PMLS Overview Real Estate Support Services RFP_April 2026.pdf
PDF 6 MB Posted
- Solicitation number
- S-Q10054-00016452
- Issued by
- Multnomah County, Oregon
About this file
This is a pre-proposal conference presentation for the Portland Metro Levee System (PMLS), a regional flood protection initiative involving the District and federal partnership with the U.S. Army Corps of Engineers (USACE). The District is seeking qualified consultants to provide real estate support services on an on-call, task order basis with multiple concurrent assignments. Core services requested include title research and historic rights analysis, real estate due diligence, acquisition and negotiation, appraisals, documentation, acquisition strategy development, risk identification, utility coordination, and programmatic support. The PMLS project encompasses 13,000 acres across four cities with 27 miles of levee and 12 pump stations, and involves 19 improvements including raising levees, replacing pump stations, and constructing new levee and floodwall infrastructure across multiple project sections (Vanport, Delta Park, Middle Columbia Slough, Blue Lake Fairview Lake, Upper Columbia Slough, and Salmon Creek). The project timeline spans from 2026 through 2031, with design phases at 30%, 60%, and 90% completion scheduled between late 2026 and 2028, and construction packages beginning October 2027. A pre-proposal conference was held in April 2026 to clarify scope, address risks and priorities, and support strong proposals. Questions are directed to Nicole via OregonBuys, with contact details provided for Mark Wilcox (Senior Project Manager) and Amber Ayers (Project Manager/Senior Planner).
The local cost share for real estate acquisitions is $12,802,000 (7% of total project costs), with additional local funding of $23,877,000 (13%) for relocations and utilities, and $26,697,250 (15%) in cash payments to USACE for project engineering and design costs. Federal cost share comprises $117,698,750 (65% of total project costs). The District is responsible for executing all real estate work including acquisition, title research, and relocation efforts to deliver certifiable rights, while USACE defines project needs and drives the design that informs the real estate plan. Current project status includes a completed gap analysis, surveys nearing completion, and largely defined footprints. The District seeks consultant support for title complexity resolution, acquisition strategy development, utility coordination across multiple providers, and scaling implementation of real estate activities. Strong proposals should demonstrate experience with complex infrastructure projects, title reconstruction expertise, utility coordination experience, and ability to manage schedule-driven work. Services are expected to be delivered responsively within one to two days with proactive risk identification and high-quality deliverables.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Portland Metro Levee System
(PMLS)
Real Estate Support Services RFP Pre-Proposal Conference – April 2026 Purpose: Overview of Project, Scope, and Consultant Expectations
Purpose of Pre-Proposal
• Provide overview of the PMLS project and real estate needs
• Clarify scope of services and expectations
• Highlight key risks, priorities, and timelines
• Answer questions to support strong proposals
About the District
• Regional flood protection system 13,000 acres across 4 cities 27 miles of levee 12 pump stations ~40 employees
• Modernized under ORS 550
• Expanded role: water quality, habitat, resilience
A History of Flooding
PMLS Overview
• Why project exists
• Scale + importance
• Federal partnership (USACE)
PMLS Objectives Reduce flood damages, threats to life safety, and risk to critical infrastructure
Increase resilience and reliability of the system and the awareness of flood risk
Improve operability and decrease flood response and recovery time
This project also addresses key vulnerabilities and needs for FEMA accreditation
Make 30% of the levees stronger and more reliable.
Increase the level of protection for the western part of the flood management system to reduce failure and to prevent overtopping and levee breaches.
Build a new levee and floodwall where the ad-hoc levee railroad embankment failed in 1948, destroying the City of Vanport.
The Portland Metro Levee System project includes 19 improvements that will:
Fill in low spots where overtopping poses a risk.
Replace or upgrade 3 outdated pump stations which move water from behind the levees out of the system and prevent internal flooding.
Improve access to back-up power for 6 critical pump stations.
PMLS TIMELINE & KEY MILESTONES
Onboarding
Strategic Acquisition Planning
• Roadmap for board engagement
• Rerack real estate and relocations tracking systems
Acquisitions Execution
• Gap Analysis
• Continue acquisition process for High Risk Instruments
Support of Attorneys Opinion of Compensability Gap analysis
• Real Estate Working
Group Kickoff
Acquisitions Execution
• Gap Analysis
• Begin at-risk acquisition of High Risk Instruments
Support of Attorneys Opinion of Compensability Gap analysis
• Real Estate Working
Group Kickoff
FSD will enter into Project Partnering (Construction) Agreement with the U.S. Army Corps of Engineers
• Real estate acquisitions no longer at risk
Acquisitions Execution
• As plans move towards 90%, high volume of acquisitions expected
Levees and floodwall work
• 30% designs -Most designs, approx.
end of CY2026
• 60% designs - Most designs, approx. Q3 CY2027
• 90% designs - Most designs, approx. Q3 CY2026
• Construction
• Package 1 – October 2027
• Package 3 – October 2029
• Package 4 – January 2029
• Package 6 – January 2031
• Package 7 - January 2029
Pump station work o 30% designs -January 2027 o 60% designs -June 2027 o 90% designs -August 2028 o Final plans/specs
Package 2 – March 2028 Package 5 – September 2028 o Construction Package 2 – January 2029 Package 5 – October 2029
PMLS Real Estate in Context of Total Project Costs
Local cost share - Real Estate, $12,802,000 , 7%
Local cost share - Relocations &
Utilities, $23,877,000 , 13%
Local cost share - Cash to the USACE, includes PED costs, $26,697,250 , 15%Federal cost share, $117,698,750 , 65%
The PMLS Cost Share - January 2026 Estimate
Nature of the Work What Makes This Work Complex
• Multi-parcel acquisitions across active urban area
• Legacy and incomplete property records
• Utility conflicts and relocations
• Coordination with federal, state, and local partners
• Integration with design + construction sequencing
Vanport Section (PEN 1)
Spot fill and widen existing levee. Add gravel to levee base.
Construct a new levee and connect to the new floodwall.
Build a floodwall that connects the new levee to the existing floodwall.
Relocate and raise the railroad underpass flood closure.
Add a four-season maintenance path on levee.
Add back-up power source to pump station.
Add band of concrete between road and floodwall to prevent scour/failure in event of overtopping flows.
Replace existing floodwall. Add permanent flood closures.
Delta Park (PEN 2) Raise levee by 1-1.5 ft and replace roadways (Bridgeton Rd.)
Spot fill levee.
Add back-up power source to pump station.
Extend and raise floodwall.
Widen and spot fill existing levee.
Add gravel to the levee.
Replace pump station and add back-up power source.
Raise levee by 3-4 ft and replace roadway (Marine Dr.)
Add back-up power source to pump station.
Increase levee height by up to 2 ft.
Replace pump station and add back-up power source.
Middle Columbia Slough (MCDD West)
Widen and spot fill existing levee.
Add gravel toe drain to the levee.
Blue Lake
Fairview Lake
Upper Columbia Slough (MCDD East)
2021 completed work-in-kind: replaced trash rake and added back-up power source to pump station.
Su nd ial R oa d
NE 223 rd Ave.
Salmon Creek (SDIC)
Raise levee by 4-6 ft.
Widen levee to address potential vulnerability.
Raise levee low spot by 4 ft.
Elevate and replace pump station with additional capacity and add back-up power source.
PMLS Project FootprintPMLS Project Footprint
PMLS Gantt Chart
Roles & Responsibilities
USACE Role
• Defines needs
• Design drives real estate plan District Role
• Executes ALL real estate work
• Acquisition, title, relocation
• Delivers certifiable rights
Current Status
Where We Are
• Gap analysis complete
• Survey nearing completion
• Footprint largely defined
Where We Need Help
• Title complexity
• Acquisition strategy
• Utility coordination
• Scaling implementation
Scope of Services
Core Services
• Title research & historic rights analysis
• Real estate due diligence
• Acquisition & negotiation
• Appraisals
• Documentation
Strategic & Advisory
• Acquisition strategy
• Risk identification
• Coordination across disciplines
Utility Coordination
• Identify conflicts
• Coordinate with providers
• Align with construction sequencing
Programmatic Support
• Process development
• Documentation
• Board/executive support
Delivery of Services
• On-Call Contract
• Task Order Based
• Multiple Concurrent
Assignments
• Responsive (1–2 days)
• Proactive risk identification
• High-quality deliverables
• Coordination across teams
Performance Expectations
What We're Looking For
Strong Proposals Will Demonstrate:
Experience with complex infrastructure projects
Title reconstruction expertise
Utility coordination experience
Ability to manage schedule-driven work
Clear, organized approach
Procurement Process
Timeline
OregonBuys
Questions through Nicole
No outside communication
Questions?
Mark Wilcox, PMLS Senior Project Manager mwilcox@urbanfloodsafetyor.gov
Amber Ayers, Project Manager | Senior Planner aayers@urbanfloodsafetyor.gov
| Portland Metro Levee System (PMLS) |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Slide Number 17 |
| PMLS Gantt Chart |
| Roles & Responsibilities |
| Current Status |
| Scope of Services |
| Delivery of Services |
| What We're Looking For |
| Procurement Process |
| Questions?��Mark Wilcox, PMLS Senior Project Manager mwilcox@urbanfloodsafetyor.gov��Amber Ayers, Project Manager | Senior Planner�aayers@urbanfloodsafetyor.gov� |