SCOPE OF WORK Residential gates.docx
DOCX document 748 KB Posted
- Attached to
- Removal and Replacement of Vehicle Sliding Gates
- Solicitation number
- PR16273426
- Issued by
-
Department of State US Embassy Pretoria
About this file
This is a Scope of Work (SOW) for the removal and replacement of vehicle sliding gates at three U.S. Government-owned properties located at 54 6th Ave Houghton, 44 Green Acres Birdhaven, and 7 Trebyam Edenburg. The contractor shall design, furnish, and install three new vehicle sliding gates while removing existing gates, with all work performed in compliance with UL 325: Standard for Safety - Door, Drapery, Gate, Louver, and Window Operators and Systems, subject to design review and approval by the Regional Security Officer (RSO).
The scope encompasses site surveys, detailed design drawings (including site plans, structural details, electrical schematics, and safety device layouts), demolition and removal of existing gates with proper disposal, civil works including excavation and concrete foundations, electrical installation with control panels and UL 325-required safety devices (non-contact sensors, contact sensors, entrapment protection), and gate supply and installation with appropriate warning signage. The contractor must conduct full functional testing and joint acceptance testing with the RSO, provide UL 325 compliance certification, as-built drawings, operation and maintenance manuals, and warranty documentation. Contractor qualifications must include demonstrated experience with UL 325-compliant vehicle gate systems at government or high-security facilities, proper licensing and insurance, and personnel subject to security vetting. The contract is fixed-price with no deposit payments authorized and payment via EFT within 30 calendar days after delivery and invoice receipt. The solicitation closing date is 5:00 p.m. on 10 December 2026, with a mandatory site meeting on 3 December at 10:00 a.m.; quotes must reference PR16273426 and be submitted to pretoria_quotations@state.gov and kriekjx@state.gov. The U.S. Embassy Pretoria, Department of State, is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation provision and clauses.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK (SOW)
Removal and Replacement of Vehicle Sliding Gates at Three U.S. Government-Owned Properties
1. Purpose This Scope of Work (SOW) establishes the requirements for a contractor to remove three (3) existing vehicle sliding gates and design, furnish, and install three (3) new vehicle sliding gates at three U.S. Government-owned properties located at:
· Site 1: 54 6th Ave Houghton
· Site 2: 44 Green Acres, Birdhaven
· Site 3: 7 Trebyam, Edenburg All work shall be performed in full compliance with UL 325: Standard for Safety – Door, Drapery, Gate, Louver, and Window Operators and Systems, and shall be subject to design review and final approval by the Regional Security Officer (RSO) or designee.
2. Background The existing vehicle sliding gates at the above properties have reached the end of their service life and/or do not meet current safety and security standards. The Department requires removal of the existing gates and installation of new, code-compliant vehicle sliding gate systems, including all associated civil, structural, electrical, and control system works necessary for full operational functionality.
3. Scope of Services
3.1 Design Phase
1. The Contractor shall conduct a site survey of all three properties to verify existing conditions, dimensions, utility locations, and structural constraints.
2. The Contractor shall prepare detailed design drawings for each site, including but not limited to:
· Site plans showing gate location, swing/slide clearances, and vehicle approach/queuing areas
· Structural details (foundations, tracks, columns, gate framing)
· Electrical schematics (power supply, operator wiring, control panel, safety devices, lighting if applicable)
· Gate operator specifications and manufacturer cut sheets
· Safety device layout (photo eyes, edge sensors, loop detectors) per UL 325 requirements
· Anti-tailgating/anti-climb features, as applicable to security requirements
3. All design drawings and specifications shall be submitted to the RSO (or designated Diplomatic Security representative) for review and written approval prior to commencement of any construction or procurement activity.
4. The Contractor shall incorporate any RSO-requested revisions and resubmit for approval until final sign-off is obtained.
5. No construction, demolition, or procurement of long-lead items shall proceed without documented RSO design approval.
3.2 Demolition and Removal
1. Safely disconnect, remove, and dispose of the three existing vehicle sliding gates, including gate panels, tracks, operators, control panels, and associated hardware, at each site.
2. Cap or safely isolate existing electrical service connections in accordance with applicable electrical codes.
3. Properly dispose of all removed materials in accordance with local environmental regulations and Post's waste disposal procedures.
4. Restore any surfaces disturbed during removal to a safe, level condition in preparation for new installation.
3.3 Civil Works
1. Excavation, grading, and foundation work as required to support new gate tracks, columns, and operator pads.
2. Concrete foundations, footings, and pads sized per manufacturer and structural engineering requirements.
3. Repair and reinstatement of paving, curbing, drainage, and landscaping disturbed by construction.
4. Installation of conduit runs and trenching for electrical and control cabling.
3.4 Electrical Works
1. Supply and installation of electrical service to each gate operator, including disconnects, breakers, and grounding in accordance with the National Electrical Code (NEC) or host-country equivalent, as applicable.
2. Installation of gate operator control panels, wiring, and all safety interlocks.
3. Installation and testing of all UL 325-required safety devices, including but not limited to:
· Non-contact sensors (photo eyes)
· Contact sensors (safety edges)
· Inherent entrapment protection within the gate operator
4. Installation of access control interfaces (card readers, keypads, remote controls) as required to integrate with existing site security systems, coordinated with the RSO.
5. Testing of all electrical connections, grounding, and control functions prior to final commissioning.
3.5 Gate Supply and Installation
1. Furnish and install three (3) new vehicle sliding gates, including gate panels, tracks, rollers, guides, and stops.
2. Furnish and install UL 325-listed gate operators sized appropriately for gate weight, length, and frequency of use (commercial/industrial duty classification, as applicable).
3. All gate systems shall include required UL 325 entrapment protection for the applicable gate class, and shall not rely on operator-only protection where secondary safety devices are required by the standard.
4. Install appropriate warning signage as required by UL 325 (e.g., "Automatic Gate" warning placards).
4. UL 325 Compliance Requirements The Contractor shall ensure that the complete gate and operator system complies with the current edition of UL 325, including but not limited to:
· Proper classification of gate operators (Class I, II, III, or IV) based on intended use and location
· Provision of primary and secondary entrapment protection devices appropriate to the gate class
· Compliance with force and pressure limits for gate operators
· Proper signage and labeling as required by the standard
· Functional testing of all safety devices prior to final acceptance The Contractor shall provide manufacturer documentation and UL 325 listing certificates for all gate operators and safety devices supplied under this contract.
5. Testing, Commissioning, and Acceptance
1. Upon completion of installation at each site, the Contractor shall perform full functional testing of the gate system, including all safety devices, access control integration, and manual/emergency release mechanisms.
2. The Contractor shall conduct a joint acceptance test with the RSO or designated Post representative at each site.
3. The Contractor shall provide a UL 325 compliance certification for each installed system.
4. Final acceptance shall be contingent upon written RSO sign-off confirming the gate system meets design specifications and UL 325 requirements.
Inspection Requirements to be signed off by COR
1. Are warning signs installed and visible from both sides?
2. Are guideposts installed and securely fixed to the ground?
3. Are two non-pinch rollers fitted on the interior of the guidepost?
4. Are gaps between vertical bars less than 57mm?
5. Does the gate have an edge sensor on the trailing edge of the gate?
6. Are photo eye sensors (emitter or reflector) installed in the open position?
7. Are physical stops installed at both open and closed positions?
8. Is the gate controller system grounded?
9. Are photo eye sensors (emitter or reflector) installed in the closed position?
10. Does the gate have an edge sensor on the leading edge of the gate?
11. Pedestrian gate installed near the sliding gate?
12. Is the pedestrian gate clearly designated?
13. Are access control devices at least six ft/1.8 meters beyond the gate?
14. Are additional draw-in zones protected with edge sensors?
15. Entrapment zones in public areas have a fence installed of 1.2 meters of height?
6. Deliverables
1. Site survey reports (all three sites)
2. RSO-approved design drawings and specifications (all three sites)
3. Manufacturer cut sheets and UL 325 listing documentation for gates, operators, and safety devices
4. As-built drawings following installation
5. UL 325 compliance certification for each site
6. Operation and maintenance (O&M) manuals for all installed equipment
7. Warranty documentation
7. Schedule [Insert required project milestones, e.g., design submission deadline, RSO approval turnaround, construction start/completion dates per site]
8. Contractor Qualifications
1. Demonstrated experience installing UL 325-compliant vehicle gate systems at similar (preferably government or high-security) facilities.
2. Licensed and insured to perform civil, structural, and electrical work in the host country/jurisdiction.
3. Personnel shall be vetted/cleared as required by Post security procedures prior to site access.
9. Security Requirements
1. All Contractor personnel shall comply with Post access control and security procedures, as directed by the RSO.
2. Any changes to gate design, location, or security features during construction shall require prior RSO approval.
3. The Contractor shall coordinate all site access and working hours with Post management to minimize disruption to operations.
10. Design concept drawings image6.jpeg image7.jpeg image8.jpeg image1.png image2.png image3.jpg image4.jpeg image5.jpg