Perry Park GI Improvements Issued for Bid.pdf

PDF 14 MB Posted

Attached to
WRC: Perry Park Improvements Rebid
Solicitation number
Oak-0000000979
Issued by
Michigan

About this file

This document is a comprehensive set of engineering and design plans for the Perry Park Green Infrastructure Improvements project, prepared by Geosyntec Consultants and MKSK Studios for the Joseph Jones Drain Drainage District in Pontiac, Michigan. The project involves creating a stormwater management system with green infrastructure improvements, including a stormwater wetland, drainage infrastructure, pedestrian paths, landscaping, and site restoration. The plans are dated May 9, 2025, with a subsequent re-bid date of July 29, 2025, and cover 19 detailed sheets including site layouts, grading, utility plans, erosion control, landscape design, and construction details.

The project is funded by the Clean Water State Revolving Fund (CWSRF), with federal award number SLRFRP0127 from the U.S. Department of the Treasury to the State of Michigan. The total project area is approximately 9.4 acres, with a composite runoff coefficient of 0.36. The design includes stormwater management calculations for channel protection, volume control, and 100-year detention, with a designed pump station and wetland system to reduce non-point source pollution. The project aims to improve water quality by collecting stormwater runoff, facilitating infiltration, and providing vegetative treatment. The site will feature native landscaping, including trees, shrubs, and ground cover, with specific attention to soil preparation, planting techniques, and long-term maintenance considerations.

View the file

Other files

File Type Posted
20250730 - Perry Park Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREPARED FOR: PREPARED BY:

VICINITY MAP

JOSEPH JONES DRAIN DRAINAGE DISTRICT

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

PONTIAC, MICHIGAN

GEOSYNTEC PROJECT NO. CSWR3013

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MICHIGAN 48105

TELEPHONE: 734.332.8004

OAKLAND COUNTY WATER

RESOURCES COMMISSIONER

ONE PUBLIC WORKS DRIVE 95 WEST

WATERFORD, MICHIGAN 48328

N

PROJECT

LOCATION

COVER SHEET

NOT FOR CONSTRUCTION

3057 NORTH ROCKWELL STREET

CHICAGO, ILLINOIS 60618

312.809.9707 MKSKSTUDIOS.COM

INDEX OF SHEETS

Sheet Number Sheet Title

FUNDED BY

CLEAN WATER STATE REVOLVING FUND

CW-5963A

SUPPORTED IN WHOLE OR IN PART, BY FEDERAL

AWARD NUMBER SLRFRP0127 AWARDED O THE

STATE OF MICHIGAN BY THE U.S. DEPARTMENT

OF THE TREASURY

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: May 9, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

.\(2025)0729 Seal.tif

LEGEND

FOUND IRON PIPE

FOUND MONUMENT

TREE OR BRUSH LIMIT

FOUND IRON ROD

C/L OF DITCH

EXIST. SANITARY SEWER

EXIST. SPOT ELEVATION

EXIST. OVERHEAD UTILITY LINE

EXIST. UTILITY POLE

EXIST. CONTOUR

EXIST. LIGHT POLE

BASSWOOD

BOX ELDER

CEDAR

WALNUT

SPRUCE

MAPLE

LOCUST

ASH

BIRCH

HAWTHORNE

EXIST. CATCH BASIN OR INLET

EXIST. STORM SEWER

EXIST. WATER MAIN

EXIST. BEEHIVE INLET

TREE LEGEND

OAK

PROPERTY LINE

0 20 40

SCALE IN FEET

N

NOTES

1. SURVEY INFORMATION SHOWN FROM MIDWESTERN CONSULTING

LLC. (DATED APRIL 19, 2024). GEOSYNTEC MAKES NO GUARANTEE

NOR ASSUMES ANY LIABILITY AS TO THE COMPLETENESS OR

ACCURACY OF THE SURVEY.

2. SUPPLEMENTAL EXISTING CONDITIONS INFORMATION HAS BEEN

ADDED TO SURVEY BACKGROUND BASED ON GEOSYNTEC'S SITE

VISIT.

3. ALL DIMENSIONS ARE GIVEN IN FEET.

4. ALL BEARINGS AND DISTANCES ARE BASED ON NAD83 MICHIGAN

STATE PLANES, SOUTH ZONE, INTERNATIONAL FOOT (2011

ADJUSTMENT), GPS DERIVED.

5. ALL ELEVATIONS SHOWN ARE REFERENCED TO NAVD83, GPS

DERIVED.

LEGAL DESCRIPTION

(PER NOWAK AND FRAUS ENGINEERS CERTIFIED SURVEY, JOB

#H295, PLS. CHAD FINDLEY #55108, DATED: 2/15/2013) LOT 635 AND

ALL OF VACATED NELSON STREET (50' WIDE) BETWEEN E. RUNDELL

STREET (60' WIDE) AND MARQUETTE STREET (60' WIDE) PER CITY OF

PONTIAC RESOLUTION 870, DATED 10-07-1975, OF THE PLAT OF

'MODERN HOUSING CORPORATION ADDITION" BEING A PART OF THE

SOUTHWEST 1/4 OF SECTION 21, T3N, R10E, CITY OF PONTIAC,

OAKLAND COUNTY, MICHIGAN AS RECORDED IN LIBER 20 OF PLATS,

ON PAGE 22 OF THE OAKLAND COUNTY RECORDS, EXCEPT THAT

PART BEING DESCRIBED AS: BEGINNING AT A POINT ON THE

SOUTHERLY LINE OF SAID LOT 635 BEING 476.14 FEET ALONG THE

ARC OF A CURVE TO THE LEFT, RADIUS OF 1402.69 FEET, CENTRAL

ANGLE OF 19°26'56" AND A CHORD BEARING OF S79°10'06"E, 473.86

FEET FROM THE SOUTHWEST CORNER OF SAID LOT 635; THENCE

N01°06'26"E, 106.47 FEET; THENCE N53°57'01"E, 180.00 FEET TO A

POINT ON THE NORTHERLY LINE OF SAID LOT 635 TO AN

ON-TANGENT CURVE; THENCE 176.74 FEET ALONG THE ARC OF A

CURVE TO THE LEFT, RADIUS OF 956.92 FEET, CENTRAL ANGLE OF

10°34'57", CHORD BEARING S67°42'50"E, 176.49 FEET TO A REVERSE

CURVE; THENCE 39.11 FEET ALONG THE ARC OF A CURVE TO THE

RIGHT, RADIUS OF 20.00 FEET, CENTRAL ANGLE OF 112°02'31",

CHORD BEARING S16°59'03"E, 33.17 FEET; THENCE S39°02'12"W, 79.70

FEET TO A TANGENT CURVE; THENCE 93.00 FEET ALONG THE ARC OF

A CURVE TO THE RIGHT, RADIUS OF 125.30 FEET, CENTRAL ANGLE

OF 42°31'34", CHORD BEARING S.62°03'51"W., 90.88 FEET TO A

COMPOUND CURVE; THENCE 190.47 FEET ALONG THE ARC OF A

CURVE TO THE RIGHT, RADIUS OF 1402.69 FEET, CENTRAL ANGLE OF

07°46'48", CHORD BEARING S87°13'02"W, 190.32 FEET TO THE POINT

OF BEGINNING.

BENCHMARKS

SET SPIKE IN E. SIDE OF UTILITY POLE LOCATED WEST OF

BITUMINOUS PARKING ALONG THE WEST SIDE OF PERRY PARK ±260

FEET SOUTH OF MARQUETTE STREET. ELEVATION=944.88 (NAVD88)

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

EXISTING CONDITIONS

EXISTING VIEW A

MATCHLINE - EXISTING VIEW A

MATCHLINE - EXISTING VIEW A

LIMITS OF WORK

EXISTING GROUND MAJOR CONTOUR (5')

EXISTING GROUND MINOR CONTOUR (1')

RIGHT-OF-WAY

TREE PROTECTION FENCE

REMOVE CONCRETE

STABILIZED CONST. ENTRANCE (SEE SHEET 7)

TOPSOIL STOCKPILE AND STAGING AREA

PROTECT

REMOVE

SALVAGE

CONSTRUCTION FENCE

LEGEND

X

SF

SF

PERFORATED RISER

WITH ROCK JACKET

LOW

SF SILT FENCE

REMOVE PICNIC

TABLE AND

BARBEQUE GRILL

TREE PROTECTION FENCE (TYP)

REMOVE PICNIC

TABLE AND

BARBEQUE GRILL

REMOVE CONC. PAD

REMOVE CONCRETE PAD

PROPERTY LINE

TREE PROTECTION FENCE (TYP)

TREE PROTECTION FENCE (TYP)

PROTECT EX SIGN

PROTECT EXISTING BOLLARDS,

PUMP STATION, AND

ASSOCIATED ELECTRICAL

INFRASTRUCTURE

REMOVE EX

LIGHT POLE

CONTRACTOR TO REMOVE

BUILT UP SOIL AND

VEGETATION ON TOP OF THE

EXISTING ASPHALT AND IN

BETWEEN CURB STOPS ALONG

THE EAST EDGE OF THE

PARKING AREA IN ORDER TO

MAINTAIN POSITIVE DRAINAGE

(484 LF)

REMOVE 37 LF OF 12"

STORM DRAIN SEE UTILITY

PLAN FOR PROPOSED

CONNECTION

REMOVE EXISTING CATCH BASIN

SF

SF

SF

SF

SF

SF

SF

SF

TOPSOIL STOCKPILE

AND STAGING AREA

6' x 12' SEDIMENT TRAP

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X X

X X

X X

X X

X X

X X

X X

X

X

X

X

X

X

X

X

X

X X

X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

PERFORATED RISER WITH ROCK JACKET

EXISTING CATCH BASIN TO BE

CONVERTED INTO PERFORATED RISER

AND REMAIN IN PLACE UNTIL CB 101 IS

INSTALLED. SEE SESC PHASE II

SEQUENCE

EXISTING STORM DRAIN TO REMAIN IN

PLACE UNTIL CB 101 IS INSTALLED.

SEE SESC PHASE II SEQUENCE

230 LF SILT FENCE

CONTRACTOR TO CLEAR AND

GRUB ENTIRE AREA WITHIN

LIMITS OF WORK

CONTRACTOR TO CLEAR AND

GRUB ENTIRE AREA WITHIN

LIMITS OF WORK

LOW

LOW

LOW

LOW

LOW

LOW

LOW

LO

W

LOW

LO

W

LO

W

LOW

LOW

LO

W

LOW

LO

W

LO

W

LO

W

LO

W

LO

W

LO

W

CONSTRUCTION ENTRANCE

X

X X

X

X

SF

PROTECT EX SIGN

X

X

X

X

X

X X

X

X

XX

X

X

X

X

X

X

X

X

X

X

X

X

TREE PROTECTION FENCE (TYP)

GATE

CONTRACTOR TO CLEAR AND

GRUB ENTIRE AREA WITHIN

LIMITS OF WORK

LOW

LOW

LO

WLOW

LOW

LO

W

0 20 40

SCALE IN FEET

N

NOTES

1. NOTIFY THE ENGINEER IN WRITING OF ANY IDENTIFIED DISCREPANCIES WITHIN

THE CONSTRUCTION DOCUMENTS PRIOR TO THE START OF WORK.

2. PRIOR TO THE COMMENCEMENT OF WORK, VERIFY LOCATIONS AND DEPTHS OF

ALL UNDERGROUND UTILITIES THAT MAY BE AFFECTED BY CONSTRUCTION AND

TAKE RESPONSIBILITY FOR DAMAGES TO SUCH UTILITIES CAUSED AS A RESULT

OF CONSTRUCTION.

3. TAKE ALL NECESSARY PRECAUTIONARY MEASURES TO PROTECT THE PUBLIC AND

ADJACENT PROPERTIES FROM DAMAGE THROUGHOUT CONSTRUCTION,

INCLUDING DAMAGES TO UTILITIES, WALKS, WALLS, DRIVES, AND CURBS.

4. PROTECT ALL EXISTING FEATURES NOT MARKED FOR REMOVAL.

5. SECURE ALL NECESSARY PERMITS AND NOTIFY ALL UTILITY COMPANIES WITH

UTILITIES ON THE SITE PRIOR TO THE CONSTRUCTION OF THE PROJECT. ADHERE

TO ALL APPLICABLE LOCAL, STATE AND FEDERAL LAWS OR REGULATIONS

PERTAINING TO THE PROJECT.

6. ESTABLISH AND MAINTAIN SITE SECURITY UNTIL PROJECT ACCEPTANCE.

7. USE DIMENSIONS SHOWN ON DRAWINGS FOR LAYOUT OF THE WORK. DO NOT

USE SCALE DIMENSIONS FROM PLANS, SECTIONS OR DETAILS ON THE DRAWINGS.

8. DETAILS NOTED AS TYPICAL SHALL APPLY IN ALL CASES UNLESS SPECIFICALLY

SHOWN OR NOTED OTHERWISE. WHERE NO SPECIFIC DETAIL IS SHOWN, THE

CONSTRUCTION SHALL BE IDENTICAL OR SIMILAR TO THAT INDICATED FOR LIKE

CASES OF CONSTRUCTION ON THIS PROJECT.

9. TAKE NOTE OF ALL GRADING AND DRAINAGE WAYS AND MAINTAIN THESE DRAIN

WAYS FLOWS FREE OF OBSTRUCTIONS.

10. ALL CONSTRUCTION SHALL CONFORM TO ALL APPLICABLE CODES, REGULATIONS,

AND ORDINANCES PER CITY OF PONTIAC, MICHIGAN PUBLIC WORKS STANDARDS

AND SPECIFICATIONS.

11. ALL SOIL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSTALLED

PRIOR TO STARTING REMOVALS AND DEMOLITION.

12. EXISTING TREES TO REMAIN SHOULD BE PROTECTED WITH TEMPORARY FENCING

TO THE DRIP LINE. NO WORK SHALL OCCUR WITHIN THE DRIP LINE.

13. PRIOR TO CONSTRUCTION, ALL FENCING AND BARRICADES SHALL BE INSTALLED.

14. CONTRACTOR TO CLEAR AN D GRUB ENTIRE AREA WITHIN LIMITS OF WORK

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

SITE DEMOLITION AND EROSION CONTROL PLAN

MATCHLINE - SITE AND DEMOLITION VIEW A

SITE AND DEMOLITION VIEW A

BEST MANAGEMENT PRACTICE (BMP) IMPLEMENTATION SEQUENCE

PHASE 1

1. POST SESC PERMIT AT CONSTRUCTION ENTRANCE.

2. STAKE THE PROJECT LIMITS OF DISTURBANCE AS SHOWN ON THE SESC DRAWING.

3. BEGIN CLEARING AND GRUBBING ONLY THE MINIMUM AREA NECESSARY FOR

INSTALLATION BMPS. CLEAR AREAS REQUIRED FOR BMPS AS EACH BMP IS BEING

INSTALLED.

4. INSTALL STABILIZED CONSTRUCTION ENTRANCES.

5. INSTALL INLET PROTECTION IN EXISTING INLETS.

6. INSTALL PERFORATED RISER AND ROCK JACKET AT EXISTING CB (BEEHIVE).

7. INSTALL TEMPORARY SEDIMENT TRAPS. STABILIZE IMMEDIATELY UPON

COMPLETION OF SEDIMENT TRAP CONSTRUCTION.

8. INSTALL TREE PROTECTION.

9. REMOVE EXISTING LIGHT POLE, BARBEQUE GRILLS, PICNIC TABLES AND

ASSOCIATED CONCRETE PADS.

10. CONTRACTOR TO COORDINATE AND CONDUCT SWPPP PHASE 1 IMPLEMENTATION

REVIEW MEETING PRIOR TO BEGINNING PHASE 2.

MATCHLINE - SITE AND DEMOLITION VIEW A

SEE LANDSCAPING DETAILS

X

X X

X

X

SF

PROTECT EX SIGN

X

X

X

X

X

X X

X

X

XX

X

X

X

X

X

X

X

X

X

X

X

X

TREE PROTECTION FENCE (TYP)

LOW

LOW

LO

WLOW

LOW

LO

W

ST

ST

D

D

947948

941942

940941942

94194

PROPERTY LINE

SF

SF

SF

SF

SF

SF

SF

SF

TOPSOIL STOCKPILE

AND STAGING AREA

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X X

X X

X X

X X

X X

X X

X X

X

X

X

X

X

X

X

X

X

X X

X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

LOW

LOW

LOW

LOW

LOW

LOW

LOW

LO

W

LOW

LO

W

LO

W

LOW

LOW

LO

W

LOW

LO

W

LO

W

LO

W

LO

W

LO

W

LO

W

SURFACE ROUGHENING ON

SLOPES > 5%

970 LF FIBER LOG AROUND ROCK

INLET PROTECTION

INLET PROTECTION

CONTRACTOR MAY EXPAND OR

RELOCATE SEDIMENT TRAPS TO

CAPTURE AND DIRECT WATER TO

PERFORATED RISER

ROCK DONUT

PROTECTION

345 LF FIBER LOG AROUND ROCK

LEGEND

LIMIT OF WORK

EXISTING MAJOR CONTOUR (5')

EXISTING MINOR CONTOUR (1')

PROPOSED MAJOR CONTOUR (5')

PROPOSED MINOR CONTOUR (1')

WETLAND ELEVATION INDICATOR

FIBER LOG

SEDIMENT TRAP

INLET PROTECTION (SEE SHEET 7)

ROCK DONUT FES PROTECTION

TEMPORARY SEEDING AND STABILIZAITON

LOW

0 20 40

SCALE IN FEET

N

NOTES

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

PROPOSED EROSION CONTROL PLAN

MATCHLINE - EROSION CONTROL VIEW A

MATCHLINE - EROSION CONTROL VIEW A

EROSION CONTROL VIEW A

BEST MANAGEMENT PRACTICE (BMP) IMPLEMENTATION SEQUENCE

PHASE 2

1. BEGIN CLEARING AND GRUBBING THE SITE (PHASE CLEARING AND

GRUBBING TO THE EXTENT PRACTICAL TO MINIMIZE THE AMOUNT OF AREA

DISTURBED AT ANY GIVEN TIME).

2. STRIP AND STOCKPILE TOPSOIL. SOIL STOCKPILE MUST BE STABILIZED

WITH TEMPORARY SEED AND PROVIDED PERIMETER CONTROLS IN

ACCORDANCE WITH THE SESC DETAIL.

2. BEGIN GRADING THE SITE.

3. IMPLEMENT TEMPORARY STABILIZATION MEASURES ON ANY DISTURBED

AREAS WHERE CONSTRUCTION ACTIVITIES WILL NOT RESUME FOR 14

DAYS OR MORE. IMPLEMENTATION OF TEMPORARY STABILIZATION

MEASURES MUST BE INITIATED IMMEDIATELY AND COMPLETED WITHIN

SEVEN (7) DAYS FROM WHEN CONSTRUCTION ACTIVITIES TEMPORARILY

CEASED ON ANY PORTION OF THE SITE.

4. BEGIN INSTALLATION OF ROCK DRAINAGE LAYER AND UNDERDRAIN.

INSTALL FIBER ROLL ALONG EDGE OF ROCK LAYER AS IT IS INSTALLED.

5. CONTRACTOR MAY EXTEND OR RELOCATE SEDIMENT TRAPS AS

NECESSARY TO MANAGE STORMWATER ONSITE. ALL STORMWATER

SHOULD BE DIRECTED THROUGH SEDIMENT TRAPS AND THE PERFORATED

PIPE WITH ROCK JACKET UNTIL CB 101 AND FES 101 ARE INSTALLED WITH

ROCK DONUT. CONTRACTOR MAY USE SOLID-WALLED PIPE AS NECESSARY

TO DIRECT STORM WATER FROM OR THROUGH ROCK DRAINAGE LAYER. IF

PIPE IS USED TO DIRECT WATER, IT MUST BE REMOVED OR PROPERLY

ABANDONED (INCLUDING CAPS FOR TEMPORARY LATERALS FROM

UNDERDRAIN SYSTEM).

6. INSTALL STORM PIPE AND STRUCTURES. INSTALL INLET PROTECTION

MEASURES AT STORM SEWER INLETS AS EACH INLET STRUCTURE IS

INSTALLED. INSTALL ROCK DONUT AT FES 101 AS SOON AS THE

STRUCTURE IS INSTALLED.

7. CONTRACTOR MAY PUMP FROM THE FILTERED WATER WITHIN

PERFORATED RISER INTO CB 101 DURING THE TRANSITION. ROCK DONUT,

ROCK DRAINAGE LAYER, AND INLET PROTECTION MUST BE INSTALLED AT

CB 101 PRIOR TO RECEIVING STORMWATER BY GRAVITY FLOW.

8. ONCE CB 101 AND ASSOCIATED CONTROLS (ROCK DONUT, FIBER ROLL,

AND INLET PROTECTION) ARE INSTALLED AND FUNCTIONAL, EXISITNG CB,

EXISTING PIPE, AND SEDIMENT TRAPS MAY BE REMOVED.

9. INSTALL GRASSED SWALE. IMMEDIATELY STABILIZE SWALE UPON

COMPLETION.

10. COMPLETE GRADING, MAINTENANCE PATHS, BOULDER STONES,

PROPOSED PICNIC AREAS, AND INSTALLATION OF PERMANENT

STABILIZATION MEASURES ON ALL DISTURBED AREAS. FINAL

STABILIZATION OF DISTURBED AREAS MUST BE INITIATED IMMEDIATELY

AND COMPLETED WITH FIVE (5) CALENDAR DAYS FROM WHEN CLEARING,

GRADING, EXCAVATING, OR OTHER EARTH-DISTURBING ACTIVITIES HAVE

CEASED ON ANY PORTION OF THE SITE.

11. REMOVE ALL REMAINING TEMPORARY BMPS UPON APPROVAL OF

OAKLAND COUNTY WRC, OR ITS DESIGNATED REPRESENTATIVE.

12. PERMANENTLY STABILIZE ANY AREAS DISTURBED BY THE REMOVAL OF

TEMPORARY BMPS.

13. JET UNDERDRAIN PIPES TO ENSURE THE PIPES ARE CLEARED OF

BLOCKAGES. REMOVE ANY SEDIMENT ACCUMULATION IN CB 101.

14. NOTIFY OAKLAND COUNTY WRC, OR ITS DESIGNATED REPRESENTATIVE,

OF FINAL SITE STABILIZATION. THE SITE IS CONSIDERED TO HAVE

REACHED FINAL STABILIZATION WHEN EVERY SQUARE FOOT OF GROUND

DISTURBANCE IS VEGETATED WITH A DENSITY OF 90% AND AT LEAST 1

INCH IN HEIGHT.

15. OAKLAND COUNTY WRC, OR ITS DESIGNATED REPRESENTATIVE, TO

SUBMIT NOTICE OF TERMINATION TO THE PERMITTING AGENCY.

NOTE:THE CONTRACTOR MAY COMPLETE CONSTRUCTION ACTIVITIES

CONCURRENTLY PROVIDED ALL PRECEDING BMPS AND STABILIZATION

ACTIVITIES HAVE BEEN COMPLETELY INSTALLED.

* DORMANT SEEDING IS FOR USE IN THE LATE FALL AFTER THE SOIL TEMPERATURE REMAINS

CONSISTENTLY BELOW 50 F, PRIOR TO THE GROUND FREEZING. THIS PRACTICE IS

APPROPRIATE IF CONSTRUCTION ON A SITE IS COMPLETED IN THE FALL BUT THE SEED WAS NOT

PLANTED PRIOR TO RECOMMENDED SEEDING DATES. NO SEED GERMINATION WILL TAKE PLACE

UNTIL SPRING. A COOL SEASON ANNUAL GRASS MAY BE ADDED IN AN ATTEMPT TO HAVE SOME

FALL GROWTH.

· MULCH MUST BE USED WITH DORMANT SEED.

· DO NOT SEED WHEN THE GROUND IS FROZEN OR SNOW COVERED.

PLANTING ZONES:

SEEDING WINDOW

ZONE 1 ZONE 3ZONE 2

5/1 - 10/1

SOURCE: ADAPTED FROM MDOT INTERIM 2003 STANDARD SPECIFICATIONS FOR

CONSTRUCTION

4/15 - 10/10 5/1 - 9/20

LOWER PENINSULA

(NORTH OF T20N)

LOWER PENINSULA

(SOUTH OF T20N)

UPPER PENINSULA

LOWER PENINSULA

(SOUTH OF U.S. 10)

SOURCE: ADAPTED FROM USDA NRCS TECHNICAL GUIDE #342 (1999)

11/1 - FREEZE

4/1 - 8/1

SEEDING DATES

(WITH IRRIGATION

OR MULCH)

10/25 - FREEZE10/25 - FREEZE

UPPER

PENINSULA

ZONE 3

5/1 - 9/10

Lower PENINSULA

(NORTH OF U.S. 10)

ZONE 2

5/1 - 9/20

ZONE 1

DORMANT

SEEDING

DATES*

o

SEEDING DATES

(W/O IRRIGATION

OR MULCH)

4/1 - 5/20 5/1 - 6/10 5/1 - 6/15

8/10 - 10/1 8/1 - 9/20 8/1 - 9/20 or or or

SEEDING WINDOW 11/15 - Freeze 11/01 - Freeze

PERMANENT SEEDING

DORMANT SEEDING*

11/01 - Freeze

INSTALLATION

1. REVIEW SESC PLAN AND CONSTRUCTION PHASING TO IDENTIFY AREAS IN NEED OF PERMANENT

VEGETATIVE STABILIZATION.

2. PREPARE SEEDBED AND APPLY SEED IN ACCORDANCE WITH LANDSCAPE PLAN AND RELATED

DETAILS AND SPECIFICATIONS.

3. MULCH IMMEDIATELY AFTER SEEDING.

4. DORMANT SEED MIXES ARE FOR USE AFTER THE GROWING SEASON, USING SEED WHICH LIES

DORMANT IN THE WINTER AND BEGINS GROWING AS SOON AS SITE CONDITIONS BECOME

FAVORABLE.

5. PROTECT SEEDED AREAS FROM PEDESTRIAN OR VEHICULAR TRAFFIC.

6. DIVERT CONCENTRATED FLOWS AWAY FROM THE SEEDED AREA UNTIL VEGETATION IS

ESTABLISHED.

MAINTENANCE

· INSPECT WEEKLY AND WITHIN 24 HOURS FOLLOWING EACH RAIN EVENT IN THE FIRST FEW

MONTHS FOLLOWING INSTALLATION TO BE SURE SEED HAS GERMINATED AND PERMANENT

VEGETATIVE COVER IS BEING ESTABLISHED.

· ADD SUPPLEMENTAL SEED AS NECESSARY.

· SEEDS NEED ADEQUATE TIME TO ESTABLISH.

· MAY NOT BE APPROPRIATE IN AREAS WITH FREQUENT TRAFFIC.

· SEEDED AREAS MAY REQUIRE IRRIGATION DURING DRY PERIODS.

· SEEDING SUCCESS IS SITE SPECIFIC, CONSIDER MULCHING OR SODDING WHEN NECESSARY.

SEED TYPE

OATS, BARLEY

ANNUAL RYE

WHEAT

SOURCE: ADAPTED FROM USDA NRCS TECHNICAL GUIDE #342 (1999)

BUCKWHEAT

PERENNIAL

RYEGRASS

INSTALLATION

1. REVIEW CONSTRUCTION PHASING AND SOIL EROSION CONTROL PLAN TO IDENTIFY

AREAS REQUIRING TEMPORARY SEEDING.

2. SELECT ANNUAL GRASS SEED FOR TEMPORARY COVER AREAS.

3. SEED MIXES MAY VARY, SHOULD ONLY CONTAIN ANNUAL, NON-AGGRESSIVE SPECIES,

AND GENERALLY INCLUDE RYE, WHEAT, OR OAT SPECIES. SEED MIXES SHOULD BE

OBTAINED FROM A SEED SUPPLIER AS SEED MIXES ARE DEPENDENT ON SOIL TYPE,

LIGHT, MOISTURE, AND USE APPLICATION.

4. PREPARE SEEDBED BY REMOVAL OF CONSTRUCTION/WOODY DEBRIS. THEN SCARIFY

OR RAKE SEEDBED.

5. SLOPES STEEPER THAN 1:3 SHOULD BE ROUGHENED.

6. APPLY SEED AS SOON AS POSSIBLE AFTER SEEDBED PREPARATION. MULCH

IMMEDIATELY AFTER SEEDING ALL SLOPES, UNSTABLE SOILS, HEAVY CLAY SOILS, AND

ALL AREAS ADJACENT TO WETLANDS, WATERCOURSES, OR SENSITIVE AREAS.

7. THE TIME TO SEED IS DEPENDENT ON THE CLIMATE OF THE AREA. MICHIGAN HAS

THREE CLIMATIC ZONES.

8. PROTECT SEEDED AREAS FROM PEDESTRIAN/VEHICULAR TRAFFIC.

9. DIVERT CONCENTRATED FLOWS AWAY FROM SEEDED AREA UNTIL VEGETATION IS

ESTABLISHED.

10. INSPECT TEMPORARY SEEDED AREAS WEEKLY AND FOLLOWING EACH RAIN EVENT

UNTIL FINAL GRADING AND STABILIZATION ACTIVITIES ARE COMPLETED.

11. MUST BE FOLLOWED BY PERMANENT SEEDING.

MAINTENANCE

· SEEDS NEED ADEQUATE TIME TO ESTABLISH.

· MAY NOT BE APPROPRIATE IN AREAS WITH FREQUENT TRAFFIC.

· SEEDED AREA MAY REQUIRE IRRIGATION IN DRY PERIODS.

4/1 - 9/15 per 1,000 sq.ft.

8/1 - 10/15

9/20 - 10/15

4/15 - 8/1

8/1 - 10/10

9/10 - 10/10

5/1 - 8/1

8/1 - 11/1

9/10 - 10/1

2 lbs.

per acre

96 lbs.

AMOUNT

3 lbs. 120 lbs.

3 lbs. 120 lbs.

ZONE 1

LOWER PENINSULA

(SOUTH OF U.S. 10)

ZONE 2

LOWER PENINSULA

(NORTH OF U.S. 10)

ZONE 3

UPPER PENINSULA

6/1 - 7/15 6/1 - 7/15 6/15 - 7/15 2 lbs. 75 lbs.

8/1 - 10/15 6/1 - 8/1 8/1 - 10/1 0.5 lbs. 20 lbs.

GENERAL NOTES:

1. THE CONTRACTOR SHALL MAINTAIN A COPY OF THE SESC PERMIT AND PLAN ON THE SITE FOR THE DURATION

OF CONSTRUCTION.

2. THE CONTRACTOR SHALL ADHERE TO THE SESC PLAN DURING CONSTRUCTION OPERATIONS.

3. THE SESC PLAN INCLUDES RELEVANT SPECIFICATIONS, A NARRATIVE PLAN AND ASSOCIATED APPENDICES, AND THE SESC DRAWINGS AND ASSOCIATED DETAIL SHEETS.

4. IT IS THE CONTRACTOR'S RESPONSIBILITY TO MAINTAIN AND REPAIR ALL BMPS DURING CONSTRUCTION.

5. ALL EARTH-DISTURBING CONSTRUCTION ACTIVITIES SHALL BE PERFORMED WITHIN THE LIMITS OF

DISTURBANCE AS INDICATED ON THE SESC DRAWINGS.

6. THE CONTRACTOR IS RESPONSIBLE FOR REVIEWING THE LIMITS OF DISTURBANCE SHOWN ON THE DRAWINGS AND FIELD-STAKING THE LIMITS OF DISTURBANCE LINE PRIOR TO THE START OF CONSTRUCTION.

7. BMPS DEPICTED ON THE PHASE 1 SESC DRAWING ARE TO BE INSTALLED PRIOR TO THE START OF ANY LAND

CLEARING OR GRADING ACTIVITIES.

8. THE CONTRACTOR SHALL APPLY TEMPORARY EROSION AND SEDIMENTATION CONTROL MEASURES WHEN REQUIRED BY THESE PLAN DRAWINGS AND IMPLEMENT ADDITIONAL MEASURES AS DICTATED BY SITE

CONDITIONS.

9. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ANY SEDIMENTATION RESULTING FROM WORK ON THIS SITE IS CONTAINED ON THE SITE AND NOT ALLOWED TO COLLECT ON ANY OFF-SITE AREAS OR IN

WATERWAYS.

10. SLOPES ARE TO BE LEFT IN A ROUGHENED CONDITION DURING THE GRADING PHASE TO REDUCE RUNOFF

VELOCITIES AND EROSION.

11. CONTRACTOR LAYDOWN, STAGING AND STOCKPILE AREAS ARE TO BE LOCATED WITHIN THE PERMITTED

LIMITS OF DISTURBANCE.

12. SILT FENCE IS TO BE INSTALLED AROUND THE PERIMETER OF ON-SITE SOIL STOCKPILE AREAS AS DICTATED BY SITE CONDITIONS. ADDITIONALLY, INACTIVE PORTIONS OF THE STOCKPILE AREAS ARE TO BE STABILIZED

AS REQUIRED HEREIN.

13. THE CONTRACTOR IS RESPONSIBLE FOR REGULARLY CHECKING SEEDED AREAS TO SEE THAT A GOOD STAND OF VEGETATION IS ESTABLISHED. AREAS SHOULD BE FERTILIZED, WATERED, AND RESEEDED AS NEEDED.

THE CONTRACTOR IS RESPONSIBLE TO ENSURE VEGETATION IS ESTABLISHED FOR A WARRANTY PERIOD OF

TWO FULL GROWING SEASONS.

14. TRACKING OF SOIL AND SEDIMENT ONTO OFF-SITE ROADWAYS SHALL BE MINIMIZED THROUGH THE USE OF APPROPRIATE MEASURES. THE CONTRACTOR SHALL IMMEDIATELY REMOVE ANY SOIL OR SEDIMENT TRACKED

ONTO THE ROADWAYS.

15. THE CONTRACTOR SHALL BRING TO THE SITE AND USE ONLY EQUIPMENT THAT IS WELL-MAINTAINED AND

WITHOUT LEAKS.

16. THE SOIL EROSION AND SEDIMENT CONTROLS WILL BE MAINTAINED WEEKLY AND AFTER EVERY STORM

EVENT BY THE CONTRACTOR

DEWATERING

DISCHARGES FROM DEWATERING ACTIVITIES, INCLUDING DISCHARGES FROM DEWATERING OF TRENCHES AND EXCAVATIONS, ARE PROHIBITED UNLESS MANAGED BY APPROPRIATE CONTROLS. IN NO CASE IS WATER FROM

DEWATERING ACTIVITIES TO BE PUMPED OFF-SITE WITHOUT BEING PROPERLY TREATED.

DEWATERING THAT HAS SEDIMENT-LADEN WATER MUST DISCHARGE TO A SEDIMENT BASIN OR EQUIVALENT SETTLING, FILTERING, OR ENERGY DISSIPATION MEASURES TO REMOVE SUSPENDED SOLIDS BEFORE DISCHARGE.

SEDIMENT BAGS, INFILTRATION TRENCHES, VEGETATED SWALES, OR FILTER BERMS MAY ALSO BE USED.

SECONDARY CONTAINMENT SHOULD BE USED TO PREVENT THE POTENTIAL LEAK OF CHEMICALS USED DURING

DEWATERING, SUCH AS CHEMICALS FOR FLOCCULATION.

CONCRETE WASHOUT

DISCHARGE OF EXCESS OR WASTE CONCRETE AND/OR WASH WATER FROM CONCRETE TRUCKS WILL BE ALLOWED ON THE CONSTRUCTION SITE, BUT ONLY IN DESIGNATED LINED AND DIKED AREAS TO PREVENT CONTACT BETWEEN THE CONCRETE AND/OR WASH WATER AND STORMWATER THAT WILL BE DISCHARGED FROM

THE SITE. THE DESIGNATED CONCRETE WASHOUT SHALL BE INDICATED WITH SIGNAGE.

ANY DISCHARGE FOR WASHING AND/OR RINSING WATERS FROM CONCRETE MIXING EQUIPMENT INCLUDING READY MIX TRUCKS IS PROHIBITED. SUCH POLLUTANTS SHALL BE ADEQUATELY TREATED AND CANNOT BE DISCHARGED TO WATERS OF THE STATE. ANY SPILLS SHALL BE CLEANED IMMEDIATELY UPON DISCOVERY.

DUST CONTROL

LARGE AREAS OF SOIL THAT ARE DENUDED OF VEGETATION AND HAVE NO PROTECTION FROM PARTICLES BEING PICKED UP AND CARRIED BY WIND SHOULD BE PROTECTED WITH A TEMPORARY COVER OR KEPT UNDER CONTROL WITH WATER OR OTHER SOIL ADHERING PRODUCTS TO LIMIT WIND TRANSPORTED PARTICLES EXITING

THE SITE PERIMETER.

WATER TRUCKS OR OTHER DUST CONTROL AGENTS ARE TO BE USED AS NEEDED DURING CONSTRUCTION TO MINIMIZE DUST GENERATED ON THE SITE. TACKIFIERS MAY BE USED TO HOLD SOIL IN PLACE AND PREVENT DUST.

MANUFACTURER RECOMMENDATIONS FOR APPLICATION RATES MUST BE USED FOR DUST CONTROL

APPLICATIONS. DUST CONTROL MUST BE PROVIDED BY THE CONTRACTOR TO A DEGREE THAT IS IN COMPLIANCE

WITH APPLICABLE LOCAL AND STATE DUST CONTROL REGULATIONS.

EQUIPMENT/VEHICLE MAINTENANCE

DISCHARGE FROM WASHING AND MAINTENANCE OF EQUIPMENT OR VEHICLES WILL BE ALLOWED ON THE CONSTRUCTION SITE, BUT ONLY IN DESIGNATED LINED AND DIKED AREAS TO PREVENT CONTACT BETWEEN THE

WASH WATER AND STORMWATER THAT WILL BE DISCHARGED FROM THE SITE.

DISCHARGES OF CONTAMINATED WATERS FROM WASHING AND MAINTAINING VEHICLES OR EQUIPMENT, INCLUDING WASHING AND/OR RINSING WATERS FROM CONTAINERS OR APPLICATORS INVOLVED WITH THE USE OF PAINT, CONCRETE, OR OTHER SUCH MATERIALS, IS PROHIBITED. SUCH POLLUTANTS SHALL BE ADEQUATELY

TREATED AND CANNOT BE DISCHARGED TO WATERS OF THE STATE.

SOLID WASTE

NO SOLID MATERIALS, INCLUDING CONSTRUCTION MATERIALS, ARE ALLOWED TO BE DISCHARGED FROM THE SITE WITH STORMWATER. ALL SOLID WASTE, INCLUDING DISPOSABLE MATERIALS INCIDENTAL TO THE MAJOR CONSTRUCTION ACTIVITIES, MUST BE COLLECTED AND PLACED IN CONTAINERS. THE CONTAINERS SHALL BE EMPTIED WHEN 95% FULL, OR AS NECESSARY, BY A CERTIFIED TRASH DISPOSAL SERVICE AND HAULED AWAY FROM THE SITE. COVERS FOR THE CONTAINERS SHALL BE PROVIDED AS NECESSARY TO MEET STATE AND LOCAL

REQUIREMENTS. CONSTRUCT COVERS AS PRACTICABLE, OR REQUIRED, TO PREVENT STORMWATER CONTACT

AND POLLUTANT DISCHARGES FROM SOLID WASTE RECEPTACLES.

SANITARY FACILIITIES

ALL PERSONNEL INVOLVED WITH CONSTRUCTION ACTIVITIES MUST COMPLY WITH STATE AND LOCAL SANITARY OR SEPTIC SYSTEM REGULATIONS. TEMPORARY SANITARY FACILITIES WILL BE PROVIDED AT THE SITE THROUGHOUT THE CONSTRUCTION PHASE. PORTABLE TOILETS MUST BE KEPT AWAY FROM DRAINAGE COURSES AND LOW AREAS AND SECURELY ANCHORED SUCH THAT THEY WILL NOT BE TIPPED OR KNOCKED OVER.

SECONDARY CONTAINMENT FOR EACH PORTABLE TOILET SHALL BE PROVIDED TO PREVENT THE DISCHARGE OF

SEWAGE ON-SITE.

STOCKPILE MANAGEMENT

MATERIALS RESULTING FROM CLEARING AND GRUBBING EXCAVATION OPERATIONS AND OTHER SUCH SOIL STOCKPILES SHALL BE CONSOLIDATED UP SLOPE FROM ADEQUATE SEDIMENTATION CONTROLS. DIVERSIONS, BERMS, DITCHES, STORAGE BASINS, ETC. WILL BE USED IN ORDER TO DIVERT, RETAIN, OR DETAIN FLOWS OR OTHERWISE LIMIT EXPOSURE TO AND DISCHARGE FROM STOCKPILES. INACTIVE STOCKPILES SHALL BE STABILIZED IN ACCORDANCE WITH THE SPECIFICATION INDICATE IN THE GENERAL PERMIT OR AS SPECIFIED

HEREIN, WHICHEVER IS MORE STRINGENT.

SOIL EROSION AND SEDIMENT CONTROL NOTES TEMPORARY SEEDING

PERMENANT SEEDING

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

SESC NOTES

4"-8" ROCK

1' THICK LAYER 3/4"

TO 1-1/2" CRUSHED

AGGREGATE

(WASHED)

8 X 2" DIA HOLES

CORED INTO EXISTING

STRUCTURE SPACED 8"

ON CENTER

EX. CATCHBASIN

RIM ELEV: 938.46

937.6'

935.6'

934.6' 933.6'

935.2'

NON-WOVEN

GEOTEXTILE

SECTION B-B

PLAN VIEW

CROSS SECTION

HALF PLAN VIEW

CENTERLINE CROSS SECTION

FLOW

FLOW

2'

1'

2'

2:1

2:1

NOTES:

1. SEDIMENT SHALL BE REMOVED WHEN THE SEDIMENT HAS

ACCUMULATED TO ONE-HALF THE

HEIGHT OF THE STONE BERM.

HEIGHT=

0.9' MAX.

END STONE

1' MIN ABOVE

STONE BERM

DESIGN ELEVATION

RIPRAP

COARSE AGGREGATE

WETLAND SLOPE

FES

CENTERLINE

RIPRAP COARSE AGGREGATE

2:1

2:1

FES

ELEV. 939.9

6' x 12' SEDIMENT TRAP

6' x 12' SEDIMENT TRAP

EXPOSE 3' OF EX.

CATCHBASIN TO CONVERT

TO PERFORATED RISER

WITH ROCK JACKET

B

A A

B

PLAN VIEW

4"-8" ROCK

1' THICK LAYER 3/4"

TO 1-1/2" CRUSHED

AGGREGATE

(WASHED)

8 X 2" DIA HOLES

CORED INTO EXISTING

STRUCTURE SPACED 8"

ON CENTER

EX. CATCHBASIN

RIM ELEV: 938.46

937.6'

933.6'

935.2'

NON-WOVEN

GEOTEXTILE

935.6'

934.6'

SECTION A-A

NOTES:

1. TREES SHALL BE IRRIGATED TO PROVIDE AT

LEAST 1 INCH OF WATER APPLIED ONCE A WEEK

USING A SLOW DELIVERY METHOD.

2. NO PRUNING SHALL BE PERFORMED EXCEPT BY

APPROVED ARBORIST.

3. NO EQUIPMENT SHALL OPERATE INSIDE THE

PROTECTIVE FENCING INCLUDING DURING

FENCE INSTALLATION AND REMOVAL.

KEEP OUT

TREE

PROTECTION

AREA

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

SESC DETAILS

NTS

SEDIMENT TRAPS

DETAIL6

NTS

FIBER ROLL

DETAIL6

NTS

ROCK DONUT FES PROTECTION

DETAIL6

NOTES

1. SEDIMENT SHALL BE REMOVED AND TRAP RESTORED TO ITS

ORIGINAL DIMENSIONS WHEN THE SEDIMENT HAS

ACCUMULATED TO 1/2 THE DESIGN DEPTH OF THE TRAP.

REMOVED SEDIMENT SHALL BE DEPOSITED IN AN UPLAND AREA

IN SUCH A MANNER THAT IT WILL NOT ERODE

2. THE STRUCTURE SHALL BE INSPECTED AFTER EACH RAIN EVENT

AND REPAIRS MADE AS NEEDED

3. THE SEDIMENT TRAP SHALL BE REMOVED AND THE AREA

STABILIZED WHEN THE CONTRIBUTORY DRAINAGE AREA HAS

BEEN PROPERLY STABILIZED. THE SWALE SEDIMENT TRAP WILL

BE PROPERLY BACKFILLED AND THE SWALE OR DITCH

RECONSTRUCTED

NTS

PERFORATED RISER WITH ROCK JACKET

DETAIL6

FIBER ROLLS ARE USED TO TRAP SEDIMENT BY FILTERING WATER PASSING THROUGH THE BERM AND ALLOWING WATER TO POND. THEY USE COMPOST INSERTED INTO FLEXIBLE, PERMEABLE TUBE WITH A PNEUMATIC BLOWER

DEVICE OR EQUIVALENT.

MATERIALS SHALL HAVE A PH BETWEEN 5.0-8.0; 100% PASSING A 2" SIEVE AND A MINIMUM OF 70% GREATER THAN THE 3/8" SIEVE; MOISTURE CONTENT IS LESS THAN 60%; MATERIAL SHALL BE RELATIVELY FREE OF INERT OR FOREIGN

MAN-MADE MATERIALS

FIBER ROLLS SHALL BE LAID ON LEVEL CONTOUR. 9” FILTER SOCKS SHALL BE USED ON 20% TO 33% SLOPES. THE

MAXIMUM SLOPE LENGTH ABOVE FILTER SOCK SHOULD BE LIMITED TO 50FT.

INSTALLATION

1. PLACE FIBER ROLL ON A LEVEL LINE ACROSS SLOPES, GENERALLY PARALLEL TO THE BASE OF THE SLOPE.

2. STAKE FIBER ROLL WITH WOODEN STAKES AS SHOWN IN THE PROFILE. STAKES SHOULD BE BURIED 12” MIN IN

SOIL.

3. FIBER ROLLS INTENDED TO BE LEFT AS PERMANENT FILTER OR PART OF THE NATURAL LANDSCAPE, SHALL BE

SEEDED AT THE TIME OF INSTALLATION.

MAINTENANCE

1. INSPECT FIBER ROLLS AFTER EACH SIGNIFICANT RAIN.

2. REMOVE SEDIMENTS COLLECTED AT THE BASE OF THE FIBER ROLL WHEN THEY REACH 1/3 OF THE EXPOSED

HEIGHT OF THE PRACTICE.

3. REPLACE OR REPAIR WITH MORE EFFECTIVE ALTERNATIVE WHERE THE FILTER SOCK DETERIORATES OR FAILS.

4. FOR REMOVAL, DISPERSE THE FIBER ROLL ON SITE WHEN NO LONGER REQUIRED IN SUCH A WAY AS TO

FACILITATE AND NOT OBSTRUCT SEEDINGS.

NOTE:

1. ACCUMULATED SEDIMENT SHALL BE REMOVED WHEN SEDIMENT REACHES

HALF THE OVERALL HEIGHT OF THE FIBER ROLL.

2. HARDWOOD STAKE SPACING SHALL BE PER MANUFACTURER'S

SPECIFICATIONS.

INSTALLATION

1. SEDIMENT TRAPS SHALL BE PLACED ADJACENT TO

THE EXISTING CATCH BASIN

2. EXPOSE 3’ OF THE FACE OF THE EXISTING CATCH

BASIN

3. CORE 8 2-INCH DIAMETER HOLES, 2 VERTICAL ROWS

OF 4 SPACED 8” ON CENTER

4. ROCK SHALL BE PLACED ON NON-WOVEN

GEOTEXTILE FABRIC

5. THE CORE OF THE ROCK JACKET SHALL BE

CONSTRUCTED OF 4”-8” STONE. THE STONE SHALL

BE PLACED TO COMPLETELY COVER THE CORED

HOLES BY AT LEAST 1’ IN ALL DIRECTIONS

6. ¾” TO 1-1/2” CRUSHED AGGREGATE (WASHED)

SHALL BE PLACED ON THE FACE OF THE ROCK

JACKET 12” THICK

7. THE SLOPE OF THE ROCK JACKET SHOULD BE 1:2

OR FLATTER

8.

MAINTENANCE

1. PERFORATED RISER WITH ROCK JACKET SHOULD

BE INSPECTED AFTER EACH RUNOFF EVENT

2. CLOGGED STONE SHOULD BE PERIODICALLY

CLEANED

3. NEEDED REPAIRS SHOULD BE INITIATED

IMMEDIATELY AFTER INSPECTION

4. ACCUMULATED SEDIMENT SHOULD BE

PERIODICALLY REMOVED

NTS

TREE PROTECTION FENCE

DETAIL6

1 REFER TO LANDSCAPING DETAILS FOR TREE PROTECTION

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

WRC SESC DETAILS

NOTE:

INLET FILTERS TO INCLUDE

AREA FOR OVERFLOW

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

MAINTENANCE NOTES

PHASE 1 CONTRACTOR'S MAINTENANCE

RESPONSIBILITIES

WRC MAINTENANCE

RESPONSIBILITIES

PHASE 2 CONTRACTOR'S

MAINTENANCE RESPONSIBILITIES

PHASE 2 CONTRACTOR'S

MAINTENANCE SCHEDULE

During Construction - Contractor's Maintenance Responsibilities Vegetation and Maintenance Guarantee Period - Contractor's

Maintenance Responsibilities

LIMIT OF WORK

EXISTING MAJOR CONTOUR (5')

EXISTING MINOR CONTOUR (1')

PROPOSED MAJOR CONTOUR (5')

PROPOSED MINOR CONTOUR (1')

WETLAND ELEVATION INDICATOR

PROPOSED MAINTENANCE PATH

RIP RAP

UNDERDRAIN CLEANOUT

PROPOSED FLARED END SECTION (FES)

PROPOSED SPOT ELEVATION

APPROX. SPOT ELEVATION: MATCH EXISTING

GRADE

SIDEWALK DRAINAGE TRENCH

861.50

861.50 M.E.

PROPOSED PERFORATED UNDERDRAIN

UUU 4

PROPOSED STORM SEWER))

CATCH BASIN

PROPOSED SOLID UNDERDRAIN

GRASS SWALE

LOW

(SEE HARDSCAPE PLAN)

NEW JOSEPH JONES DRAIN ROW EASMENT

ST

ST

D

D

947948

941942

940941942

94194

943.42 M.E.

943.34 M.E.

942.66 942.66

942.60 942.57

942.35 942.26

942.15

942.14

942.71

942.00

943.17 943.08

943.58943.55

941.83

941.91 942.30

942.37

942.36 942.29

942.19 942.11

942.14

942.10

942.20

942.27

942.42 942.45

942.31 942.34

942.51 942.54

942.44 942.47

942.38 942.41

946.00

941.31 942.09 942.12

942.30 942.33

942.15 942.12

942.16 942.13

942.10 942.15

941.84 941.88

941.29 941.38

941.29 941.36

941.48

941.56

942.27 942.19

942.43 942.36

943.42 943.35

943.00 942.97

942.01 941.98

942.04 942.01

943.59 943.51

946.86

946.78

945.60

945.52

944.40

944.32

941.34 941.45

939.91

939.91

940.00 939.97

939.95

939.95

939.98

939.95

939.95

939.95

939.95

939.95

939.99 939.95943.18

943.25

941.54

942.07 942.14

941.95

942.02

942.08

942.41

941.45

941.86

942.71 M.E.

942.60 M.E.

942.94 M.E.

943.20 M.E.

943.63 M.E.

943.40 M.E.

943.99 M.E.

942.17 942.09

938.99939.00

939.00

941.38

941.28

947.04

947.00

944.99

945.00

949.50

949.91

949.19

942.10

942.74

942.46

PROP. WETLAND

BOTTOM ELEV. = 939.0'

TOP OF WETLAND. = 940.50'

TOP OF BASIN = 941.25'

PROP MAINTENANCE PATH -

SEE HARDSCAPE PLAN

PROPERTY LINE

PROPERTY LINE

TOP OF BASIN ELEVATION = 941.25

TOP OF WETLAND LIMITS: 940.5'

TOP OF WETLAND ELEVATION = 940.40

TOP OF BASIN ELEVATION = 941.25

FES 103

FES 104

939.9

939.9

CB 101 (4' DIA. BEEHIVE)

RIM: 941.25'

CB 102 (4' DIA. BEEHIVE)

RIM: 942.00'

UUUU

UUUU UU

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U U

U

UU

U

UUUU

U

U

U

U

U

U

U

>>UUUUUU

11.25° BEND

45° BEND

45° BEND

11.25° BEND

22.5° BEND

22.5° WYE

11.25° BEND

22.5° BEND

45° BEND

45° BEND

45° BEND

22.5° BEND

CO 301

RIM: 941.75

CO 302

RIM: 941.75

CO 303

RIM: 941.75

UUUUU

U

U

U

45° BEND

45° BEND

11.25° BEND

33 LF 6" D

IA

SO

LID

PVC

0.0%

55 LF 6" D

IA

PER

F PVC

0.0%

28 LF 6" DIA

SOLID PVC @ 0.0%

47 LF 6" DIA

PERF PVC @ 0.0%

30 LF 6" DIA

PERF PVC @ 0.0%

35 LF 6" DIA

PERF PVC @ 0.0%

15 LF 6" DIA

PERF PVC @ 0.0%

20 LF 6" DIA

PERF PVC @ 0.0%

2 X 34 LF 6" DIA

PERF PVC @ 0.0%15 LF 6" DIA

PERF PVC @ 0.0%

8 LF 6" DIA

PERF PVC @ 0.0%

29 LF 6" DIA

SOLID PVC @ 0.0%

25 LF 6" DIA

SOLID PVC @ 0.0%

38 LF 6" DIA

PERF PVC @ 0.0%

30 LF 6" DIA

PERF PVC @ 0.0%

15 LF 6" DIA

PERF PVC @ 0.0%

15 LF 6" DIA

PERF PVC @ 0.0%

15 LF 6" DIA

PERF PVC @ 0.0%

35 LF 6" DIA

SOLID PVC @ 0.0%

26 LF 6" DIA

SOLID PVC @ 0.0%

13 LF 6" DIA

SOLID PVC @ 0.0%

20 LF 6" DIA

PERF PVC @ 0.0%

6" UNDERDRAIN @ 0.0%

PERFORATED

WITHIN LIMITS OF

ROCK ONLY

ROCK DRAINAGE

TO WETLAND

SEE SIDEWALK TRENCH DETAIL

SIDEWALK TRENCH DRAIN

FL: 941.28'

FES 101

FES 102

LOW

LOW

LOW

LOW

LOW

LOW

LOW

LO

W

LOW

LO

W

LO

W

LOW

LOW

LO

W

LOW

LO

W

LO

W

LO

W

LO

W

LO

W

LO

W

NEW JOSEPH JONES DRAIN

RIGHT-OF-WAY ESMT.

NEW JOSEPH JONES DRAIN

RIGHT-OF-WAY ESMT.

NEW JOSEPH JONES DRAIN

RIGHT-OF-WAY ESMT.

ADJUST PUMP FLOATS

HIGH LEVEL ON = 941.00'

LOW LEVEL ON = 940.50'

CONTRACTOR TO REMOVE SOIL

AND DEBRIS FROM EDGE OF

PAVEMENT TO PROMOTE POSITIVE

DRAINAGE TO TRENCH DRAIN

FINISH TURF ELEVATIONS ALONG EXISTING

PAVEMENT SHALL BE HELD TO MINUS 1/2 INCH

BELOW EXISTING PAVEMENT ELEVATION. SLOPE

GRADE TO DIRECT WATER AWARE FROM THE

STREET TO PREVENT PONDING

950.00

944.95 M.E.

946.81 M.E.

947.90 M.E.

950.06 M.E.

950.00

949.91

950.05

953.50 M.E.

953.50 M.E.

LOW

LOW

LO

WLOW

LOW

LO

W

CONTRACTOR TO VERIFY EX. ELEV. IN FIELD

FINISH TURF ELEVATIONS ALONG EXISTING

PAVEMENT SHALL BE HELD TO MINUS 1/2 INCH

BELOW EXISTING PAVEMENT ELEVATION. SLOPE

GRADE TO DIRECT WATER AWARE FROM THE

STREET TO PREVENT PONDING

0 20 40

SCALE IN FEET

N

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

GRADING AND UTILITY PLAN

NOTES

1. NOTIFY THE ENGINEER IN WRITING OF ANY IDENTIFIED

DISCREPANCIES WITHIN THE CONSTRUCTION DOCUMENTS PRIOR

TO THE START OF WORK. CONTRACTOR SHALL VERIFY ALL SITE

CONDITIONS PRIOR TO STARTING WORK. IN ALL CASES WHERE A

CONFLICT MAY OCCUR, THE ENGINEER SHALL BE NOTIFIED AND

WILL INTERPRET THE INTENT OF THE CONTRACT DOCUMENTS.

2. PRIOR TO THE COMMENCEMENT OF WORK, VERIFY LOCATIONS AND

DEPTHS OF ALL UNDERGROUND UTILITIES THAT MAY BE AFFECTED

BY CONSTRUCTION AND TAKE RESPONSIBILITY FOR DAMAGES TO

SUCH UTILITIES CAUSED AS A RESULT OF CONSTRUCTION.

3. SECURE ALL NECESSARY PERMITS AND NOTIFY ALL UTILITY

COMPANIES WITH UTILITIES ON THE SITE PRIOR TO THE

CONSTRUCTION OF THE PROJECT. ADHERE TO ALL APPLICABLE

LOCAL, STATE AND FEDERAL LAWS OR REGULATIONS PERTAINING

TO THE PROJECT.

4. USE DIMENSIONS SHOWN ON DRAWINGS FOR LAYOUT OF THE

WORK. DO NOT USE SCALE DIMENSIONS FROM PLANS, SECTIONS

OR DETAILS ON THE DRAWINGS.

5. TAKE NOTE OF ALL GRADING AND DRAINAGE WAYS AND MAINTAIN

THESE DRAIN WAYS FLOWS FREE OF OBSTRUCTIONS.

6. ALL CONSTRUCTION SHALL CONFORM TO ALL APPLICABLE CODES,

REGULATIONS, AND ORDINANCES PER CITY OF PONTIAC, MICHIGAN

PUBLIC WORKS STANDARDS AND SPECIFICATIONS.

7. CONTRACTOR TO MAINTAIN POSITIVE DRAINAGE TO WETLAND

FROM EXISTING PAVEMENT AREA AFTER REMOVING EXCESS

SEDIMENT AND VEGETATION

8. FINISH TURF ELEVATIONS ALONG EXISTING PAVEMENT SHALL BE

HELD TO MINUS 1/2 INCH BELOW EXISTING PAVEMENT ELEVATION.

SLOPE GRADE TO DIRECT WATER AWARE FROM THE STREET TO

PREVENT PONDING

9. SEE SHEET 10: INFRASTRUCTURE PROFILES FOR STORM SEWER

PROFILES.

10. SEE SHEET 12 FOR ADDITIONAL UTILITY AND GRADING NOTES.

11. CONTRACTOR TO REMOVE SOIL AND DEBRIS FROM EDGE OF

PAVEMENT TO PROMOTE POSITIVE DRAINAGE TO THE TRENCH

TRAIN

GRADING VIEW A

MATCHLINE - GRADING VIEW A

MATCHLINE - GRADING VIEW A

FUTURE WORK - NOT IN CONTRACT

1FUTURE WORK - NOT IN CONTRACT

EL

EV

AT

IO

N (F

EE

T)

EL

EV

AT

IO

N (F

EE

T)

DISTANCE (FEET)

0+00 0+78

FE

S

IN

V

EL

.0

15' OF 12" DIA RCP @ 3.14%

PROPOSED GRADE

EXISTING GRADE

C B

4' D

IA

E

.J .I.

W C

O

VE

R C

AT

C

H B

AS

IN

R

IM

E

LE

V

1.

EX

. 1 2"

W

IN

V O

U T

±9

.9

2' V

.I.

F.

"R

C P

N

IN

V

IN

.6

0' 6"

P

VC

N E

IN

V

IN

.5 0'

6" P

VC

N

E

IN

V

IN

.5

0'

2 X 6" DIA PVC UNDERDRAIN

XINV EL: 937.50'

EX 12" DIA RCP

EX

. P

U M

P

ST

AT

IO

N W

ET

W

EL

L

R

IM

E

LE

V

2.

SU

M P

EL

EV

.8

" E

IN

V

IN

.2

9' 7"

S W

IN

V

O U

T

0.

EX 6" DIA FOREMAIN

6" MIN. BEDDING (SEE DETAIL)

EG = 940.70

CONNECT TO EXISTING

STORM DRAIN. INVERT

ELEVATION TO BE VERIFIED

IN FIELD (V.I.F)

SEE DETAIL 6 ON SHEET 12 FOR

FLARED END SECTION AND

LIMITS OF RIP-RAP ROCK

4:1

EL

EV

AT

IO

N (F

EE

T)

EL

EV

AT

IO

N (F

EE

T)

DISTANCE (FEET)

0+00 0+55

C B

4' D

IA

E

.J .I.

W C

O

VE

R C

AT

C

H

BA

SI

N

R

IM

E

LE

V

2.

" E

IN

V O

U T

9.

45' OF 12" DIA RCP @ 1.0%

FE

S

IN

V

EL

.0

0PROPOSED GRADE

EXISTING GRADE

EG = 942.95

6" MIN. BEDDING (SEE DETAIL)

SEE DETAIL 6 ON SHEET 12 FOR

FLARED END SECTION AND

LIMITS OF RIP-RAP ROCK

4:1

EL

EV

AT

IO

N (F

EE

T)

EL

EV

AT

IO

N (F

EE

T)

DISTANCE (FEET)

0+00 0+40

30' OF 12" DIA RCP @ 0.0%

FE

S

IN

V

EL

.0

FE

S

IN

V

EL

.0

PROPOSED GRADE

EXISTING GRADE

6" MIN. BEDDING (SEE DETAIL)

SEE DETAIL 6 ON SHEET 12 FOR

FLARED END SECTION AND

LIMITS OF RIP-RAP ROCK

SEE DETAIL 6 ON SHEET 12 FOR

FLARED END SECTION AND

LIMITS OF RIP-RAP ROCK

4:14:1

0 5 10

SCALE IN FEET

N

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

INFRASTRUCTURE PROFILES

FES 101 TO EX. PUMP STATION

HORIZONTAL SCALE: 1" = 5'

VERTICAL SCALE: 1" = 5'

FES 103 TO FES 104

HORIZONTAL SCALE: 1" = 5'

VERTICAL SCALE: 1" = 5'

CB 102 TO FES 102

HORIZONTAL SCALE: 1" = 5'

VERTICAL SCALE: 1" = 5'

CB 101 SECTION VIEW

LIMITS OF DISTURBANCE

DRAINAGE AREA BOUNDARY

HYDRAULIC SOIL GROUP (HSG) C

HYDRAULIC SOIL GROUP (HSG) A/D

LOW

PROP. STORMWATER TREATMENT

WETLAND

LOW

LOW

LOW

LO

W

LO

W

LOW

LO

W

LOW

LOW

LO

W

LO

W

LO

W

ST

947948

941942 943944

941942

940941942

94194

0 20 40

SCALE IN FEET

N

NOTES

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

SITE LAYOUT AND DRAINAGE MAP

STORMWATER MANAGEMENT SUMMARY

DRAINAGE AREA AND RUNOFF COEFFICIENT

IMPERVIOUS AREA

HSG C AREA = 2.6 ACRES C VALUE = 0.25

HSG A/D = 5.8 ACRES C VALUE = 0.30

IMPERVIOUS AREA = 1.0 ACRES C VALUE = 0.95

TOTAL AREA = 9.4 ACRES COMPOSITE C VALUE = 0.36

WRC VOLUME CALCULATIONS

CHANNEL PROTECTION VOLUME CONTROL (CPVC)

EQUATION: VCPR = 4,716 X C X A

WHERE

C = POST-DEVELOPMENT RUN-OFF COEFFICIENT

A = TOTAL SITE AREA

CALCULATION

VCPR = 4,716 X 0.36 X 9.4 = 15,969 CUBIC FEET

CHANNEL PROTECTION RATE CONTROL (CPRC)

EQUATION: VED = 6,897 X C X A

WHERE

C = POST-DEVELOPMENT RUN-OFF COEFFICIENT

A = TOTAL SITE AREA

CALCULATION

VED = 6,897 X 0.36 X 9.4 = 23,339 CUBIC FEET

100-YEAR DETENTION VOLUME

EQUATION: V100D = (V100R X R) - VCPR

WHERE

V100R = POST-DEVELOPMENT 100-YEAR RUNOFF = 18,985 x C X A

18,985 X 0.36 X 9.4 = 62,245 CUBIC FEET

VCPR = CHANNEL PROTECTION VOLUME CONTROL

R = STORAGE CURVE FACTOR = (0.206 - 0.15x ln(Q100P / Q100IN)

WHERE

Q100P = ALLOWABLE 100-YEAR POST DEVELOPMENT PEAK FLOW = QVR X A

WHERE

QVR = VARIABLE RELEASE RATE (CFS/ACRE) = 1.1055 - 0.206 x ln (A)

QVR = 1.1055 - 0.206 X ln (9.4) = 0.644 CFS/ACRE

Q100P = 0.644 X 9.4 = 6.05 CUBIC FEET PER SECOND (CFS)

Q100IN = 100-YEAR POST DEVELOPMENT PEAK INFLOW RATE = I100 X C X A

WHERE I100 = 100-YEAR PEAK RAINFALL INTENSITY = 12.73 IN/HR

12.73 X 0.36 X 9.4 = 43.07 CFS

R = (0.206 - 0.15x ln(6.05 / 43.07) = 0.50

V100D = (62,245 X 0.5) - 15,969 = 16,175 CUBIC FEET < VED

V100D = (62,245 x 0.5) = 32,144 CUBIC FEET

100-YEAR DETENTION VOLUME DRAWDOWN

CALCULATION

DESIGN PUMP RATE = 460 GPM = 1.025 CFS

DRAWDOWN TIME = 32,144 CF / 1.025 CFS =

31,360 SECONDS = 8.71 HOURS

STAGE STORAGE TABLE

NATIVE SOIL

WETLAND LIMITS = 940.50'

EX 6" PRESSURE PIPE TO EX 12"

SEWER ALONG E. RUNDELL ST.

EXISTING PUMP STATION

ADJUST PUMP FLOATS

HIGH LEVEL ON = 941.00'

LOW LEVEL ON = 940.50'

4:1

MAX. BOTTOM = 939.00'

TOP OF ROCK = 939.9'

18" SOIL MEDIA MIX EX 12" SEWER EX 6" SEWER

CB 101

RIM ELEV. = 941.25'

WOVEN GEOTEXTILE FABRIC

WETLAND PLANTING ZONE

6" PERF UNDERDRAIN @ 0.0%

COURSE AGGREGATE

ASTM NO.57

TOP OF BASIN = 941.25'4:1

MAX.

FES 101

12" RCP SEWER

(2) 6" x 6" PVC CLEANOUT TEE W/ 6" SCREW CAP

TOP ELEV. = 938.5'

1.5% MAX

PEDESTRIAN AND MAINTENANCE PATHS

(SEE HARDSPACING PLAN)

CONNECT TO EX. 12 SEWER

3" BASIN STONE

(SEE LANDSCAPING PLANS)

SECTION B-B

1.

5"

6" MDOT CLASS II

GRAVEL DRAINAGE

SLOPED TO DRAIN

TO WETLAND2% MIN.

STREET

DRAINAGE GRAVEL

M

IN

6"

CONCRETE PAD

18" MIN.

M

AT

C H

E

XI

ST

IN

G C

U R

B

AN

D G

U

TT

ER

FRAME

6" SUBBASE, TYP. EACH

SIDE OF TRENCH DRAIN

6" CONCRETE

EXPANSION

JOINT TYP.,

IF ABUTTING

PAVEMENT

PLAN VIEW

ST

R

EE

T

TOP OF INLET WALL

FLOW

METAL TRENCH

DRAIN COVER

6" TY

P.

AGGREGATE OR CONC. PATH

STORMWATER

FACILITY

METAL TRENCH DRAIN

GRATE TO MATCH SLOPE

OF ADJACENT SIDEWALK

SECTION A-A

" M

IN

6" M

IN

TOP OF INLET WALL

6" MDOT CLASS II

6"

FLOW FLOW

6"

6"

3" O.C., TYP.

A

A

B

6"

6"TY

P.

941.28 941.38

6" MIN.

GRAVEL DRAINAGE

SLOPED TO DRAIN

TO WETLAND

ASTM NO. 57 STONE

B

GENERAL NOTES

1. TYPE AND CLASS OF PIPE SHALL BE AS SPECIFIED ON PLANS.

2. CLASS '"B'" BEDDING SHALL BE USED THROUGHOUT, UNLESS OTHERWISE SPECIFIED ON THE

PLAN.

3. ALL END SECTIONS 18" AND LARGER SHALL BE PROVIDED WITH A BAR SCREEN UNLESS

OTHERWISE APPROVED.

4. STANDARD RIP-RAP SHALL BE 8"-15" FRAGMENTED ROCK, HEAVY RIP-RAP SHALL BE 16"-24"

FRAGMENTED ROCK. (NO BROKEN CONCRETE)

5. MANHOLE REQUIREMENTS:

5.1. ALL NEW CATCH BASINS, INLETS, AND MANHOLES ARE TO BE MANUFACTURED TO ASTM

C-478 SPECIFICATIONS.

5.2. ALL NEW CATCH BASINS, INLETS, AND MANHOLES SHALL HAVE WRC APPROVED

FLEXIBLE, WATERTIGHT SEALS WHERE PIPES PASS THROUGH WALLS. MANHOLES SHALL

BE OF PRECAST SECTIONS WITH MODIFIED GROOVE TONGUE AND RUBBER GASKET

TYPE JOINTS SECTIONS SHALL BE WRC APPROVED MODIFIED ECCENTRIC CONE TYPE.

5.3. TAPS THROUGH MANHOLE JOINTS OR CONE SECTIONS ARE PROHIBITED UNLESS

OTHERWISE APPROVED.

5.4. MANHOLE STEPS TO BE PLASTIC COATED STEEL MEETING THE REQUIREMENTS IN ASTM

D 2146, TYPE II, GRADE 49108, MA. INDUSTRIES P.S.I. POLYPROPYLENE, (OR APPROVED

EQUAL). STEPS TO BE INSTALLED DURING MANHOLE MANUFACTURE. PLACE AT 16

CENTERS 45 FROM CENTERLINE OF SEWER.

5.5. CONE SECTION WITH MODIFIED GROOVE TONGUE JOINTS AND WITH STUD INSERTS

CAST IN PLACE. TOP TO HAVE FLUSH SURFACE.

5.6. ASTM C-478 RISER SECTION WITH MODIFIED GROOVE TONGUE JOINTS.

5.7. RES-SEAL, LINK-SEAL, PRESS WEDGE LI, OR KOR-N-SEAL BOOT (WITH STAINLESS STEEL

KORBAND) FLEXIBLE RUBBER MANHOLE JOINTS. (OR APPROVED EQUAL).

5.8. THE INSIDE JOINTS OF MANHOLES, CATCH BASINS, AND PIPE SIZES OVER 42" AND

LARGER IN DIAMETER SHALL BE POINTED UP WITH MORTAR UPON COMPLETION OF

BACKFILLING.

6. CONCRETE PIPE REINFORCEMENTS:

6.1. CONCRETE PIPE TO BE PER ASTM C76 STANDARDS.

6.2. IT WILL BE REQUIRED TO TV ALL PIPE 30 DAYS AFTER INSTALLATION

6.3. THE CONTRACTOR SHALL PROVIDE REINFORCED CONCRETE PIPE AS SPECIFIED ON THE

PLANS.

6.4. ALL REINFORCED CONCRETE PIPE SHALL HAVE MODIFIED GROOVED TONGUE JOINTS

WITH O-RING TYPE RUBBER GASKET, PER ASTM SPECIFICATIONS C443.

6.5. THE INSIDE JOINTS OF MANHOLES, CATCH BASINS, AND PIPE SIZES OVER 42" AND

LARGER IN DIAMETER SHALL BE POINTED UP WITH MORTAR UPON COMPLETION OF

BACKFILLING.

7. RESTORATION REQUIREMENTS:

7.1. ALL DISTURBED AREA WITHIN THE COUNTY DRAIN RIGHT-OF-WAY SHALL BE RESTORED

AS FOLLOWS:

7.2. UNDER ROADS, SIDEWALKS, DRIVEWAYS AND PARKING AREAS, BACKFILL MATERIAL

SHALL BE PLACED LOOSELY INTO TRENCHES IN SIX (6) INCH LAYERS WITH EACH LAYER

COMPACTED TO NOT LESS THAN 95% OF MAXIMUM DRY DENSITY AS DETERMINED BY

THE ASTM D 1557 COMPACTION STANDARD (MODIFIED PROCTOR COMPACTION TEST).

ALL OTHER AREAS SHALL HAVE EACH LAYER COMPACTED TO NOT LESS THAN 90% OF

MAXIMUM DRY DENSITY.

7.3. FINISH SUBGRADE

7.4. TOPSOIL ACCEPTABLE TO THE ENGINEER TO ATTAIN FINISHED GRADE. TOPSOIL MUST

NOT BE CONTAMINATED AND MAY NOT BE A MIXTURE OF NATURAL UNDERLYING SOILS,

SUBBASE MATERIALS, OR OTHER MATERIALS. IT MUST CONSIST OF NATURAL LOAM,

SANDY LOAM, SILTY LOAM OR CLAY LOAM HUMUS-BEARING SOIL ADAPTED TO THE

SUSTENANCE OF PLANT LIFE. TOPSOIL MUST BE NEITHER EXCESSIVELY ACIDIC NOR

EXCESSIVELY ALKALINE. IT MUST BE OF MINERAL ORIGIN, EXCLUSIVE OF ANY PEAT OR

MUCK.

7.5. APPLY SEED AND FERTILIZER AS FOLLOWS:*

* SOD IS REQUIRED IN MAINTAINED LAWN AREAS. REFER TO WRC GENERAL

SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS AND INFORMATION.

- APPLY STRAW OR MARSH HAY MULCH IN AN AIR-DRY CONDITION TO ALL SEEDED

AREAS OVER THE SURFACE TO A UNIFORM THICKNESS AT 2 TONS/ACRE.

- MULCH SHALL BE ANCHORED IN PLACE WITH BIODEGRADABLE NETTING, NOT

LARGER THAN 1½" BY 2" NOR SMALLER THAN ½" BY ½".

- THE CONTRACTOR SHALL BE RESPONSIBLE TO ENSURE THE GROWTH OF ALL

SEEDED AREAS, AND SHALL RE-SEED AS NECESSARY TO ACCOMPLISH THIS.

8. THE STORM DRAIN NOTES AND DETAILS SHEET SHALL BE A SUPPLEMENT TO WRC

STANDARDS AND SPECIFICATIONS, WHICH ARE AVAILABLE ON THE WRC WEBSITE

(WWW.OAKGOV.COM/WATER).

LOCATION SEEDING REQUIREMENTS FERTILIZER REQUIREMENT

SLOPE AND DITCH, BANKS,

ETC.

M.D.O.T. "ROADSIDE MIX"

TURF SEED MIXTURE TGM

(10% KENTUCKY BLUE, 20%

PERENNIAL RYE, 30% HARD

FESCUE, 40% CREEPING

RED FESCUE APPLIED AT

220 LB/ACRE

M.D.O.T. SEEDING AND

SODDING FERTILIZERS,

CLASS A

OTHER AREAS M.D.O.T. "ROADSIDE MIX"

TURF SEED MIXTURE THM

(30% KENTUCKY BLUE, 20%

PERENNIAL RYE, 50%

CREEPING RED FESCUE)

APPLIED AT 220 LB/ACRE

M.D.O.T. SEEDING AND

SODDING FERTILIZERS,

CLASS A

6" 3/8" DIA PERFORATIONS 6" CENTER TO CENTER

120°

PIPE DETAIL PERFORATION PATTERN

(ALTERNATING)

GRASS

SWALE

3"

8" MIN. COVER

4" MIN.

15" MIN.

CROSS SECTION

3" MIN.

CLEANOUT DETAIL

6" SOLID PVC

UNDERDRAIN

6" SOLID PVC

UNDERDRAIN

1'

12" RCP TO FES 101

12" RCP TO PUMP

STATION

6" X 6" TEE

WITH SCREW CAP

6" X 6" TEE

WITH SCREW CAP

6"

6"

CB 101 TOP

DOWN VIEW

6" X 6" TEE WITH SCREWCAP

SCREW CAP

NTS

TYPICAL WETLAND SECTION

DETAIL12

F

E

D

C

2 3

B

A

1 2 3

4 5 6 7 8

54 6 7 8

F

E

D

C

B

A

PERRY PARK GREEN INFRASTRUCTURE IMPROVEMENTS

301 EDISON ST, PONTIAC MI 48342-1425

PROJECT:

SITE:

TITLE:

APPROVED BY:

REVIEWED BY: DRAWING NO.:

OF

DRAWN BY:

DESIGN BY:

CHECKED BY: FILE:

PROJECT NO.:

DATE: JULY 29, 2025

CSWR3013

DATEREV APPDESCRIPTION DRN

3057 NORTH ROCKWELL STREET

CHICAGO, IL 60618

TELEPHONE: 312.809.9707

MKSKSTUDIOS.COM

THIS DRAWING MAY NOT BE ISSUED

FOR PROJECT TENDER OR

CONSTRUCTION, UNLESS SEALED.

DATE

CJH

WF

RH

RH

EC

R

Know what's below.

Call before you dig.

2100 COMMONWEALTH BLVD, SUITE 100

ANN ARBOR, MI 48105

TELEPHONE: 586.744.9003

05/09/2025 ISSUED FOR BID ECCJH

07/29/2025 ISSUED FOR RE-BID ECCJH

UTILITY DETAILS

NTS

SIDEWALK TRENCH DRAIN

DETAIL12

N…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .