This Project Labor Agreement (PLA) Request for Information (RFI) seeks market research input for a runway repair project at Barksdale Air Force Base in Louisiana. The construction project involves a full-depth reconstruction of approximately 68,500 square yards of concrete pavement across multiple runway and taxiway sections, including pavement crushing/recycling, asphalt overlay, and re-striping. The project is design-bid-build with an estimated construction magnitude of $25M-$100M and a planned 540-calendar day performance period. NAVFAC Southeast is specifically soliciting confidential feedback from potential contractors, unions, and other stakeholders regarding the proposed Project Labor Agreement (PLA) through a detailed questionnaire, with responses due by 2:00 PM Eastern on 6/12/2025. The government is seeking insights on labor availability, potential specialized construction requirements, wage comparisons, and potential cost implications associated with implementing a PLA for this federal construction project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Labor Agreement (PLA) Request for Information (RFI) for

Construction Project for Barksdale Runway 15-33 Repairs in the State of Louisiana

Rev.2 June 3, 2025 1

This is a request for information/market survey. This is not a request for proposal, request for quote, or an invitation for bid. There will be no solicitation, specification, or drawings available at this time.

Naval Facilities Engineering System Command (NAVFAC) Southeast is soliciting comments from the public addressing the potential use of Project Labor Agreements (PLA) for the following construction project. The construction project is to repair runway 15-33 at Barksdale Air Force Base (AFB), Bossier

City, Louisiana. Construction may include, but is not limited to, a full-depth reconstruct of pavement sections within the Runway 15 approach, Runway 33 approach, Taxiway Alpha, Taxiway Charlie, Taxiway Delta, and Taxiway Echo 1. Approximate total concrete pavement reconstruction area is

68,500 square yards. The typical proposed concrete pavement section is 24-inches thick, underlain with

12-inches of crushed concrete base course, underlain with chemically stabilized subgrade (cement and lime additive). As part of this project, the existing concrete pavement is required to be crushed, processed, and re-used as base course material. Asphalt pavement mill and overlay and asphalt section full-depth construction is required to accommodate the new concrete pavement geometry. Additionally, the entire length of Runway 1533 is required to be re-striped in accordance with DoD and FAA criteria located in the State of Louisiana. Project will be design-bid-build (DBB). NAICS Code: 237310. The magnitude of construction is anticipated to be $25M – $100M. General period of performance is anticipated to be approximately 540 calendar days.

A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement as described in 29 U.S.C. 158 (f). Federal Acquisition Regulation (FAR) policy states:

Executive Order (E.O.) 14063, Use of Project Labor Agreements for Federal Construction Projects, requires agencies to use PLAs in large-scale construction projects (defined as a construction projects with a total estimated cost at or above $35M) to promote economy and efficiency in the administration and completion of Federal construction projects. When awarding a contract in connection with a large-scale construction project, agencies shall require use of a PLA for contractors and subcontractors engaged in construction on the project, unless an exception(s) at FAR 22.504(d) applies. Reference is made to: FAR Subpart 22.5 Use of Project Labor Agreements for Federal Construction Projects;

provision, FAR 52.222-33 Notice of Requirement for Project Labor Agreement; and to clause, FAR

52.222-34 Project Labor Agreement.

In consideration of the above factors, and any others which may be deemed appropriate, the public is invited to provide responses on the use of a PLA for this construction project utilizing the attached questionnaire.

In light of recent court decisions on PLAs, the Government is seeking additional information on the use of PLAs for this project. This survey is for planning purposes only and shall not be construed as an obligation on the part of the Government. The Government does not intend to award a contract on the basis of this market survey or otherwise pay for the requested information. The Government will not provide a debriefing on the results of this survey. All information will be held in a confidential manner and will only be used for the purposes intended. (See question #4)

Responses shall be submitted on the attached questionnaire via email to Cynthia McMonigle at cynthia.a.mcmonigle.civ@us.navy.mil no later than 2:00 PM Eastern time on 6/12/2025.

Project Labor Agreement (PLA) Questionnaire

Questions Responses

1) Are you responding as a representative of a government entity, union, contractor (union or non-union) and/or qualified small business?

2) Would the work involve specialized construction that is available from only a limited number of contractors or subcontractors? Explain in detail.

3) What is your understanding of the availability of union labor and non-union labor in this area for this type of project? Are you otherwise aware of national, regional, or local interest in participating in this project by union or non-union contractors.

Explain in detail.

4) As a qualified contractor for a project of this type, would you be interested in participating in this project?

Would the requirement of a PLA under this project impact your interest in any way? If you have submitted an offer under this solicitation, would you continue to compete for this project if the solicitation is amended to require a PLA? Explain in detail.

mailto:cynthia.a.mcmonigle.civ@us.navy.mil

5) Are you aware of PLAs having been used on other similar construction projects in the area and/or other nearby areas?

Explain in detail.

6) How do union wage rates compare to prevailing wage rates for this type of project and in this area, i.e., prevailing wage rates under the Construction Wage Rates Requirements statute (formerly known as the Davis-Bacon Act). Explain in detail.

7) Are there any ways in which the requirement of a PLA might increase costs on a project of this type in this area? Explain in detail.