PIN 3950.63 Contract Proposal Book_Signed.pdf
PDF 5 MB Posted
- Attached to
- HECTOR STREET COMPLETE STREET State and local contract opportunity
- Solicitation number
- 2061523
- Issued by
- Tioga County, New York
About this file
This document is the Contract Proposal Book for the Hector Street Complete Street project in the City of Ithaca, Tompkins County, New York, with PIN 395063 and City Capital Project #846.
The proposed project includes the installation of new sidewalks, ADA compliant ramps, retaining walls, and bicycle accommodations such as an on-road bike lane and a side path. It also involves modifying two horizontal curves along Hector Street to improve safety. The project is a unit price contract with a base bid, and bids are due on January 16, 2020 by 2:00 PM. The work is to be substantially complete within 180 calendar days and fully complete within 240 calendar days of the notice to proceed. A 3% DBE participation goal is required.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| PIN 3950.63 Contract Proposal Book_Signed.pdf.crdownload | CRDOWNLOAD file | |
| Cover Addendum 1 .pdf | ||
| Hector Street Complete Street Project Bid Tab.pdf | ||
| PIN 3950.63 Plans.pdf | ||
| PIN 3950.63 Plans.pdf.crdownload | CRDOWNLOAD file | |
| Solicitation of Interest Checklist Form.pdf | ||
| Addendum 137.pdf | ||
| City of Ithaca - Hector Street Notice of Award Form_Signed by all.pdf | ||
| Vendor Responsibility Questionnaire For Profit - fillable15.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF ITHACA
OFFICE OF THE CITY ENGINEER
108 EAST GREEN STREET
ITHACA, NEW YORK 14850
CONTRACT DOCUMENTS
HECTOR STREET COMPLETE STREET
CITY OF ITHACA
TOMPKINS COUNTY, NEW YORK
PIN 395063
D035697
CITY CAPITAL PROJECT #846
DECEMBER 2019
BID DUE DATE: __________________________
CONTRACTOR: __________________________
AWARD DATE: __________________________
TIM LOGUE SVANTE L. MYRICK
CITY DIRECTOR OF ENGINEERING MAYOR
Submitted in accordance with Highway Law and the Standard Specifications officially finalized and adopted on January 1, 2020 as posted on the Department’s website.
SECTION 00002
HECTOR STREET COMPLETE STREET, PIN 395063
CONTRACT DOCUMENTS
HECTOR STREET COMPLETE STREET
CITY OF ITHACA
TOMPKINS COUNTY, NEW YORK
PIN 395063
D035697
CITY CAPITAL PROJECT #846
Date 12/9/2019
SECTION 00003
HECTOR STREET COMPLETE STREET, PIN 395063
TABLE OF CONTENTS
INTRODUCTORY INFORMATION
SECTION-DESCRIPTION
00002-CERTIFICATION PAGE
00003-TABLE OF CONTENTS
00004-LIST OF CONTRACT DOCUMENTS
BIDDING REQUIREMENTS
SECTION-DESCRIPTION
00100-ADVERTISEMENT FOR BIDS
00200-INSTRUCTIONS TO BIDDERS
00400-BID FORM AND SUPPLEMENTS
00410-SUPPLEMENT A – BID PROPOSAL
00410-SUPPLEMENT A – UNIT COST BID FORMS
00420-SUPPLEMENT B – BID BOND……
00430-SUPPLEMENT C – STATEMENT OF BIDDER’S QUALIFICATIONS.
00440-SUPPLEMENT D – DISCLOSURE OF LOBBYING ACTIVITIES
00450-SUPPLEMENT E – NON-COLLUSIVE BIDDING CERTIFICATIONS..
00460-SUPPLEMENT F – DBE UTILIZATION GOALS
00470-SUPPLEMENT G – LIST OF SUBCONTRACTORS
00480-SUPPLEMENT H – IRAN ENERGY DIVESTMENT CERTIFICATION
00490-SUPPLEMENT I – INDEMNIFICATION AGREEMENT…
00500-SUPPLEMENT J – STATEMENT OF INSURANCE COVERAGE
00510-SUPPLEMENT K – NON-BIDDER’S RESPONSE
00520-SUPPLEMENT L – SEXUAL HARASSMENT PREVENTION
CERTIFICATION
CONTRACT FORMS
SECTION-DESCRIPTION
00600-AGREEMENT
00610-NOTICE OF AWARD
00620-NOTICE TO PROCEED
00630-INSURANCE REQUIREMENTS
CONDITIONS OF THE CONTRACT
SECTION-DESCRIPTION
00805-FEDERAL CONSTRUCTION CONTRACT REQUIREMENTS
00810-NEW YORK STATE PREVAILING WAGE SCHEDULE
FEDERAL PREVAILING WAGE SCHEDULE
10000-GENERAL
11000-SPECIAL NOTES
PAGE NO.
AB-1 – AB-2
IB-1 – IB-10
BF-1 – BF-2
BF-3 – BF-8
BF-9 – BF-26
BF-27 – BF-30
BF-31 – BF-32
BF-33 – BF-36
BF-37 – BF-42
BF-43 – BF-44
BF-45 – BF-46
BF-47 – BF-48
BF-49 – BF-50
BF-51 – BF-52
BF-53 – BF-54
BF-55 – BF-56
PAGE NO.
A1 – A12
NA-1
NP-1
IN-1 – IN-4
PAGE NO.
CCR-1 – CCR-39
PWS-1
FWS-1 – FWS-16
GN-1 – GN-8
SN-1 – SN-26
SECTION 00003
HECTOR STREET COMPLETE STREET, PIN 395063
SPECIFICATIONS
SECTION-DESCRIPTION PAGE NO.
11100-TECHNICAL SPECIFICATIONS..……………………………………….. TS-1 – TS-17
11200-SIGN FACE LAYOUTS……………………………………………………... SG-1 – SG-9
11300-PERMIT INFORMATION………………………………………………… PE-1 - PE-3
1400-CROSS SECTIONS…………………………………………………………. XS-1 - XS-152
SECTION 00004
HECTOR STREET COMPLETE STREET, PIN 395063
LIST OF CONTRACT DOCUMENTS
The contract documents for this project consist of the following items:
1. This Agreement including all documents listed in Article 2 of the Agreement, specifically, but not limited to any Special Notes or Special Specifications;
2. Bonds and Insurances, as required;
3. Construction and Material Specifications:
The documents and specifications for the Hector Street Complete Street, dated December 2019, as listed in the Table of Contents.
New York State Department of Transportation Standard Specifications (US Customary Units) with addenda and modifications current as of the date shown on the proposal book cover. Where reference is made to New York State, State Department of Transportation, Commissioner, Deputy Chief Engineer of the Technical Services Department (D.C.E.T.S.), Deputy Chief Engineer (Structures) (D.C.E.S.), Geotechnical Engineering Bureau (G.E.B.), etc., the appropriate OWNER’s Official or Erdman Anthony’s ENGINEER or Resident Project Representative shall be substituted. In any instance where the provisions of the NYS Department of Transportation Standard Specifications are in conflict with the provisions contained within this document, the stricter provision shall govern. The OWNER or its representative shall make the final interpretations of any irregularities, ambiguities or questions arising out of the Specifications and the New York State Department of Transportation Specifications used on this project. Copies of the New York State Department of Transportation Specifications can be obtained directly from the New York State Department of Transportation.
4. Contract Drawings:
Engineering drawings entitled, “Hector Street Complete Street,” dated December 2019, and consisting of the following drawings:
SHEET
No.
DECRIPTION DRAWING No.
1 COVER -
2 - 4 ABBREVIATIONS & SYMBOLS LA-1 thru LA-3 5 - 7 TYPICAL SECTIONS TS-1 thru TS-3
8 GENERAL NOTES GN-1
9 ESTIMATE OF QUANTITIES QU-1
10 - 12 WORK ZONE TRAFFIC CONTROL WZ-1 thru WZ-3 13 - 21 SURVEY & ALIGNMENT SA-1 thru SA-9
22 - 23 MAINTENANCE JURISDICTION PLAN &
TABLE
MJ-1 thru MJ-2
24 - 28 MISCELLANEOUS TABLES MT-1 thru MT-5
SECTION 00004
HECTOR STREET COMPLETE STREET, PIN 395063
29 - 38 MISCELLANEOUS DETAILS MD-1 thru MD-10
39 EROSION SEDIMENT CONTROL NOTES EN-1
40 - 55 EROSION CONTROL PLANS ES-1 thru ES-16 56 - 71 PLANS PL-1 thru PL-16 72 - 77 PROFILES PR-1 thru PR-6 78 - 95 PAVEMENT MARKING & SIGNING PLANS PM-1 thru PM-18 96 - 97 RETAINING WALLS RW-1 thru RW-2 98 - 101 HEADWALLS ST1-1 thru ST2-2
5. Addenda (if any) issued for this contract
6. Instructions to Bidders;
7. Contractor’s Bid, including Bid Form, Unit Price Proposal, and Supplements;
8. Notice of Award;
9. The following which may be delivered or issued after the Effective Date of the
Agreement and are not attached hereto:
a. Notice to Proceed
b. Work Change Directives
c. Change Orders
d. All Written Amendments and other documents amending, modifying or supplementing the Contract Documents pursuant to Paragraphs 3.04 of the General Conditions.
SECTION 00100
HECTOR STREET COMPLETE STREET, PIN 395063
AB-1
Advertisement for Bids
City of Ithaca – Department of Public Works 108 East Green Street
Ithaca New York 14850
PH: (607) 274-6535
Sealed Bids for the “Hector Street Complete Street” project located in the City of Ithaca, New York will be received by the office of the City Controller at 108 East Green Street, Ithaca, NY until January 16, 2020 at 2:00 PM. The bids will then be publicly opened and read aloud.
The proposed project provides for the installation of a new sidewalk on the north side of Hector Street between 500 feet west of the City/Town of Ithaca line and the 600 block of Hector Street. ADA compliant sidewalk ramps, including detectable warning devices and retailing walls will also be installed. Existing sidewalks in need of repairs will also be replaced. Bicycle accommodations will be provided through the installation of an on-road bike lane between the western project limit and 715 Hector Street and an 8-foot wide side path between 211 Hector Street and Floral Avenue.
Bus stops will also be modified. In addition to the pedestrian and bicycle improvements, two horizontal curves along Hector Street will be modified to reduce grading impacts and improve sight distance. The project is a Unit Price contract including a Base Bid.
BIDS SHALL BE SUBMITTED IN A SEALED ENVELOPE, ENTITLED: HECTOR STREET COMPLETE
STREET BID.
Each bid shall be accompanied by a deposit in the amount of: Five Percent (5%) of the Total Gross Sum Bid in the form of a Certified Check, Bank Draft, or Bid Bond. Cash will not be acceptable as a deposit. Bid deposits of all unsuccessful bidders shall be returned promptly upon execution of the contract with the successful bidder.
Copies of the contract documents, listed in the Table of Contents and the List of Contract Documents, may be downloaded and printed from the City’s website at: www.cityofithaca.org/bids
Documents may be examined from the website, as well as at the following locations:
City of Ithaca, Engineer’s Office, 108 East Green Street, Ithaca, NY 14850 Erdman Anthony, 145 Culver Road, Rochester, New York 14620
Amendments can only be accomplished by means of Addenda issued by the City of Ithaca or its designee. Written questions should be addressed to Robert Schiller, P.E., of Erdman Anthony at schillerr@erdmananthony.com and copied to John Licitra at jlicitra@cityofithaca.org. Questions must be received up to 72 hours prior to the bid opening.
The City reserves the right to reject any or all bids and to waive any informality or technicality in any bid in the interest of the Owner. Attention of Bidders is particularly called to the requirements for ensuring that employees, applicants for employment, and contractors are not discriminated against; refer to the Contract Documents for additional information.
A DBE participation goal of 3% is required as part of this contract. Each Bidder submitting a Bid to the Owner shall execute and attach thereto, the Certification regarding Equal Employment Opportunity. Although the Bidder is not required to attach such Certification by proposed sub-contractors to his Bid, the Bidder is here advised of this requirement so that appropriate action can be taken to prevent subsequent delay in sub-contract awards.
Advertised in:
Ithaca Journal, NYS Contract Reporter
John Licitra Date Sidewalk Program Manager
SECTION 00100
HECTOR STREET COMPLETE STREET, PIN 395063
AB-2
PAGE INTENTIONALLY LEFT BLANK
SECTION 00200
HECTOR STREET COMPLETE STREET, PIN 395063
IB-1
INSTRUCTIONS TO BIDDERS
1. DEFINED TERMS
Terms used in these Instructions to Bidders which are defined in the NYSDOT Standard Specifications have the meanings assigned to them in the General Provisions, Section 100. The term “Bidder” means one who submits a Bid directly to Owner, as distinct from a sub-Bidder, who submits a bid to a Bidder. The term “Successful Bidder” means the lowest, qualified, responsible and responsive Bidder to whom Owner (on the basis of Owner’s evaluation as hereinafter provided) makes an award. The term “Bidding Documents” includes the Advertisement for Bids, Instruction to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). For the purposes of this contract, the term Engineer shall refer to Erdman Anthony and the term “Owner” shall refer to the City of Ithaca.
2. COPIES OF BIDDING DOCUMENTS
Complete sets of the Bidding Documents may be downloaded and/or printed from the City of Ithaca website at www.cityofithaca.org/bids. Copies are available for review in the Office of the City Engineer.
Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents. Owner and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use.
3. EXAMINATION OF CONTRACT DOCUMENTS AND SITE
It is the responsibility of each Bidder before submitting a Bid, to (a) examine the
Contract Documents thoroughly, (b) visit the site to become familiar with local conditions that may affect cost, progress, performance or furnishing of the Work, (c) consider federal, state and local Laws and Regulations that may affect cost, progress performance or furnishing of the Work, (d) study and carefully correlate Bidder’s observations with the Contract Documents, (e) notify Engineer of all conflicts, errors or discrepancies in the Contract Documents and (f) be familiar with all Public Utility Requirements.
Written notification shall be made to Robert Schiller, P.E., Erdman Anthony, 145 Culver Road, Suite 200, Rochester, NY 14620 or emailed to schillerr@erdmananthony.com with an email copy to John Licitra at jlicitra@cityofithaca.org.
Information and data reflected in the Contract Documents with respect to
HECTOR STREET COMPLETE STREET, PIN 395063
IB-2
Underground Facilities at or contiguous to the site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities or others.
Neither the Owner nor the Engineer assumes responsibility for the accuracy or completeness thereof unless it is expressly provided otherwise in the Contract Documents.
Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders on subsurface conditions, Underground Facilities and other physical conditions, and possible changes in the Contract Documents due to differing conditions appear in the Contract Documents.
Before submitting a Bid, each Bidder will, at Bidder’s own expense, make or obtain any additional examinations, investigations, explorations, tests and studies and obtain any additional information and data which pertain to the physical conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance or furnishing of the Work in accordance with the time, price and other terms and conditions of the Contract Documents.
On request in advance, Owner will provide each Bidder access to the site to conduct such explorations and tests as each Bidder deems necessary for submission of a Bid.
Bidder shall fill all holes, clean up and restore the site to its former condition upon completion of such exploration.
The lands upon which the Work is to be performed, right-of-way and easements for access thereto and other lands designated for use by contractor in performing the Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment are to be provided by Contractor. Easements for permanent structures or permanent changes in existing structures are to be obtained and paid for by Owner unless otherwise provided in the Contract Documents.
The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Contract Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Contract Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the work.
4. INTERPRETATIONS AND ADDENDA
All questions about the meaning or intent of the Contract Documents are to be
HECTOR STREET COMPLETE STREET, PIN 395063
IB-3
directed to Engineer in writing. Written notification shall be made to Robert Schiller, P.E., Erdman Anthony, 145 Culver Road, Suite 200, Rochester, New York 14620 or emailed to schillerr@erdmananthony.com with an email copy to John Licitra at jlicitra@cityofithaca.org. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda and will be posted to the website noted in Section 2 not less than 3 business days before the Bid due date. Questions received less than ten days prior to the date for opening of Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. It is the Bidder’s responsibility to check the website before submitting the Bid to see if any Addenda have been posted.
Addenda may also be issued to modify the Bidding Documents as deemed advisable by Owner and Engineer.
5. BID SECURITY
Each bid must be accompanied by a Bid security made payable to Owner in the amount of five percent (5%) of the Bidder’s total sum gross bid and in the form of a certified or bank check or a bid bond (on form attached) issued by a surety meeting the requirements of the General Provisions.
The bid security of the successful Bidder will be retained until such Bidder has executed the agreement and has furnished the required contract security, whereupon the bid security will be returned. If the successful Bidder fails to execute and deliver the agreement and furnish the required contract security within fifteen days after the Notice of Award, the Owner may annul the Notice of Award and the bid security of that Bidder will be forfeited. The bid security of other Bidders whom the Owner believes to have a reasonable chance of receiving the award may be retained by the Owner until the earlier of the seventh day after the effective date of the agreement or the forty-sixth day after the bid opening, whereupon the bid security furnished by such Bidders will be returned. Bid security with bids which are not competitive will be returned within seven days after the bid opening.
6. CONTRACT TIME
Time is of the essence. The work under this contract shall be substantially complete within 180 calendar days of the date fixed in the Notice to Proceed. The work shall be completed and ready for final payment in accordance with the General Provisions within 240 calendar days of the date fixed in the Notice to Proceed.
7. LIQUIDATED DAMAGES
Provisions for liquidated damages are set forth in Section 108-03.B of the Standard
Specifications.
8. SUBSTITUTE OF “OR-EQUAL” ITEMS
The Contract, if awarded, will be on the basis of materials and equipment described in the Drawings or specified in the Specifications without consideration of possible substitute of “or-equal” item of material or equipment. Application for acceptance of a substitute “or-equal” may be furnished to the Engineer for consideration after the
HECTOR STREET COMPLETE STREET, PIN 395063
IB-4
Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by Engineer is set forth in the General Provisions.
9. SUBCONTRACTORS, SUPPLIERS AND OTHERS
If conditions require the identity of certain Subcontractors, Suppliers and other persons and organizations (including those who are to furnish the principal items of material and equipment) to be submitted to Owner in advance of the specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within seven days after the Bid opening submit to Owner a list of all such Subcontractors, Suppliers and other persons and organizations proposed for those portions of the Work for which such identification is required.
Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, person or organization if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, other person or organization, either may before the Notice of Award is given request the apparent Successful Bidder to submit an acceptable substitute without an increase in Bid price.
If apparent Successful Bidder declines to make any such substitution, Owner may award the contract to the next lowest Bidder that proposes to use acceptable Subcontractor, Supplier, and other persons and organizations. Declining to make requested substitutions will not constitute grounds for sacrificing the Bid security of any Bidder. Any Subcontractor, Supplier, other person or organization listed and to whom Owner or Engineer does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in the General Provisions.
No Contractor shall be required to employ any Subcontractor, Supplier, other person or organization against whom Contractor has reasonable objection.
10. BID FORM
The Bid Form is included with the Contract Documents; additional copies may be obtained from Engineer or Owner.
All blanks on the Bid Form must be completed in ink or by typewriter and must be signed in ink. Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, Bid item, alternative, adjustment unit price item, and unit price item listed therein. In the case of optional alternatives, the words, “No Bid,” “No Change,” or “Not Applicable” may be entered.
Bids by corporations must be executed in the corporate name by the president or a vice-president (or other corporate officer accompanied by evidence of authority to sign) and the corporate seal must be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation must be shown
HECTOR STREET COMPLETE STREET, PIN 395063
IB-5
below the signature.
Bids by partnerships must be executed in the partnership name and signed by a partner, whose title must appear under the signature, accompanied by evidence of authority to sign. The official address of the partnership must be shown below the signature.
All names must be typed or printed below the signature.
The Bid shall contain an acknowledgment of receipt of all Addenda (the numbers of which must be filled in on the Bid Form).
The name, postal address, telephone number and email address of a person responsible for communications regarding the Bid must be shown.
The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
11. SUBMISSION OF BIDS
Bids shall be submitted at the time and place indicated in the Advertisement for Bids and shall be enclosed in an opaque sealed envelope, marked with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted) and name and address of the Bidder and accompanied by the Bid security and other required documents. If the Bid is sent through the mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope with the notation “BID ENCLOSED” on the face of it.
12. BASIS OF BID; COMPARISON OF BIDS
Bidders shall submit a Bid on a unit price basis for each item of Work in the Bid schedule. The total of all estimated prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with the General Provisions.
Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
13. MODIFICATION AND WITHDRAWAL OF BIDS
Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids.
If, within twenty-four hours after Bids are opened, any Bidder files a duly signed, written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the
HECTOR STREET COMPLETE STREET, PIN 395063
IB-6
preparation of its Bid, that Bidder may withdraw its Bid and the Bid security will be returned. Thereafter, that Bidder will be disqualified from further bidding on the Work to be provided under the Contract Documents.
14. OPENING OF BIDS
Bids will be opened and (unless obviously non-responsive) read aloud publicly. An abstract of the amounts of the base Bids and major alternates (if any) will be made available to Bidders after the opening of Bids.
15. BIDS TO REMAIN SUBJECT TO ACCEPTANCE
All bids will remain subject to acceptance for forty-five days after the day of the Bid opening, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to that date.
16. AWARD OF CONTRACT
Owner reserves the right to reject any and all Bids without limitation, to waive any and all informalities not involving price, time or changes in the work and to negotiate contract terms with the Successful Bidder, and the right to disregard all nonconforming, non-responsive, unbalanced or conditional Bids. Also, Owner reserves the right to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by Owner.
In evaluating Bids, Owner will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
Owner may consider the qualifications and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations must be submitted. Owner also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award.
Owner may conduct such investigations as Owner deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications and financial ability of Bidders, proposed Subcontractors, Suppliers and other persons and organizations to perform and furnish the Work in accordance with the Contract Documents to Owner’s satisfaction within the prescribed time.
If the contract is to be awarded, it will be awarded to the lowest responsible Bidder whose evaluation by Owner indicates to Owner that the award will be in the best interests of the Project.
If the contract is to be awarded, Owner will give the Successful Bidder a Notice of Award within forty-five days after the day of the Bid opening.
HECTOR STREET COMPLETE STREET, PIN 395063
IB-7
More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
17. CONTRACT SECURITY AND INSURANCE
The General Provisions and Special Notes set forth Owner’s requirements as to
Payment and Performance Bonds. Owner’s insurance requirements are set forth in Section 00630 of these Contract Documents. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by the required Payment Bond and insurance certificates.
18. SIGNING OF AGREEMENT
When Owner gives a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the agreement with all other written Contract Documents attached. Within ten calendar days thereafter Contractor shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner with the required Bonds. Within fifteen days thereafter Owner shall deliver one fully signed counterpart to the Contractor. Each counterpart is to be accompanied by a complete set of the Drawings with appropriate identification.
19. SALES AND USE TAXES
The City of Ithaca is exempt from Federal, State and local taxes. A tax exempt form will be issued by the Owner upon execution of the contract.
20. RETAINAGE
Retainage will not be required for this project.
21. EQUAL OPPORTUNITY CLAUSE
In accordance with the laws of the State of New York and ordinances of the CITY OF
ITHACA, the Contractor shall not discriminate against any employee, applicant for employment, sub-contractor, supplier of materials or services, or program participant because of actual or perceived: age; creed; color; disability; domestic violence victim status; ethnicity; familial status; gender; gender identity or expression; height;
immigration or citizenship status; marital status; military status; national origin;
predisposing genetic characteristics; race; religion; sex; sexual orientation;
socioeconomic status; or weight.
22. NON-COLLUSIVE CERTIFICATION, DISCLOSURE OF LOBBYING
ACTIVITY, AND ELIGIBILITY CERTIFICATIONS
Bids shall be accompanied by the Non-Collusive, Disclosure of Lobbying Activities, and Eligibility Certifications.
23. PREVAILING WAGES
HECTOR STREET COMPLETE STREET, PIN 395063
IB-8
This is a prevailing wage contract. A certified payroll is required in this contract.
24. RESPONSIBILITY DETERMINATIONS
24.1 GUIDELINES
In deliberating upon the responsibility of the Bidder or a subcontractor, the Owner shall give due consideration to any credible evidence or reliable information that the past or current record of a Bidder or proposed contractor includes any of the following:
24.1.1 Lack of adequate expertise, prior experience with comparable projects or financial resources.
24.1.2 Criminal conduct in connection with government contract or the conduct of business activities involving the infliction, injury or intentional property damage, in connection with involvement in a pattern of racketeering, labor racketeering, extortion, obstruction of justice or other comparable crimes; bribery, fraud, bid-rigging, embezzlement or other comparable crimes; or serious moral turpitude, fundamental lack of integrity or knowing disregard for the law. Evidence of such conduct may include a judgment of conviction, pending criminal indictment of formal grant of immunity in connection with a criminal prosecution of the Bidder or proposed subcontractor, and director or officer, or any holder of five percent (5%) or more of the shares or equity of the Bidder or proposed subcontractor, or any affiliate of the Bidder or proposed subcontractor.
24.1.3 Grave disregard for the personal safety of employees, City personnel or members of the public. Due consideration shall be given to whether available evidence concerning the training of employees, equipment actually in use at the work site and company practices for identifying and addressing deficiencies and securing employee compliance demonstrates a genuine commitment to safety or lack of the same.
24.1.4 Any other significant Labor law violation, including but not limited to child labor law violations, failure to pay wages or unemployment insurance tax delinquencies.
24.1.5 Any significant violation of the Workers’ Compensation Law, including but not limited to the failure of a Bidder or proposed subcontractor to provide proof of workers’ compensation or disability benefits coverage.
24.1.6 Any criminal conduct involving violations of the Environmental Conservation Law or other federal, state or city environment statutes or repeated or significant civil violations of federal, state or city environmental statutes or regulations.
24.1.7 The failure of a Bidder or contractor to demonstrate good-faith efforts to comply with applicable federal, sate or city statutes and regulations requiring efforts to solicit and utilize minority-owned and women-owned business enterprises and disadvantaged business enterprises as potential subcontractors, in connection with a
HECTOR STREET COMPLETE STREET, PIN 395063
IB-9
pending bid for the performance of a federal-aid or state- or city-funded or assisted project subject to such statutory and regulatory requirements.
24.1.8 The failure of a Bidder, contractor or proposed subcontractor to comply with federal, state or city statutes or regulations requiring the hiring, training and employment of persons presumed to be disadvantaged in accordance with federal, state, or city definitions to meet federal, state and city equal employment opportunity requirements.
24.1.9 Submission of a bid that is mathematically or materially unbalanced.
24.1.10 The submission of a bid which is so much lower than the Owner’s engineers’ estimate for the cost of, or anticipated bids for, the contract that it appears unlikely that the Bidder will be able to perform the contract satisfactorily at the price bid.
24.1.11 Any other cause of so serious or compelling a nature that it raises questions about the present responsibility of a contractor or subcontractor, including but not limited to, submission to a contracting agency of a false or misleading statement on a uniform questionnaire, or in some other form, in connection with a bid for or award of a contract or a request for approval of a subcontractor.
24.1.12 The failure to offer for purchase, provide, or otherwise use products and services that have lesser or reduced effect on human health and the environment when compared with competing products or services that serve the same purpose, or that are not in compliance with the City of Ithaca Environmentally Preferable Purchasing policy guidelines.
24.1.13 In addition to the factors specified above, the Owner may also give due consideration to any other factors consideration by the contracting agencies to bear upon responsibility, including but not limited to any mitigating factor brought to the Owners’ attention by the Bidder or proposed subcontractor.
25. ESTIMATED QUANTITIES
The Bidder agrees that the estimated quantities given in the bid are only for the purpose of comparing bids and that the Bidder is satisfied with and will at no time dispute the estimates as a means of comparing the aforesaid bids, that the Bidder will make no claim for loss of profits or anticipated profits because of any difference between the estimated quantities and the quantities of the various classes of work actually furnished or performed, that the Owner not be held responsible if any of the estimated quantities should be found to not even approximate those actually measured during performance of the work, and the Owner may direct an increase, decrease or omission of the quantities of any class or part of the work as may be deemed necessary or desirable.
In the event of an overrun and/or underrun in the estimated unit price quantities contained in the bid, the unit price of that respective item will be used for payment.
HECTOR STREET COMPLETE STREET, PIN 395063
IB-10
26. FEDERAL AID PROJECT
Bidders are hereby notified that this is a Locally Administered Federal-Aid project and that all rules, regulations, reporting, and requirements shall be complied with, including, but not limited to, the Davis Bacon Act Wage laws.
SECTION 00400
HECTOR STREET COMPLETE STREET, PIN 395063
BF-1
BID FORM
PROPOSAL OF:
(hereinafter called "Bidder"), organized and existing under the laws of the State of ____________________ doing business as (a corporation) (a partnership) (an individual), to the City of Ithaca (hereinafter called "Owner").
In compliance with your Advertisement for Bids, Bidder hereby proposes to perform all work necessary for the completion of the Hector Street Complete Street, in conformance with the Contract Documents within the time frame set forth and at the prices stated below.
By submission of this Bid, each Bidder certifies, and in the case of a joint Bid, each party thereto certifies as to his own organization, that this Bid has been arrived at independently, without consultation, communication, or agreement as to any matter relating to this Bid with any other Bidder or with any competitor.
The Bidder’s attention is called to:
a. The fact that weather is always a consideration and it is reasonable to expect there may be significant periods of sub-freezing temperatures, high water flows, and precipitation during construction. Requests to extend the Contract Time or claims for delays in completion due in part or in whole to weather conditions will not be considered.
b. The fact this project is of limited construction duration and requires an expedited construction schedule for completion after award.
c. It is reasonable to expect material manufacturers may have limited production capacity and schedule opportunities. Requests to extend the Contract Time or claims for delays in completion due in part or in whole to providing the specified materials shall not be considered.
d. Bidder shall put forth the necessary level of effort required to achieve the substantial completion date and to complete all Work within the specified Contract Time, and shall include the costs of this effort in the Bid.
e. Liquidated damages are included in this Contract.
f. In regard to any taxes applicable to the project, the Contractor shall acquire a copy of form ST-120.1 from the NYS Department of Taxation and Finance and follow accordingly.
g. The Owner reserves the right to accept alternative bid items, if any, in any order or combination, unless otherwise specifically provided in the Bidding Documents. If the
SECTION 00400
HECTOR STREET COMPLETE STREET, PIN 395063
BF-2
Contract is to be awarded, it will be awarded to the lowest responsive/responsible Bidder who demonstrates the work experience and project management qualifications, meets all the terms of the Contract Documents, and offers the lowest cost on the basis of the sum of the Base Bid and the Alternates accepted, where evaluation by the Owner indicates to the Owner that award will be in the best interest of the project.
h. Final payment or release of retainage will be made to the Contractor upon completion of all services, submission of reports, as-built drawings, bonds, guarantees and approval of same by the Owner.
Bidder hereby agrees to commence work under this contract in accordance Article 3 - Contract Time and Performance of the Agreement, with completion in accordance with the Contract Term limits specified:
Substantial Completion within 180 calendar days of the date fixed in the Notice to Proceed and Final Completion within 240 calendar days of the date fixed in the Notice to Proceed.
The Bidder shall schedule the construction duration within the period of time between the Notice to Proceed and the completion dates referenced, and shall be expected to put forth the necessary level of effort required to achieve the completion dates so established and shall include the costs of this effort in the Bid.
The Contractor shall pay liquidated damages for each work day after the substantial completion date that Contractor requires to achieve substantial completion of the work as specified in the Special Note. Damages shall continue to be assessed until, in the opinion of the Owner, the project is ready for its intended use. The Contractor shall pay liquidated damages for each calendar day after the final completion date the Contractor requires to achieve final completion.
The Bidder shall submit a Unit Price Bid for all the work included in this Contract. On the following pages, the Bidder shall break down the Unit Price Bid by each item listing the unit bid price and extension by which he arrived at the Unit Price Bid. These items are probable quantities provided to the Bidder and are to be considered approximate only. The Owner does not expressly or by implication agree the actual quantities will correspond therewith and reserves the right to increase or decrease any quantity or to eliminate any quantity as the Owner may deem necessary.
The Bidder shall be satisfied as to the accuracy of these quantities prior to submitting the Bid.
The unit bid prices will be used to negotiate Change Orders should the Owner desire to modify the Scope of the project.
The Owner will award the contract for the proposed improvements to the Bidder submitting the lowest acceptable bid in accordance with the Contract Documents.
SECTION 00410
HECTOR STREET COMPLETE STREET, PIN 395063
BF-3
SUPPLEMENTAL A
BID PROPOSAL
PROJECT IDENTIFICATION: Hector Street Complete Street
PIN 395063
CP# 846
THIS BID IS SUBMITTED TO: City of Ithaca Department of Public Works 108 East Green Street Ithaca, New York 14850
1. The undersigned BIDDER proposes and agrees, if this Bid is accepted, to enter into an agreement with OWNER in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Contract Price and within the Contract Time indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.
2. BIDDER accepts all of the terms and conditions of the Advertisement for Bids, the Instructions to Bidders, and its supplement, if any, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for forty-five days after the day of Bid opening. BIDDER will sign and submit the Agreement with the Bonds and other documents required by the Bidding Requirements as indicated in the Instruction to Bidders.
3. In submitting this Bid, BIDDER represents and certifies, as more fully set forth in the Agreement, that:
a. BIDDER has examined copies of all the Contract Documents and of the following addenda, receipt of all which is hereby acknowledged:
Addendum Date Addendum Number
b. BIDDER has familiarized itself with the nature and extent of the Contract Documents, Work, site, locality, and all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work.
c. In accordance with the General Provisions, BIDDER has studied carefully all reports and tests of subsurface conditions and drawings of physical conditions, to the extent they exist at the time of Bidding.
HECTOR STREET COMPLETE STREET, PIN 395063
BF-4
d. BIDDER has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests and studies (in addition to or to supplement those referred to in
(C) above) which pertain to the subsurface or physical conditions at the site or otherwise may affect the cost, progress, performance or furnishing of the Work as BIDDER considers necessary for the performance or furnishing of the Work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract Document, similar information or data are, or will be required by BIDDER for such purposes.
e. BIDDER has reviewed and checked all information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsibility for the accurate location of said Underground Facilities. No additional examinations, investigations, explorations, test, reports of similar information or data in respect of said Underground Facilities are or will be required by BIDDER in order to perform and furnish the work at the Contract Price, within the Contract Time and in accordance with the other terms and conditions of the Contract Documents.
f. BIDDER has correlated the results of all such observations, examinations, investigations, explorations, tests, reports and studies with the terms and conditions of the Contract Documents.
g. BIDDER has given ENGINEER written notice of all conflicts, errors or discrepancies that it has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to BIDDER.
h. This Bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation;
BIDDER has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; BIDDER has not solicited or induced any person, firm or corporation to refrain from bidding; and BIDDER has not sought by collusion to obtain for itself any advantage over any other Bidder or over
OWNER.
4. BIDDER agrees that the work under this contract shall be substantially complete within 180 consecutive calendar days of the date of the NOTICE TO PROCEED. The work shall be completed and ready for final payment in accordance with the General Provisions within 240 calendar days of the date fixed in the NOTICE TO PROCEED.
The BIDDER accepts the provisions for the Agreement as to liquidated damages.
HECTOR STREET COMPLETE STREET, PIN 395063
BF-5
5. The following documents are submitted with and made a condition of this Bid:
a. Unit Price Proposal (Supplement A);
b. Required Bid security as outlined in Instructions to Bidders
(Supplement B);
c. Required Bidder’s Qualification Statement (Supplement C);
d. Disclosure of Lobbying Activities (Supplement D);
e. Non-Collusive Bidding Certification (Supplement E);
f. DBE Utilization Certification (Supplement F);
g. List of Subcontractors (Supplement G);
h. Iran Energy Divestment Certification (Supplement H);
i. Indemnification Agreement (Supplement I);
j. Statement of Insurance Coverage (Supplement J);
k. Non-Bidder’s Response (Supplement K);
l. Sexual Harassment Prevention Certification (Supplement L)
6. Estimated Quantities and Bid Item Description
a. The Bidder agrees that the estimated quantities given in the bid are only for the purpose of comparing bids and that the Bidder is satisfied with and will at no time dispute the estimates as a means of comparing the aforesaid bids, that the Bidder will make no claim for loss of profits or anticipated profits because of any difference between the estimated quantities and the quantities of the various classes of work actually furnished or performed, that the Owner not be held responsible if any of the estimated quantities should be found to not even approximate those actually measured during performance of the work, and the engineer may direct an increase, decrease or omission of the quantities of any class or part of the work as may be deemed necessary or desirable. The Bidder is advised that in the event of an overrun and/or underrun in the estimated unit price quantities contained in the bid, the unit price of that respective item will be used for payment.
b. Bidder shall complete the Work in accordance with the Contract Documents for the Hector Street Complete Street on, or before, the dates specified in the Contract Documents for the Unit Prices listed on attached document, Unit Price Proposal, and for the total estimated Base Bid sum of:
Write out in words
Write out in dollar figures
HECTOR STREET COMPLETE STREET, PIN 395063
BF-6
7. This Bid is submitted by:
If BIDDER is: An individual
By______________________________________________________________ (Individual’s Signature)
Name (typed or printed): ___________________________________________
Doing business as:_____________________________________
If BIDDER is: A Partnership by___________________________________________________________ (Partnership Name)
(Signature of General Partner – attach evidence of authority to sign)
Name (typed or printed): __________________________________________
If BIDDER is: A Corporation by__________________________________________________ (Corporation Name) (Seal)
(State of Incorporation) by _________________________________________________ (Signature – attach evidence of authority to sign)
Name (typed or printed): _________________________________
(Title) (Corporate Seal)
Attest_______________________________________________ (Secretary)
Date of Qualification to do business in New York is _____/_____/______
HECTOR STREET COMPLETE STREET, PIN 395063
BF-7
If BIDDER is: A Joint Venture
Name of Joint Venture: ___________________________________
First Joint Venture Name: ________________________________(SEAL) by________________________________________________________ (Signature – attach evidence of authority to sign)
Name (typed or printed): ______________________________________
Title: ______________________________________________________
Second Joint Venture Name: _____________________________(SEAL) by________________________________________________________ (Signature – attach evidence of authority to sign)
Name (typed or printed): ______________________________________
Title: ______________________________________________________
(Each joint venturer must sign. The manner of signing for each individual, partnership and corporation that is a party to the joint venture should be in the manner indicated above).
Following to be completed by all Bidders:
Bidder’s Business Address: __________________________________________
Phone No.: _______________________________________________________
Fax No.: _________________________________________________________
E-mail: __________________________________________________________
SUBMITTED ON: ___________________________________, 20_____
State Contractor License No.: ________________________________________ (if applicable)
HECTOR STREET COMPLETE STREET, PIN 395063
BF-8
HECTOR STREET COMPLETE STREET
BID PROPOSAL Brought Forward $ ………………..………….
DESCRIPTION UNIT QTY UNIT BID PRICE UNIT PRICE (WRITTEN) AMOUNT BID
201.06 CLEARING AND GRUBBING LS 1 $ ______________
_______________________________________________________ DOLLARS and
________________________________________________________ CENTS
203.02 UNCLASSIFIED EXCAVATION AND
DISPOSAL CY 3,460 $ ______________
_______________________________________________________ DOLLARS and
________________________________________________________ CENTS
203.03 EMBANKMENT IN PLACE CY 2,460 $ ______________
_______________________________________________________ DOLLARS and
________________________________________________________ CENTS
203.07 SELECT GRANULAR FILL CY 700 $ ______________
_______________________________________________________ DOLLARS and
________________________________________________________ CENTS
203.21 SELECT STRUCTURE FILL CY 139 $ ______________
_______________________________________________________ DOLLARS and
________________________________________________________ CENTS
204.0…