SOW sky light tinting atrium (1).doc

DOC document 1 MB Posted

Attached to
Skylight Tinting CWA @ COB
Solicitation number
PR16174246
Issued by

About this file

This is a Statement of Work (SOW) for maintenance and repair services at the U.S. Consulate General in Frankfurt, Germany. The project involves skylight tinting at the Consulate's atrium, requiring the contractor to furnish all materials, equipment, and labor to clean existing atrium glass panels and apply sun protection film (specifically Bruxsafol solar heat reduction product) to windowpanes exceeding 3 square meters each. The work must comply with international codes and standards including the OBO Building Code, National Fire Prevention Association standards, International Building Code, and applicable OSHA regulations. Work is to be performed during normal U.S. Consulate business hours (0800-1630 Monday-Friday, excluding holidays) unless alternate hours are approved by the Contracting Officer's Representative (COR).

The total period of performance is 58 calendar days from award, with pre-construction submittals due within 20 days (including insurance, schedule, and product data sheets), government review within 10 days, material procurement spanning 28 days (21 days for ordering, 7 days for shipping), and mobilization/construction phases requiring crew information submission 5 days in advance. The contractor must provide a German and English-speaking Project Site Manager approved by the COR and is responsible for quality control, site protection, waste management, and restoration of the work area. All contractor personnel require Visit Authorization Requests (VAR) prior to entry, and personnel must complete mandatory online safety briefings before commencing work. The contractor bears responsibility for any damage to government property and must document pre-existing conditions prior to project start.

View the file

Other files

File Type Posted
Picture CWA Glassroof.docx DOCX document
Info-Flachglasfolien.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAINTENANCE & REPAIR STATEMENT of WORK Frankfurt, Germany Sky Light Tinting Atrium

CONTENTS:

PART ONE

GENERAL

PART TWO

PRODUCTS

PART THREE

EXECUTION

PART FOUR

SCHEDULE

PART FIVE

ATTACHMENTS

U.S. CONSULATE GERNERAL FRANKFURT, GERMANY

FACILITY MANAGEMENT

PART ONE – GENERAL

C.1.1

SUMMARY:

A. The U.S. Consulate General Frankfurt has a requirement of sky light tinting located at the Atrium of the Consulate General Frankfurt. The Contractor shall furnish all materials, equipment, and labor required to complete the work. The proposed scope of work includes, but is not limited to, the following:

1. Clean atrium glass panels

2. Apply sun protection on existing glass panels C.1.2

SUBMITTALS:

A. Contractor’s crew individual identification information for visitor access requests.

B. Submit list of all subcontractors with evidence of subcontractor's insurance coverage.

C. Project schedule showing work phasing and proposed daily progress.

D. Material manufacturers and accessory product data sheets in accordance with part two.

E. Shop Drawings and calculations.

F. Warranty: The Contractor shall provide a written workmanship warranty after date of substantial completion to cover all elements of work to be free of defects. Manufacturer’s standard material/equipment warranties are to be provided for all new items.

C.1.3

CONTRACT ADMINISTRTION

A. The Contractor shall not perform any work outside this Statement of Work unless authorized in writing by the Contracting Officer (CO).

B. The CO will issue a Notice to Proceed (NTP).

C. The Contracting Officer’s Representative (COR) will oversee daily execution and ensure compliance.

D. Any proposed changes must be submitted in writing and approved before work proceeds.

E. The Contractor shall identify a Project Site Manager who shall be responsible for the overall management of the project and shall represent the Contractor on the site during construction. The Project Site Manager is required to be German and English-speaking and shall be approved by the COR.

C.1.4

QUALITY CONTROL:

A. The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.

B. The Work shall be governed by the U.S. Consulate General Frankfurt, Germany. All work is to be in compliance with International Codes and standards, which includes the most recent published edition of the OBO Building code, National Fire Prevention Association (NFPA), International Fire Code (IFC), International Building Code (IBC) , International Mechanical Code (IMC), International Plumbing Code (IPC), National Electrical Installation Standards (NEiS), National Electrical Safety Code (NESC), Standard for Electrical Safety in the Workplace (NFPA-70E) and National Electric Code (NFPA-70) as amended by OBO, also are applicable. Should there be a discrepancy between the US Government Specifications and the applicable Building Code, the more stringent of the two shall govern.

C.1.5

STORAGE OF MATERIALS:

A. The Contractor is responsible for safe and secure storage of materials.

B. On-site staging must be coordinated with the COR.

C. Temporary utilities must be connected and disconnected in coordination with Facility Management.

C.1.6

PROJECT SAFTEY:

A.

Contractor is responsible for safety and shall comply with US Consulate General requirements, US Army Corp of Engineers (USACE) Safety Manual (EM 385-1-1), U.S. OSHA Regulations and all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. Contractor shall prepare a Project Safety Plan to cover total project safety to be reviewed and approved by the Contracting Officer Representative (COR), and U.S. Consulate Post Occupational Safety and Health Officer (POSHO).

B.

Contractor shall furnish Personal Protective Equipment (PPE) for each employee as required for the specific job type and in accordance with (IAW) relevant OSHA regulations.

C.

All external personnel assigned to a project are required to participate in a mandatory online safety briefing conducted by the POSHO Safety Office. This safety training must be completed prior to the project start date and the commencement of any work activities.

1. Personnel joining the team after the project has commenced must also complete this training before undertaking any tasks.

2. Work conducted without prior safety training is strictly prohibited and will be immediately suspended upon discovery.

3. The safety briefing may be found at the following link; https://forms.office.com/g/shZ4sLh5Kn A. Electrical Safety: All electrical work must always be conducted in a "de-energized" state whenever possible and secured using the Lockout/Tagout (LOTO) system/procedure. Energized work must be handled with special precautions as outlined below.

1. Locks and tags must be applied to the equipment's energy isolation points or control panels. The tags must prominently display a warning message, along with the company name and the technician’s name. LOTO devices may only be removed by the individual who applied them.

2. Energized Work can only be performed if the supervisor requests an Energized Work Permit (EWP) at the Post Occupational Safety and Health Officer (POSHO) at least 24 hours prior to the scheduled start of work. The COR must assist the contractor in obtaining the necessary documents.

B. Hot Work: A hot work permit must be requested from the contractor at least 24 hours prior to the start of the work. The COR must assist the contractor in obtaining the necessary documents.

C. Confined Space: To enter confined spaces, the contractor must complete the required approval documents Post Approved Confined Spaces (PACS) entry permit at least 48 hours before entry and must be approved by the POSHO. The COR must assist the contractor in obtaining the necessary documents.

D. Fall Prevention: For fall heights, suitable protective measures must be taken to minimize the risk of accidents.

1. Elimination (Physically remove the hazard)

2. Substitution (Replace the hazard)

3. Engineering Controls (Isolate people from Hazard)

4. Administrative Controls (Change the way people work)

5. PPE (Protect the worker with Personal Protective Equipment) E. Temporary Ladders, Chutes, Scaffolds, Hoists and Cranes:

1. Furnish and maintain temporary ramps, scaffolds, hoists, or chutes as required for proper execution of Work.

2. Restrict debris removal to Consulate -approved area of building site.

3. Restrict location of equipment to areas as approved by the COR.

4. Such apparatus, equipment, and construction shall meet requirements of applicable federal, state, and local safety and labor laws.

5. Ladders are required to be non-conductive fiberglass construction with a load capacity (duty rating) of no less than 250 pounds (113kg).

6. Scaffolding:

a. Initial Inspection: After the scaffolding is completed, it must be inspected by a qualified person to verify proper assembly and safe functionality. This inspection ensures compliance with all safety requirements and standards.

b. Marking and Documentation: After the final inspection, the scaffolding must be clearly marked in a visible location (preferably at the access point). The label must include at least the following information:

i. Whether the scaffolding is authorized for use or not

ii. The name and signature of the authorized person who performed the inspection

iii. The address and phone number of the scaffolding contractor

iv. The type of scaffolding, load class, and width class

v. Any usage restrictions

vi. Warning notices

vii. The date of inspection

c. Scaffold users are required to conduct a daily visual inspection and, if necessary, a functional check by a qualified person before use. This inspection is to identify any obvious defects and ensure safe functionality based on the specific intended use. The inspection must be documented.

C.1.10

PROJECT SECURITY:

A.

Personnel Clearances:

1.

A Visit Authorization Request (VAR) will be required for all contractor personnel prior to entry. Contractors shall forward the following information to the COR: full name, date and place of birth, Government Identification Card, name of employer, position/discipline.

B. Vehicle Clearances: Submit authorization requests, to include dates, vehicle type, license number, and driver name, for each motorized vehicular implement used on-site.

C.

Access to Site: Contractor shall have limited access to or be admitted into the compound outside the areas designated for the project except with permission by the Consulate.

D.

Procurement/Storage: Materials shall be procured by NON-SECURE or local means and stored NON-SECURE. All materials may be inspected prior to use on the project.

PART TWO - PRODUCTS

C.2.1

GENERAL

A. The Contractor shall provide all necessary labor, material, equipment, and components necessary to ensure the installation of complete and operable systems. No materials or labor will be supplied or furnished by the Consulate.

B. All materials and equipment incorporated into the project shall be new unless noted otherwise. The Contractor shall transport and safeguard all materials and equipment required for construction.

C.2.2

PRODUCTS

A. Bruxsafol Solar heat reduction while allowing a controlled amount of natural light to pass through.

Exterior application

Vertical/horizontal application

Windowpanes each over 3sqm

PART THREE – EXECUTION

C.3.1

CONSTRUCTION REQUIREMENTS

No construction shall begin until approvals of the Pre-Construction Submittals are accepted by the COR.

The Contractor will be provided with a storage and staging area as determined by the COR. The Contractor shall be responsible for restoring the area to its original condition at the completion of the work. The Contractor shall be responsible for repair of any damage incurred to buildings or pavement as a result of storage activities. The Contractor is responsible for obtaining any additional off compound storage areas as required.

The Contractor shall always keep the work area free from accumulation of waste materials. Upon completion, the Contractor shall remove any temporary facilities and leave the project site in a clean and orderly condition acceptable to the COR.

The Contractor shall perform the work at the site during the U. S. Consulate's normal workday hours, (0800-16:30 Monday – Friday excluding holidays) unless alternate work hours are agreed upon with the COR.

Protections and Damage Plan: The Contractor shall be responsible to protect all U.S. Government property to include: all furniture, furnishings, and interior and exterior architectural finishes from damage. Any damage caused by the Contractor to architectural interior and exterior finishes will be returned to original condition by the Contractor at Contractor expense. In addition to the architectural finishes, the Contractor shall protect all non-included mechanical and electrical equipment and controls from damage throughout the duration of work. Prior to commencing the work, the Contractor along with Consulate representatives shall survey the site that will be impacted by the project work and document existing conditions. It shall be the Contractor’s responsibility to document in writing all pre-existing damaged surfaces prior to the start of the project work and to provide a copy of the documentation to the COR prior to project start.

C.3.2

INSTALLATION

Clean glass surfaces and apply sun protection

PART FOUR - SCHEDULE

C.4.1 PERIOD OF PERFORMANCE: Calendar days A. The work shall be executed in a diligent manner in accordance with a negotiated firm fixed price and performance period as outlined below.

1. Solicitation & Award of Contract:

a. Award

Zero Day

2. Pre-Construction Submittals:

a. Insurance, Schedule, & Product Data:

20 days after Award

b. Government Review:

10 days

3. Material Procurement:

a. Material Order

21 days

b. Material Shipping

7 days

4. Mobilization & Construction:

a. Crew Information

5 days in advance

b. Scope of Work

5 days TOTAL PERIOD of PERFORMACE:

58 days

PART FIVE - ATTACHMENTS

C.5.1

SEE SEPERAT PACKAGE

END OF SOW