
Description:US35 Mount Hood Asphalt Surface MaintenanceCCB#:
This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$ 30,000.00$ 30,000.00$ 18,500.00$ 18,500.00$36,990.60$ 36,990.60
2Traffic Control, Complete1LS$ 10,000.00$ 10,000.00$ 16,100.00$ 16,100.00$15,000.00$ 15,000.00
3Asphalt Grinding, 2 Inch Depth14,256SY$ 3.35$ 47,757.60$ 5.35$ 76,269.60$2.40$ 34,214.40
4Level 3, ½” Dense, HMAC1,592TON$ 132.00$ 210,144.00$ 150.75$ 239,994.00$175.00$ 278,600.00
TOTAL$ 297,901.60$ 350,863.60$ 364,805.00