Pre-bid Meeting Notes - Wellmaster Newaygo Mecosta Well Plugging Project 2026.docx
DOCX document 22 KB Posted
- Solicitation number
- DS 761 270000000007 2
- Issued by
- Oceana County, Michigan
About this file
This is a pre-bid meeting notes document for the Wellmaster Newaygo & Mecosta Orphan Well Plugging Project administered by the State of Michigan's GRMD (likely Geological and Environmental Assessment Division or similar). The project involves the plugging of two orphan wells—Troyer 1-7A and Danials 1-1B—located in Newaygo and Mecosta Counties, along with associated site restoration activities. Six contractor representatives from companies including EXCEL Site Rentals, Plants & Goodwin, Taplin, Mid-State Oil Tools, TEAM Services, and McConnell & Scully attended the November 10, 2026 pre-bid meeting held at noon. The State provided site visits to both well locations to allow contractors to evaluate access and gather field information for bidding purposes. Contractors were instructed to use line-item pricing from Schedule B Pricing Matrix rather than turn-key pricing and to submit detailed project timelines as part of their bids. No questions were generated during the pre-bid meeting.
The project utilizes Davis-Bacon Prevailing Wage requirements that all contractors must follow. Bidders are required to complete the Schedule B Pricing Matrix thoroughly with unit pricing and may add line items for additional work deemed necessary to complete the scope. Weekly pay certifications must be completed accurately and correctly, as invoice processing cannot proceed without verified pay certification. The project timeline submitted with bids is an important evaluation factor in determining best value for the State of Michigan. Specific bid due dates and question submission deadlines were covered during the meeting, with contractors directed to thoroughly review the RFP and well plugging instructions (ACOWS) prior to submitting their proposals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WELLMASTER NEWAYGO & MECOSTA ORPHAN WELL PLUGGING PROJECT – (NEWAYGO AND MECOSTA COUNTIES)
PRE-BID MEETING CONTRACTOR SIGN IN SHEET
November 10, 2026 (Started at Noon)
| NAME |
| COMPANY |
| PHONE |
| Jordan Birgy |
| EXCEL Site Rentals (Taplin Sub.) |
| 231-384-2460 |
| Mike Fritz |
| Plants & Goodwin |
| 989-630-7885 |
| Steve Minella |
| Taplin |
| 269-903-5725 |
| Mike Machuta |
| Mid-State Oil Tools |
| 989-330-3106 |
| Bryan Ingersoll |
| TEAM Services |
| 231-384-5676 |
| Kevin Smith |
| McConnell & Scully |
| 517-795-6539 |
QUESTIONS GENERATED DURING PRE-BID MEETING
1. No questions from contractors were generated during Pre-Bid Meeting.
GRMD Staff Present: Keith Kidder (ran meeting), Tola Jolayemi, and Lauren Phelps.
Keith – opened meeting at 12:00 pm Noon, and covered:
1. Stated that this pre-bid was for the Wellmaster Newaygo and Mecosta County Orphan Well Plugging Project that includes the plugging of 2 orphan wells (Troyer 1-7A, and the Danials 1-1B), and site restoration activities. I stated that is project is NOT turn-key pricing. Contractors are to review the scope of work and use line-item pricing from the Schedule B Pricing Matrix for this project. Contractors were shown both well locations by the State of Michigan, so that they had an opportunity to gather information for submitting a competitive bid.
2. Went over important dates when questions were to be submitted to the State, when answers to questions would be posted, and when bids were due to the State for this project. I encouraged all contractors to thoroughly review the RFP for important details related to this project. I instructed them to review the well plugging instructions as well as the Schedule B Pricing Matrix. I went over the basic details in each well plugging instruction (ACOWS), so that the contractors were familiar with the well construction of each well.
3. I also instructed them to fill out completely the Schedule B Pricing Matrix so that unit pricing is known in the event a change or amendment is needed in the future. I also noted that contractors can add line items to the bid table, if they need to include pricing of other items not listed in the Schedule B Pricing Matrix that they think we would need to complete the scope of work.
4. I informed the contractor group that this project will utilize Davis-Bacon Prevailing Wage (DBPW) requirements and that all contractors are to follow all requirements and regulations related to DBPW.
5. I strongly encouraged contractors to make sure that pay certifications are completed weekly, accurately, and correctly. I also noted that invoicing cannot be processed until Pay Certification is verified.
6. I instructed contractors to provide a Project Timeline as part of the bid and that it should be very detailed and clearly describe the proposed work activities, rig availability, personnel availability, and how the contractor would complete this scope of work efficiently and provide best value to the State of Michigan. A complete and detailed timeline is an important factor in determining ‘best value’ when selecting a winning vendor.
Vendors were able to observe site conditions at both well locations, evaluate access, and collect information in the field so that they could submit a competitive bid to the State. Vendors were off location by 1:30pm, Keith K. and GRMD staff left the Pre-Bid Meeting at 2:00 pm.