Post Award Construction Schedule 4WA0675.pdf
PDF 105 KB Posted
- Attached to
- Lease of Office Space within Region 10. Request for Lease Proposals (RLP) #25REG10 - Office Space
- Solicitation number
- 4WA0675
About this file
This is a Post-Award Schedule attachment for project 4WA0675 that details the timeline for design and construction activities following lease award. The schedule begins within 5 working days of lease award and outlines the key milestones leading to space acceptance.
The schedule spans 360 total working days and includes: 60 days for Lessor's Design Intent Drawings (DIDs), 25 days for government review of DIDs, 65 days for Construction Documents preparation, 25 days for government review of CDs, 30 days each for TI and BSAC price proposal submissions, 45 days for price negotiations and notice to proceed, and 160 days for completion of construction work and tenant improvements. This schedule replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Custodial Service Levels.pdf | ||
| DA 4WA0675.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE 4WA0675, PAGE 1 OF 1 PSA VERSION - REV (10/22)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
4WA0675
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Lessor Preparation of Design Intent Drawings (DIDs) 60
Government review and approval of Lessor-provided DIDs 25
The Lessor’s preparation and submission of Construction Documents (CDs)
Government review of CDs 25
Lessor Preparation and Submission of the TI and BSAC Price Proposal 30
The Lessor's preparation and submission of the BSAC price proposal 30
Negotiation of TI and BSAC price proposals and issuance of notice to proceed
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
Total Work Days from Lease Award to Government Acceptance 360
File details come from the government source that posted it. Updated .