Porti_Potti_2023_Schedule_.pdf

PDF 153 KB Posted

Attached to
CACO-RENTAL PORTA JOHNS BASE & 4 YEARS Federal contract opportunity
Solicitation number
140P4323Q0010
Issued by
Department of the Interior National Park Service Northeast Region

View the file

Other files for this federal contract opportunity

Other files attached to CACO-RENTAL PORTA JOHNS BASE & 4 YEARS, newest first.
File Type Posted
Wage_Determintaton_.pdf PDF
Combined_Synopsis_Solicitation__CAPE_COD_Porta_John_Service_.docx DOCX document
Quote_Schedule_updated_.docx DOCX document
SOW_Revised_2_8_23.pdf PDF
Sol_140P4323Q0010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

Cape Cod National Seashore Porta John pumping Schedule

April 1 , 2023-March 30, 2024 Location

Units M T W T F Sa Su Total pumps per week

Total weeks

Total pumps

Date of 1st pump Date of last pump for listed Schedule

NPS owned Porta Johns Winter/Spring Schedule

Oversand Station

Upper lot In place

1 X

X

Pump/Service 1st & 3rd Monday, in October

Pump/Service 1st Monday in each month Nov. Through Mar.

Pump/Service every Monday of the month Apr. through May

Race Point Handicap

1 X 1 13 13 Pump/Service every Monday of the month March through May

Great Island

2 X 2

Pump/Service 1st & 3rd Monday of each month, October through

March

Pump/Service every Monday of the month April through May

Total pumps 71

NPS owned Porta Johns Summer/Fall Schedule Snows Pond

1 X X 2 17 +1 day

35 Pump/Service 2 times weekly (M,+ F) from June through Sept.

Race Point Handicap

1 X X 2 15+ 1 day

32 Pump/Service 2 times weekly (M,+F) June 1st through Sept 15th

Oversand top lot

Pump 2 times weekly (M,+ F) from June 1st through Labor Day

Pump Fridays only after Labor Day

-Great Island

2 X X 4 15 + 1

62 Pump 2 times weekly (M,+ F) from June 1 through Sept 15th , High Head Parking lot

1 X X 2 9 + 1 19 Pump 2 time weekly (M &F) from July through Labor Day

Atwood Higgins In place

1 X 1 17 17 Pump/Service 1 time weekly (M) from June through Sept.

Total pumps 197

Page | 2

Contractor provided Porta Johns Summer/Fall Schedule

Oversand lower lot

Put in place The

Wednesday before

Memorial Day

1 X

X X 3

Pump/Service 3 times weekly (M,W,F) from Memorial Day through Sept.8th , Pump each Mon. after Labor Day in September

Marconi beach fee

Booth Put in place The Friday before Memorial

1 X 1 18 18 Pump/Service 1 time weekly Memorial Day through September

Little Creek

Put in Place Monday before

Memorial

60 Pump/Service 2 times weekly (M,F) from Memorial Day , through September 8th

Total pumps 126

Total NPS owned pumps 268

Total Contractor owned pumps 126

TOTAL PUMPS NPS + CONTRACTOR 394