About this file

This file contains photographs documenting the location and scope of work for a drain line replacement project at Building 9 of the USDA ARS facility in Mississippi State. The images show: 1) a manhole connection point, 2) red spray paint markings indicating the sewer line location, 3) the section from cleanout to manhole, and 4) the section from manhole to cleanout. The photos are accompanied by basic technical specifications noting requirements for sawcutting to 8" maximum depth, 95% ASTM698 density compaction, hand compaction 12" above pipe, and sand bedding for PVC trench installation.

The related contract opportunity details a requirement to replace approximately 55 linear feet of collapsed 4" cast iron sanitary sewer line serving one toilet, one floor drain, and one sink in Building 9. The work is being solicited as a small business set-aside under NAICS 238220 with an estimated value between $25,000-$100,000. Quotes are due by January 13, 2025 at 3:00 PM CST, with a 90-day period of performance after Notice to Proceed. A non-mandatory site visit is available by contacting Neil P. Johnson at 662-684-9141.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Building 9 Drain Line, newest first.
File Type Posted
Statement of Work Repair B-9 Drain Line.docx DOCX document
ARS-372.pdf PDF
ARS 371.pdf PDF
SOLICITATION 12405B25Q0038.pdf PDF
Wage Grade Determination DBA MS20240045 Oktibbeha County MS.pdf PDF
SF25A PAYMENT BOND.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Title: “Replace Building 9 Drain Line” at the USDA ARS MS State, 150 Twelve Lane, MS State, MS 39762.

SAWCUT FULLDEPTH

8"MAX.DEPTH. COMPACTTO95% OFASTM698 DENSITY

HAND COMPACT TO12"ABOVEPIPE

SANDBEDDING

TYPICALPVC TRENCHDETAIL

SCALE: NONE

Photos Figure 1 Manhole

Figure 2 Red Spray point marks approximate location of sewer line

Figure 3 From cleanout to manhole

Figure 4 From manhole to cleanout image6.jpeg image7.jpeg image1.jpeg image2.png image3.png image3.jpeg image4.jpeg image5.jpeg