ID FLAP FS SC MULTI(1), Custer Motorway Stabilization Project Federal contract opportunity
Solicitation number
69056725R000008
Issued by
Department of Transportation Federal Highway Administration

About this file

This document is a Presolicitation Notice for the Custer Motorway Stabilization Project issued by the Western Federal Lands Highway Division of the Federal Highway Administration. The project involves fill slope stabilization at two sites (Milepost 24.0 and 25.3) along the Custer Motorway in the Salmon Challis National Forest, with two bid schedules available: Schedule A covering MP 25.3 slide repair, and Schedule B covering both MP 24.0 and MP 25.3 slide repairs. The work will include stabilizing banks with buried log revetments and rebuilding slopes with reinforced soil techniques.

The solicitation is limited to six pre-approved prime contractors: ASCORP Inc., Granite Construction, Hamilton Construction, M.A. Deatley Construction, MJ Hughes Construction, and Thompson Contracting. Solicitation documents will be available during winter 2025/2026, with interested parties advised to monitor SAM.gov for the exact release date. Technical questions should be emailed to wfl.plansspec@dot.gov, and general questions can be directed to wfl.contracts@dot.gov or 360-619-7520. The project site may have limited accessibility due to snow, and prospective offerors are encouraged to view the location during fall as conditions permit.

View the file

Other files for this federal contract opportunity

Other files attached to ID FLAP FS SC MULTI(1), Custer Motorway Stabilization Project, newest first.
File Type Posted
Preliminary_ida-fs-sc-multi1_Plan.pdf PDF
PROJECT DESCRIPTION_ID FLAP FS SC MULTI(1).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Western Federal Lands Highway Division 610 E. Fifth Street

Vancouver, WA 98661 Phone 360-619-7700

Fax 360-619-7846

NOTICE TO PROSPECTIVE OFFERORS

RE: ID FLAP FS SC MULTI(1)

Custer Motorway Stabilization Project

Solicitation No. 69056725R000008

SPECIAL NOTICE RE: Idaho, Montana, and Surrounding Areas Multiple Award Task

Order Contract (MATOC).

THIS PRESOLICITATION NOTICE IS BEING POSTED ON SAM.GOV TO ANNOUNCE

THE UPCOMING PROJECT AND ASSIST POTENTIAL SUBCONTRACTORS BY

PUBLICIZING OPPORTUNITIES. A PROPOSAL WILL ONLY BE ACCEPTED FROM

THE PRIME CONTRACTORS LISTED BELOW.

Contract Number Contractor Name Phone

69056725D000002 ASCORP INC,

DBA DEBCO CONSTRUCTION

217 College Ave. STE 5

Orofino, ID 83544

208-476-3617

69056725D000003 GRANITE CONSTRUCTION

585 W Beach St.

Watsonville, CA 95076

360-606-1335

69056725D000004 HAMILTON CONSTRUCTION

2213 South F Street

Springfield, OR 97477

541-746-2426

69056725D000005 M.A. DEATLEY CONSTRUCTION, INC.

829 Evans Road

Clarkston, WA 99403

509-751-1580

69056725D000006 MJ HUGHES CONSTRUCTION, INC.

11510 NE 87TH AVE

Vancouver, WA 98662

360-314-2024

69056725D000007 THOMPSON CONTRACTING, INC

502 Gruber Rd.

Libby, MT 59923

406-293-5392

The attached preliminary plans are being furnished to aid prospective Offerors in identifying the location and type of work for this project. The project will be advertised during a period when viewing of the project may not be possible due to snow. Therefore, prospective Offerors are encouraged to view the project during fall as conditions permit. After October 1, access will be weather dependent; contact the Forest Service; Salmon Challis National Forest for current road

August 20, 2025

Preliminary Plans letter conditions at 208-879-4100. No Federal Highway Administration personnel will be available for show-me tours.

Two Bid Schedules - The work will be solicited under two alternate schedules, with different amounts of work in each schedule. One schedule will be awarded. See the Project Description document for additional details.

• Schedule A consists of MP 25.3 slide repair.

• Schedule B consists of MP 24.0 and MP 25.3 slide repair.

Project Location and Type of Work - All project work is located along Cuter Motorway in the

Salmon Challis National Forest.

This project consists of fill slope stabilization at two sites along the Custer Motorway (MP 24.0 and MP 25.3). The road is a narrow native material surfaced road with low ADT. The repairs will include stabilizing the banks with buried log revetments and rebuilding the slopes with reinforced soil slopes. The project includes two schedules as follows:

• Schedule A: MP 25.3

• Schedule B: MP 25.3 and MP 24.0

Technical Questions – All technical questions must be submitted by email wfl.plans-spec@dot.gov .

General Questions - Contact our office at wfl.contracts@dot.gov or at 360-619-7520.

Solicitation documents - Documents will be available during the winter of 2025/2026. Please monitor the SAM site (www.sam.gov) for actual date of solicitation release. To receive automatic notification through SAM, you must be logged in and select the “Follow” feature. For more information go to How do I follow items on SAM.gov?.

Thank you for your interest in this project.

mailto:plans-spec@dot.gov mailto:plans-spec@dot.gov mailto:wfl.contracts@dot.gov http://www.sam.gov/ https://www.fsd.gov/gsafsd_sp?id=gsafsd_kb_articles&sys_id=ad9c8da01bfbe1502fe5ed7ae54bcbc8

File details come from the government source that posted it. Updated .