This Statement of Work (SOW) details the U.S. Department of State's requirements for supplying and delivering a new diesel generator to the U.S. Embassy in Dili, Timor-Leste. The project involves replacing an existing Olympian GEH275 generator with a similar or equivalent model, specifying detailed technical requirements including 275 KVA/220 KW capacity, 400/230 V, 3 PHASE/50 HZ, and 1500 RPM operation. The contractor must provide a complete generator set with new radiator, engine silencer, and exhaust system, along with specific spare parts such as diode rectifier assembly, valve cover seals, filter sets, and fan belts.
The SOW mandates that all parts must be new, original equipment manufacturer (OEM) replacements, with a minimum 6-month warranty. The contractor is responsible for procurement, shipping, and delivery of the generator and related parts kit to the U.S. Embassy in Dili, with the embassy supporting customs clearance. Proposals must include detailed item descriptions, materials lists, delivery timelines, and warranty terms. The project must be completed within 365 days of the Notice to Proceed, with the contractor required to provide material order confirmation within 5 working days of award. Key points of contact include the Maintenance Supervisor and General Services Officer at the U.S. Embassy, with a Washington-based Power Support email for additional communication.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Generator Supply and Delivery
U.S. Embassy, Dili, Timor-Leste
July, 2025
1. GENERAL INFORMATION:
The U. S. Department of State requires professional services and contractor cost proposals to Supply and
Delivery a new diesel generator which will replace Embassy Dili’s old equipment. This project requires same or like brand equipment as the facilities’ current equipment:
Current Generator New Generator
Olympian GEH275 (Generator 1) Similar or equivalent to Existing Generator 1 Complete set including:
S/N OLY00000ERNS01652 New radiator, engine silencer. and exhaust
2003 system
250 KVA/200 KW
400/230 V
3 PHASE / 50 HZ Must meet the following specifications:
275 KVA/220 KW
360.90 A 400/230 V
1500 RPM 3 PHASE/50 HZ
MAXIMUM ALTITUDE 152.40 METERS
MAXIMUM AMBIENT TEMP IS 27 1500 RPM
DEGREES CELSIUS MAXIMUM ALTITUDE 152.40 METERS
MAXIMUM AMBIENT TEMP IS 27
DEGREES CELSIUS
The new generator will be located at the U.S. Embassy in Dili, Timor-Leste. This is a firm fixed price contract. All proposal packages must be accompanied by a parts list for the full functionality of all equipment requirements. All scope of work must be completed no later than 365 days after issuance of letter of Notice to Proceed.
2. PROJECT REQUIREMENTS:
The intent of this scope of work is to perform the supply and delivery of the post diesel powered generator per manufacturer’s recommended specifications and procedures. The replacement is intended to increase the reliability of Post’s electrical infrastructure. The scope of work includes, but is not limited to, the following tasks:
• Procurement of Materials o Procure a new diesel generator of same or like brand to current equipment matching “new generator” equipment specifications and related parts o Ensure all materials and components comply with relevant codes and standards.
o Spare Parts to include:
▪ Diode rectifier assembly – one set
▪ Valve cover seals – one complete set
▪ Three Complete sets of filters for each unit
▪ Fan belt – 02 each
▪ Pre-programmed Power Wizard control panel – 2 each o Special Tools / Manuals to include:
▪ Engine Barring Tool
▪ Injector height adjustment tool
▪ Operations and Maintenance Manual
▪ Parts Manual
▪ Repair and Troubleshooting Manuals to include wiring diagrams and schematics
• Delivery of Equipment o Deliver the generator and related parts kit to U.S. Embassy Dili, Avenida de Portugal, Praia dos Coqueiros, Dili, Timor-Leste o Ensure that all equipment is delivered in new condition and is ready for installation
Proposals from the vendor shall be based off manufacturer’s recommendations, the intent of and additions to, this SOW. Proposals must include a minimum 6-month warranty on parts.
2.1 DESCRIPTION OF EQUIPMENT:
List a basic summary Description of generator set(s). Make, model, size, operating hours.
Include more detailed information in appendix.
Existing Generator 1
Olympian GEH275 (Generator 1)
S/N OLY00000ERNS01652
250 KVA/200 KW
400/230 V
3 PHASE / 50 HZ
360.90 A
1500 RPM
MAXIMUM ALTITUDE 152.40 METERS
MAXIMUM AMBIENT TEMP IS 27 DEGREES CELSIUS
As of Sept. 03, 2024, total running hours is 9,500 hours
A. See Appendix A for specific serial numbers and photos, and room layout.
3. GENERAL REQUIREMENTS:
Offerors must provide a full description of equipment, cost proposal, and delivery plan.
3.1 ADDITIONAL: Refer to base legal contract for additional contract specifics.
The following requirements are specific to this SOW and tasking and are in addition to any base contract, post specific contract requirements.
3.2 PRODUCTS USED. All parts must be new, Original Equipment Manufacturer (OEM) replacement parts. Counterfeits or third-party substitutes are not authorized. All fluids must meet OEM specs and manufacturers recommendations and be provided in original unopened sealed containers.
A. Any substitutions to new original OEM parts must be approved by the COR and powersupport@state.gov
B. Re-manufactured parts are permitted but must be OEM. Warranty must be the same as for new and these parts must be specifically identified as re-manufactured in proposal.
3.3 PROCUREMENT AND SHIPPING. The contractor shall provide all materials and is responsible for getting materials to post. Post will support customs clearance processes in
Timor-Leste; however, any related fees, should they arise, must be paid by the contractor.
3.4 PROJECT COMMENCEMENT. The contractor must provide material order confirmation and approximate material lead time within 5 working days of award. Provide to post COR and email Washington based powersupport@state.gov with this confirmation.
4. SUBMITALS FOR REVIEW OF PROPOSALS
4.1 For proposals to be considered, they must include for review:
a. Detailed item descriptions including materials lists
b. Delivery timelines after receipt of order
c. Warranty terms
5. POINTS OF CONTACT.
Points of contact for this work are:
A. Maintenance Supervisor (FM, APOSHO, COR): Hiram Lasquety, Email:
LasquetyHA@state.gov
B. General Services Officer (GSO, POSHO, CO): Ian Oates, Email: OatesIK@state.gov
C. Washington-based OBO/CFSM/FAC/PS Power Support Email: powersupport@state.gov
6. WARRANTY:
A. The contractor shall warranty parts and for a minimum of 6 months from the date of delivery receipt.
END OF STATEMENT OF WORK