This is a Statement of Work (SOW) for the supply and installation of a surface water drainage system at the U.S. Embassy Annex Compound in Pretoria, South Africa. The contractor must supply, install, test, and commission a linear channel drainage system of approximately 100 linear meters using polymer-concrete channels and composite gratings rated for load class B125 or an equal product. The scope includes connecting the system to existing stormwater infrastructure and restoring all disturbed surfaces. The contractor must also provide a second option featuring a larger capacity drainage channel than specified in the primary SOW.
Work must be performed exclusively on weekends (Saturdays and Sundays) or after December 15th when weekday work will be permitted. A mandatory site meeting is scheduled for December 7, 2026 at 10:00 AM at 100 Totius Street, Groenkloof; expressions of interest to attend must be submitted by December 3, 2026. Tenders are due by close of business on December 10, 2026. All submissions and correspondence should be directed to pretoria_quotations@state.gov and kriekjx@state.gov with reference PR16370157. The U.S. Embassy issues fixed-price contracts only with no deposit payments authorized; contractors must confirm prices remain fixed and must absorb any fluctuations in currency or material costs. Payment will be made via electronic funds transfer (EFT) within 30 calendar days after delivery and receipt of goods and services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation provision and clauses.docx | DOCX document |
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work: Supply and Installation of a Surface Water Drainage System, USRAP Village, U.S. Embassy Annex Compound, Pretoria
1. Background The U.S. Embassy Pretoria needs a surface water drainage system in the USRAP Village area of the U.S. Embassy Annex Compound. The system will collect stormwater and surface runoff and carry it to the existing stormwater network.
2. Objective The Contractor will supply, install, test and commission a linear channel drainage system of about 100 linear metres. The system will use polymer-concrete channels and composite gratings rated for load class B125, or an equal product. The Contractor will also connect the system to the existing stormwater infrastructure and restore all disturbed surfaces.
3. Place of Performance USRAP Village, U.S. Embassy Annex Compound, [street address], Pretoria, Gauteng, South Africa. The exact drain alignment appears on [Attachment A – Site Plan/Drawing].
4. Materials and Specifications The Contractor will supply the following materials, or approved equals:
| # |
| Item |
| Specification |
| Qty |
| Unit |
| 1 |
| Channel drain |
| ACO MultiDrain 100, 15.0, H22.5, 1000 mm length (or equal) |
| 100 |
| Each (≈100 m) |
| 2 |
| End cap |
| End cap V100, galvanised |
| 2 |
| Each |
| 3 |
| End cap with seal |
| ACO Multiline V100S 0 end cap with seal, W100 D110, galvanised edge (or equal) |
| 1 |
| Each |
| 4 |
| Grating |
| ACO Composite black grating, 0.5 m, Drainlock locking, Microgrip anti-slip surface, load class B125 (or equal) |
| 200 |
| Each (≈100 m) |
| 5 |
| Ancillaries |
| Outlets, connectors, sealants, concrete, reinforcement (if required) and fixings needed for a complete working system |
| As required |
| Lot |
Material requirements:
· All materials must be new and undamaged, and they must come from one manufacturer's system so the parts are compatible.
· Gratings must meet load class B125 at minimum. This class covers pedestrian areas and light vehicles. If vehicles heavier than passenger cars, such as delivery trucks or emergency vehicles, will cross the drain, the Contractor must propose a higher load class.
· Gratings must use a bolt-free locking system (Drainlock or equal) and an anti-slip surface.
· The Contractor must get written approval from the Contracting Officer's Representative (COR) before substituting any material.
5. Scope of Work
5.1 Pre-Construction
1. Visit the site with the COR and confirm the alignment, levels, falls, outlet points and how the drain will connect to the existing stormwater network.
2. Detect and mark all underground utilities (electrical, water, sewer, telecommunications, irrigation and security systems) before any excavation. Do not excavate until the COR approves the utility survey.
3. Submit the deliverables listed in Section 11 and get approval for them before mobilizing.
5.2 Supply and Delivery
1. Buy and deliver all materials to the site in protective packaging.
2. Coordinate delivery times with the COR so security screening of delivery vehicles can be arranged.
3. Store materials only in the laydown area the COR designates.
5.3 Installation
1. Saw-cut and remove existing asphalt, paving, concrete or landscaping along the approved alignment.
2. Excavate trenches to the depth and width the manufacturer specifies for the channel and load class.
3. Lay a concrete bed and haunch the channels in concrete. Follow the manufacturer's installation instructions for load class B125 for concrete grade, bed thickness and haunch dimensions.
4. Lay the channels to the approved line and level. Make sure water flows steadily toward the outlet points without ponding.
5. Fit end caps at the ends of each run. Fit the sealed end cap where a watertight end is needed.
6. Connect the outlets to the existing stormwater system with compatible pipework and fittings.
7. Set the grating tops slightly below the surrounding finished surface, as the manufacturer recommends, and lock all gratings in place.
5.4 Reinstatement
1. Restore all disturbed paving, concrete, asphalt, curbing and landscaping so it matches the existing finish and level.
2. Repair any damage to existing structures, utilities or finishes caused by the work, at no cost to the U.S. government.
5.5 Testing and Commissioning
1. Flow-test each run with water while the COR watches, to show that water drains freely to the outlets with no ponding or leaks.
2. Check that every grating is secure, level and fits flush with no rocking.
5.6 Cleanup
1. Clean the site at the end of every shift and leave it safe for pedestrians and residents.
2. Remove all spoil, packaging and construction debris from the compound, and dispose of it lawfully.
3. Flush all channels clear of debris before final inspection.
6. Work Hours and Scheduling
1. The Contractor will do the work outside normal business hours, mainly on weekday evenings and at weekends. The COR will approve the exact work windows.
· Weekday after-hours: [e.g., 17:30–06:00]
· Weekends: [e.g., Saturday 07:00 – Sunday 18:00]
2. Submit a work schedule at least 5 working days before each work period.
3. Give enough artificial lighting for safe work and safe site conditions at night.
4. Keep noise and disruption low, because the USRAP Village may be occupied. Do the noisiest work, such as saw-cutting and compaction, only during the hours the COR approves.
5. Leave no open trenches unprotected at the end of a shift. Cover, barricade and light all excavations, or backfill them temporarily.
6. Keep pedestrian access to occupied facilities safe at all times, or put in place alternative routes that the COR has approved.
7. Security Requirements
1. Submit the names, identity or passport numbers, and other required details for all personnel and vehicles at least 2 working days before access is needed, so the Embassy can complete security vetting. Only vetted personnel may enter the compound.
2. Follow all compound access, screening and escort procedures set by the Regional Security Office (RSO). Escorts may be needed during after-hours and weekend work, so schedule work only within the escort windows the COR confirms.
3. Do not take photographs on the compound unless the COR approves them in writing.
4. Personnel must stay inside the designated work area and approved access routes.
5. Do not disturb, move or damage any security equipment, barriers, cabling or lighting. Report any conflict with these systems to the COR at once.
8. Safety and Compliance
1. Follow the South African Occupational Health and Safety Act and its Construction Regulations, as well as all Embassy safety requirements.
2. Submit a site-specific health and safety plan and a risk assessment. These must cover night work, excavation, saw-cutting, manual handling and protection of the public.
3. Assign a competent site supervisor who is present at all times while work is in progress.
4. Give all personnel the right personal protective equipment, including high-visibility clothing for night work.
9. Government Responsibilities The U.S. government will:
1. Provide a COR to coordinate and oversee the work.
2. Arrange security vetting, compound access and escorts for approved personnel.
3. Designate a laydown area and access routes.
4. Provide existing site drawings and utility information, where available.
5. Provide water and electricity for construction use.
10. Inspection and Acceptance
1. The COR will inspect the work at these hold points:
· utility survey complete, before excavation
· channels bedded and levelled, before concrete haunching is completed
· flow test
· final inspection after reinstatement and cleanup
2. The Contractor will fix any defects or non-conforming work within 10 working days at no cost to the U.S. government.
3. Acceptance happens when the COR confirms in writing that the system is complete, tested, reinstated and clean.
11. Deliverables
| # |
| Deliverable |
| Due |
| 1 |
| Personnel and vehicle list for security vetting |
| 2 working days before mobilization |
| 2 |
| Work plan, method statement and schedule |
| 5 working days before mobilization |
| 3 |
| Health and safety plan and risk assessment |
| Before mobilization |
| 4 |
| Manufacturer product data sheets and installation instructions |
| Before mobilization |
| 5 |
| Utility detection survey results |
| Before excavation |
| 6 |
| Progress photographs (taken in approved areas only) |
| Weekly |
| 7 |
| As-built drawing showing alignment, levels and outlet connections |
| Within 10 days of completion |
| 8 |
| Warranty certificates |
| At final acceptance |
12. Warranty
1. The Contractor will guarantee workmanship for at least [12] months from final acceptance.
2. The Contractor will pass all manufacturer material warranties to the U.S. government.
13. Period of Performance The Contractor will complete all work within 30 calendar days of the notice to proceed. This period includes material lead time.
14. Points of Contact
· COR: Hendrik Zwiegelaar – zwiegelaarhj@state.gov