PreBid Meeting Notes 11-6-2026_.pdf
PDF 277 KB Posted
- Attached to
- US101 At Market Ave Enhanced Crossing Project
- Solicitation number
- S-73000-00018254
- Issued by
- Coos County, Oregon
About this file
These Pre-Bid Meeting Notes document the mandatory pre-bid conference for the Oregon Department of Transportation's US 101 at Market Avenue Enhanced Crossing Project, Bid Number S-73000-00018254, held on November 3, 2026. The project involves installing temporary work zone traffic control, removing and constructing concrete curb ramps, sidewalks, and curbs, removing and replacing asphalt, installing striping and pavement markings, removing and installing signs, and installing a flashing beacon at US 101 and Market Avenue in Coos County, Oregon. The project is located at milepost 238.17 and requires substantial completion by March 31, 2027, with final completion by April 10, 2027. The mandatory pre-bid meeting was scheduled for November 3, 2026, at 11:00 a.m. at the project site. Bidders must submit questions or requests for clarification by November 5, 2026, at 2:00 p.m., with bid submissions closing on November 10, 2026, at 2:00 p.m. through OregonBuys. Preliminary results will be posted within one to two days of bid opening, and the intent to award will be posted within five business days unless otherwise notified.
Bidders must hold a valid Oregon Construction Contractors Board license and demonstrate previous experience with the type of work involved. Bid security is set at ten percent of the total bid amount, with performance and payment bonds each equal to one hundred percent of the awarded contract amount required upon award. Bidders must submit Form A-2 with total project cost pricing, Form A-1 and Form A-3 (bid bond) by the bid opening date, and Form A-4 (first tier subcontractor form) within two hours of bid closing or face bid rejection. The project follows the 2024 Oregon Standard Specifications for Construction and is subject to Bureau of Labor and Industries prevailing wage rates for Region 7 (Coos County), effective October 5, 2026. Liquidated damages are established at $600 per calendar day for each day beyond the substantial completion date. The project cost estimate is between $100,000 and $250,000 for bonding purposes and is funded with state funds. Key project contacts are Jessica Spann, ODOT Project Manager and Construction Administrator, at (541) 315-5999 or Jessica.Spann@odot.oregon.gov, and Terri Sinclair-Olson, ODOT Procurement & Contract Specialist, at (541) 957-3686 or Terri.Sinclair-Olson@odot.oregon.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00018254 Sample Contract.pdf | ||
| ESHIBIT 5 SPECIFICATIONS.pdf | ||
| Pre-bid location parking.pdf | ||
| Form A-2 Bid Pricing Form.xlsx | XLSX spreadsheet | |
| 00018254 Invitation to Bid.pdf | ||
| Pre-Bid Meeting Attendance Sheet.pdf | ||
| Form A-2 Bid Pricing Form R1.xlsx | XLSX spreadsheet | |
| EXHIBIT 6 PLANS.pdf | ||
| ESHIBIT 5 SPECIFICATIONS R1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting Notes
Project Name US101: AT MARKET AVE ENHANCED CROSSING
PROJECT
Bid Number S-73000-00018254 Mandatory Pre-Bid Date 11/3/2026 Time 11:00am – 11:30pm Location MP238.17 – Project Site Substantial Completion 3/31/2027 Final Completion 4/10/2027
CONTACTS
ODOT PROJECT MANAGER/
CONSTRUCTION ADMIN.: Jessica Spann (District Operations Coordinator)
CELL NUMBER: (541) 315-5999
EMAIL: Jessica.Spann@odot.oregon.gov
ODOT PROCUREMENT: Terri Sinclair-Olson (Procurement & Contract Specialist 3)
CELL NUMBER: (541) 957-3686
EMAIL: Terri.Sinclair-Olson@odot.oregon.gov
1. Introductions and Attendance
• Mandatory pre-bid meeting: all attendees must sign the attendance sheet.
• The following were in attendance:
i. Jessica Spann – ODOT
ii. Terri Sinclair-Olson – ODOT
iii. Jake Sweet – Knife River
iv. Ian Olson – Coastal Construction Services LLC
v. Mike Coplin – Skoyon Contracting LLC
vi. Randy Johnson – Brown Contracting Inc.
2. Project Completion dates
• Substantial Completion – March 31, 2027
• Final Completion – April 10, 2027
i. There were no issues with meeting the completion dates as discussed.
3. Plans / Specification Discussion
• Utility relocation - Coos Bay- North Bend Waterboard o Water Meter o Fire Hydrant o The Contractor shall notify, in writing, the Utilities listed in Section 00150.50 of the Special Provisions and Specifications, with a copy to the Project Manager, at least 14 Calendar Days before beginning the Work on the Project.
• Traffic Control o Note 2 on Sheet EA01 states “Work on one corner max, at an intersection at a time unless otherwise noted.”
o All traffic control items are to be included in the Temporary Workzone Traffic
Control, Complete bid item except for Flaggers, Flagger Station Lighting.
It was discussed; it is the contractor’s responsibility to make sure all traffic control items are accounted for and included in this bid item. There were no concerns with having the traffic control bid items underneath the lump sum bid item.
4. Procurement
• Terri Sinclair-Olson will discuss contractual obligations.
o Refer to attached document discussed during the meeting.
5. Questions and Other discussion topics
• Open discussion and questions from prospective bidders.
• Utility Relocations – Concrete and Asphalt Replacement
i. Question: Will the Coos Bay North Bend Water Board be responsible for replacing the concrete and the asphalt affected by its utility relocations?
1. Response: The Contractor will remove the existing asphalt and concrete at the affected corner to allow the Water Board to complete its utility relocation work. Following the relocation, the Water Board will backfill the excavated area with ¾”-0 aggregate and compact it. Once the backfill is complete, the Contractor will proceed with constructing the new ADA ramp, including the associated concrete and asphalt work.
• Coordination Regarding Existing Streetlights
i. Question: Can ODOT coordinate with the City of Coos Bay regarding the removal of two existing streetlights, including the potential removal of one light pole base and the removal of the antique style streetlight.
1. Response: This matter was discussed internally, and it was determined that the Contractor is responsible for bidding the project with the existing streetlights remaining in place and protected during construction.
As discussed during the meeting, Section 00150.50 requires the Contractor to coordinate with the appropriate utilities, including the City of Coos Bay. During this coordination, the Contractor may submit a written request to the city seeking authorization to have them remove the streetlights.
US101 At Market Ave Enhanced Crossing Project Install temporary work zone traffic control, remove and construct concrete curb ramps, sidewalks, and curbs, remove and replace asphalt, remove and install striping, legends, pavement bars, remove and install signs, install flashing beacon located at US101 and Market Avenue in Coos County Oregon.
A. SOLICITATION TIMELINES:
1. Deadline for questions or requests for clarification due by 11/5/2026 @ 2:00 pm.
2. Bid opening via Team. Link in document. Bidding closes 11/10/2026 @ 2:00 PM
3. Preliminary results will be posted at ODOT’s earliest convenience typically within a day or two. If all bids are over available funds, and ODOT decides to rebid, results will not be posted.
4. Intent to award will be posted within 5 business days of the bid opening date unless otherwise notified.
B. LICENSING REQIREMENTS:
1. This project requires you to be licensed with the State of Oregon Construction Contractors Board including any sub-contractors.
2. Bidder must demonstrate previous experience with the type of work of this project.
C. SUBMITTAL REQUIREMENTS: SECTION C in ITB document.
1. Bid pricing must be submitted on Form A-2 on the Attachments Tab in OregonBuys AND you must enter your TOTAL PROJECT COST under the Items Tab in OregonBuys?
2. Answer questions in Questions Tab in OregonBuys.
3. Bidder must select yes on terms and conditions tab in OregonBuys or bid will be rejected.
4. Bidder must submit completed Competitive Quote Form A-1, and A-3 (Bid Bond) no later than the Bid Opening Date and Time specified in the RFCQ in OregonBuys.
5. Bidder must submit Form A-4 (1st tier subcontractor form) within 2 hours of bid closing date and time or bid will be rejected. (Make sure you input all information requested in all columns and categories) It is required even if you have no subcontractors. If the First Tier Form is not included in the quote package you can email to the single point of contact Terri Sinclair-Olson.
6. All documents required to be filed out and submitted shall be loaded into OregonBuys into the attachments tab with the submitted bid.
7. Reference sheets need to be filled out and completed providing contact information dates name and location of projects for ODOT to check responsibility.
8. Make sure you read the ITB documents for ALL REQUIRED SUBMITTALS this list may not be all inclusive.
D. BID ADDENDUM:
1. Addendum may come forward it is bidders responsibility to ensure that ALL Addendum are known/acknowledged. Addendum if posted can be found in the Amendments tab in OregonBuys for the solicitation.
2. No changes to requirements of project unless specifically identified by Addendum.
E. OBTAINING PLANS AND SPECIFICATIONS:
1. OregonBuys Attachments Tab.
2.
This is a prevailing wage rate project. Coos County BOLI Region 7.
F. VENDOR SUPPORT FROM ODOT:
1. Oregon Department of Transportation : Contracting with ODOT : Procurement :
State of Oregon For additional support, contact Melissa Lovejoy, 503-951-2574, or by email, or leave a message at 503-951-2649 https://www.oregon.gov/odot/business/procurement/pages/howto.aspx https://www.oregon.gov/odot/business/procurement/pages/howto.aspx mailto:melissa.e.lovejoy@odot.oregon.gov?subject=ORBuys%20Vendor%20Support
File details come from the government source that posted it. Updated .