PhaseGratingAlignmentStages_STATEMENT OF WORK-Fianl-6-9-26.pdf
PDF 146 KB Posted
- Solicitation number
- 1333ND26QNB680282
About this file
This is a Statement of Work/Specifications for the upgrade of a Cold Neutron Imaging Instrument's Phase Grating Roll Alignment System at NIST. The procurement requires three high-precision rotation stages with supporting control hardware and software, to be delivered by 31 December 2026.
The rotation stages must meet stringent specifications: angular position resolution of 0.00001 degrees or better, a central clear aperture of at least 80 mm in diameter, mass under 1 kg, capability for full 360-degree rotation, minimum rotation speed exceeding 3 degrees per second, and ability to maintain resolution when mounted perpendicular to gravity while supporting 150 g. The stages must have zero backlash and mandatory powered-off position holding. The vendor must provide all required sensors, control hardware, and software (SDK-based in C/C++/C# or .NET) to achieve specified resolution across distances of up to 0.3 m between two stages and 5 m for the third stage. Cable lengths of 10 meters are required to position the control box outside a radiation area. An optional hand control unit with cable for manual operation during visible light alignment is requested.
The schedule of deliverables includes the three rotation stages, motion sensors and control hardware, cable sets, motion control software, and the optional hand control unit, all due 31 December 2026. Payment is 100% upon installation and acceptance of the fully installed system. The Government reserves the right to conduct performance testing and inspection within 15 days of receipt, with ownership transferring to NIST upon acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_1333ND26QNB680282.pdf | ||
| Attachment 2- Applicable Provisions and Clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
STATEMENT OF WORK/SPECIFICATIONS
Title: Upgrade of the Cold Neutron Imaging Instrument, Phase Grating Roll Alignment
System Date: 9 JUN 2026
I. BACKGROUND INFORMATION
The NIST neutron imaging team, in the Radiation Physics Division of the Physical Measurement Laboratory, is developing a far-field grating neutron interferometer to measure the projection of the pair correlation function, G(Z), of a sample of interest. This interferometer geometry requires precision alignment of 3 gratings about the roll direction of the neutron beam. Since G(Z) is a vector quantity, aligned perpendicular to the grating direction, the grating alignment stages need to be able to rotate a full 360°, with high resolution. The gratings are lines etched into silicon wafers, where the period of the lines is of order 1 micrometer and the wafers are 100 mm in diameter. The mass of a grating, including a holder is of order 100 g. The interferometer pattern is measured by translating one of the gratings, so that that mass of the alignment system must be kept to as low as achievable. For control hardware, the separation of two of the gratings along the beam ranges from 1 mm to 300 mm. The third grating is separated by up to 5 m. The overall grating alignment system requires translating the gratings in the vertical direction, requiring that the grating roll stages (which much also translate) be less than 1 kg in mass.
II. PURPOSE
This procurement is to obtain quantity three high precision rotation stages (resolution better than
0.00005 degrees) with a clear aperture to allow the beam to pass unattenuated and required cabling, control hardware, and control software.
Delivery Date
01 DEC 2026.
III. SPECIFIC REQUIREMENTS
SPECIFICATIONS
The rotation stage shall have an angular position resolution at least or better than 0.00001 degrees (lower is better).
1. The rotation stage shall have a central clear aperture at least 80 mm in diameter (larger is better).
2. The rotation stage shall have a mass less than 1 kg (less is better).
3. The rotation stage shall be able to rotate a full 360 degrees (continuous rotation is better).
4. The rotation stage shall have a minimum rotation speed of greater than 3 degrees per second
5. The rotation stage shall maintain resolution when mounted and operated such that the rotation axis is perpendicular to the vertical direction (perpendicular to gravity) and supporting a mass of 150 g (supporting a larger mass is better).
6. The rotation stage movement mechanism shall have 0 backlash and maintain position in the event of unplanned loss of electrical power. Mandatory powered-off position holding.
7. Vendor to provide all required sensors and control hardware and software to achieve the specified minimum resolution such that two rotation will separated at a maximum of 0.3 m and the third rotation stage will be 5 m from the other 2 stages.
2 | P a g e
8. Vendor to provide cables with lengths of 10 meters to allow the control box to be located outside a radiation area.
9. Optional: Hand control unit with cable to permit manual operation of the rotation stages during initial alignment performed with visible light.
IV. GENERAL REQUIREMENTS
Inspection & Acceptance In addition to the inspection and acceptance terms articulated in the specific FAR clause that allows the Government reserves the right to perform such performance tests and evaluations as defined below to verify specified system performance. Such tests and evaluations, if performed, shall be conducted within the environment that the system is to be operated. The Contractor has the right to be present during the tests and evaluations, if performed, at the Contractor’s expense.
NIST may choose at its discretion to forego this part of acceptance testing.
A visual inspection of the equipment will be performed by the NIST POC to identify surface defects or any form of indication that any equipment was damaged during transport to NIST. The Government shall have sole discretion to require repair or replacement of damaged and/or nonconforming supplies at no cost to the Government. The Government at any time prior to acceptance shall reject the equipment due to defects and/or nonconformance. The vendor is responsible for latent defects discovered any time after final inspection. However, the extent of its liability shall be prorated over the useful life of the equipment.
Ownership of the equipment shall transfer to NIST upon acceptance by the Government.
The Government will test, inspect, and accept or reject the equipment within 15 days of receipt of the equipment unless otherwise indicated above. The Government reserves the right to conduct quality assurance testing to confirm that a given instrument(s) meets the manufacturer’s and/or the Government’s performance specifications. It is anticipated that the equipment will meet all manufacturer’s specifications and/or the Government’s performance specifications identified in the most recent operations and maintenance manual for each piece of equipment and/or in this document.
V. SCHEDULE OF DELIVERABLES
Deliverable Number Description Format Due Date
Quantity
1 Phase grating roll alignment stages
Provide the required format for the deliverable.
For example, word, AutoCAD, Excel, PPT
31 DEC 2026 3
3 | P a g e
2 Motion sensors, motion control hardware, to control alignment stages
Sensors and controller to permit better than
0.00001 angular position resolution
31 DEC 2026 2
3 Sets of cables between stages, sensor, controllers
Cables are 10 m 31 DEC 2026 3
4 Motion control software
SDK based in C/C++/C# or
.NET
31 DEC 2026 1
5 (Optional) Hand control unit with cable to permit manual operation of the rotation stages during initial alignment performed with visible light.
31 DEC 2026 1
Standards of Acceptance: The NIST POC or COR shall review all the above deliverables and respond with an acceptance or request for revision email to the Contractor Point of Contact (POC) within 15 days.
VI. PAYMENT SCHEDULE
The Contractor will be paid, in accordance with the payments clause in the contract and as otherwise noted in this document, upon receipt of a proper invoice.
1. 100% after installation and acceptance by the POC of fully installed system
File details come from the government source that posted it. Updated .